Auditing Public private partnership - PowerPoint PPT Presentation

About This Presentation
Title:

Auditing Public private partnership

Description:

... viability and advantages of PPP over traditional public execution of the project. (HSL no delays 99% private sector, versus 97% public sector) ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 16
Provided by: JeDi7
Category:

less

Transcript and Presenter's Notes

Title: Auditing Public private partnership


1
Auditing Public private partnership
  • H.B. Kramer NCA

2
PPP in the Netherlands
  • many different forms
  • bad experiences in the past
  • no lessons learned from other countries (e.g.
    USA)
  • not always auditing by NCA allowed
  • some big DBFM contracts now

3
Focus audit
  • Different from NAO
  • NCA focus on the policy of using PPP
    Decisionmaking, added value, transparancy, costs,
    supervision, information to parliament, effects
  • NAO management, good practices, coördination of
    activities, personnel

4
Focus audit
  • different focus different products
  • explanation legal setting different, need for
    consensus with auditee

5
High Speed train infraprovider (HSL)
  • casus part of the European network, track
    Rotterdam-Belgium.
  • DBFM-contract, new instruments
  • - Public private comparator
  • - Public sector comparator

6
HSL
  • First question why PPP?
  • Who decides? On what information? Is that
    information correct?
  • What are the advantages of a PPP in this specific
    case? What is the added value cheaper? better
    public performance? public-private chemistry?

7
Public private comparator
  • Quick scan examines financial viability and
    advantages of PPP over traditional public
    execution of the project.
  • (HSL no delays 99 private sector, versus 97
    public sector)
  • Interesting point if PPP is more expensive but
    gives better performance that is an important
    element in decisionmaking.

8
Public Private Comparator (PPC)
  • Reliability of the PPC is not very high
  • Quick scan but go - no go was / (is always?)
    made on the basis of the PPC.
  • Auditing it try to find out on what facts it is
    based, who made it, were there drafts? Always
    look for authentic, original material, gather it
    yourself.
  • Look for information on added value and its
    influence on the decisionmaking.

9
Public Sector Comparator (PSC)
  • Benchmark idea OK
  • Complex calculation about costs to make by the
    State over 30 years including Designing,
    Building, Financing and Maintaining, including
    (all) the risks of the HSL
  • All brought back to one figure
  • Idea if tenders are higher NO PPP!!!

10
Auditing the PSC
  • there should be only one PSC
  • what is included? what not?
  • no adjusting, scope change or extra bandwith
    of risks should be added
  • highly manipulative if biddings are higher look
    careful to changes made in the PSC

11
Audit findings HSL PPP
  • decision for PPP was made even before the PPC
  • use of PPC and PSC only to convince parliament
    (no way back possible without high costs)
  • the outcome of the PPC and PSC had to be positive

12
What went wrong with the PSC
  • biddings were 50-80 higher
  • three new/adjusted PSCs were made scope change,
    extra risks added, risk-changes, bandwith added
    extra age, so that in the end PSC was 5 higher
    than lowest bidder.
  • 2/3 of the PSC are calculated risks

13
What went wrong with the PSC (2)
  • still uncomparable age of quality delivered was
    different
  • so called sunk costs not added to bidding so
    advantage was far less than 5-10, high learning
    costs
  • shift from costs from rails to foundation may
    cost far more
  • NCA 1.2 advantage utmost

14
Other remarks
  • risks on integrity
  • contract (English contract under Dutch legal
    system), adjusting contract impossible
  • risks remain high for the State (risk allocation
    essential)
  • information parliament vs confidentiality
    negotiations with bidders, how to keep personnel
    of good quality
  • legal risks depend on object (railway track),
    discussion on quality one bolt multiplies
    enormous.

15
Conclusion
  • if the added value is calculated in money beware
    motives maybe to buy now and pay later. Influence
    of parliament will be low in the future. Focus
    audit on calculation.
  • if the added value is in terms of public service
    political decision. Focus audit on implementation
  • Always look at risk allocation
Write a Comment
User Comments (0)
About PowerShow.com