Title: King Fahd University of Petroleum and Minerals
1King Fahd University of Petroleum and Minerals
- Department of Construction Engineering and
Management - Value Engineering
- CEM512
- Term Project
- VE in Family Trip
- Supervised by Dr. Sadi Assaf
- Prepared by Fahad Al-Azzaz
2Content
- Introduction
- VE Job Plan
- QA
31- Introduction
- The idea of this VE term project is a common
issue faced on yearly by family members here in
KSA families been working the whole year, and a
month or two before this leave they start
thinking where to go this year. Family members
are 4 persons. - Our project here in is to find the VE for the
best family trip package for a Saudi family
never traveled outside the kingdom or even
inside, and planning to enjoy their vacation,
and this is their first one. - cont.
4Cont.
- Note
- Facts were collected from the market.
- Its a simple example, as such idea is a common
practice, and it can be seen that the traveling
agencies are competing hardly to get more
travelers promoting their items using
alternative attractive promotions and offers. - This VE is applicable to Eastern Province Area
market.
52- VE Job Plan
- 2.1- Information Phase
- 2.2- Functional Phase
- 2.3- Creative Phase
- 2.4- Evaluation Phase
- 2.5- Development Phase
- 2.6- Audit Phase
-
62.1- Information Phase
- Project Information and Familys Item Criteria
- As mentioned before, the project or the task of
the VE is to select the best traveling package to
be purchased for the familys annual leave. As
such selection should make sure it achieves the
least traveling cost and covering its purpose /
desired function perfectly. - The main proposal was to have a 2 weeks trip to
Abha in Saudi Arabia. Since the family never been
outside the Eastern Province. - cont.
7Cont.
- The familys criteria for the package is
- a- The package shouldnt exceeds the assigned
budget (SR 25,000). - b- The package to be 2 weeks.
- c- Flight duration is not more than 4 hours(/-
20 minutes). - d- Family Entertainment.
- e- Historical places to be visited.
- f- Natural Scene.
- e- Weather should be nice enough.
- cont.
8Cont.
- consultation concerning the package from
- 1- Friends traveling with their families for the
last five years. - 2- Traveling agencies.
- Cont.
9Cont.
- Performance Criteria
- Objective or Required Criteria
- 1- To meet the criteria listed under project
criteria and mainly that related to budget,
entertainment, flight duration. - 2- Reasonable weather and natural scene that
make the trip enjoyable. -
- Goals, Desired Criteria or Features
- 1- relaxation.
- 2- reasonable expenditure.
- cont.
10Cont.
Price Item
3000 Tickets
9800 Accommodation
7000 Daily Expenses
19800 Total
- Original Proposal Cost Data
- the cost for a two weeks trip with all
expenditures turned to be SR 19,800.
112.2- Functional Phase
- Functional Worksheet
-
-
-
cont.
Why? Function How?
Package meet the Budget To serve the desired function /enjoy annual leave To have the proper decision
W/ Low flight duration Meet the proper criteria Meeting the set out criteria of the project
W/ Low Expenditures Shopping Entertainment Meeting the set out criteria of the project
12Cont.
- Identify Item Function
- What does it do?
- verb noun
- Enjoy Vacation
- Visit historical Places
- Entertain Family
- what must it do?
- verb noun
- Enjoy Vacation
- Visit historical Places
- Entertain Family
-
132.3- Creative Phase
- Generate Ideas
- Here below are alternative ideas proposed to be
studied and evaluated to choose the best
alternative - 1- Dubai-UAE
- 2- Beirut-Lebanon
- 3- Cairo-Egypt
- 4- Ankara-Turkey
- 5- Salalah-Oman
- cont.
14Cont.
No. Car Brand Name / Particular Cost / Package Other Expenditures Total
01 Dubai-UAE SR3,600 17,200 SR20,800
02 Beirut-Lebanon SR6,000 19,000 SR25,000
03 Cairo-Egypt SR6,000 12,875 SR18,875
04 Ankara-Turkey SR8,800 14,450 SR23,250
05 Salalah-Oman SR4,000 13,125 SR17,125
06 Abha-KSA SR3,000 16,800 SR19,800
Cont.
152.4- Evaluation Phase
- Feasibility Ranking
- Expenditure
- Flight Duration
- Entertainment
- Weather
- Historical Places
- Natural Scene
-
-
Total Rank - Abha 3 3 8 6
10 9 39 5 - Dubai 3 4 4 9
8 7 35 5 - Beirut 8 9 8 7 6
5 43 4 - Cairo 7 10 6 10
7 9 49 1 - Ankara 9 10 8 7
5 9 48 2 - Salalah 9 8 10 5
8 7 47 3 - Cont.
16Idea Comparison
Idea Advantages Disadvantages
Dubai Short flight duration, family entertainment No historical places to visit
Beirut Medium flight duration, family entertainment, historical places, nice weather Daily expenses
Cairo Medium flight duration, family entertainment, historical places Weather is hot
Ankara Family entertainment, historical places, nice weather Long flight duration
Salalah historical places, nice weather, Short flight duration Entertainment
.
17Cont.
- Determining Weights for Evaluation
- Goals, Desired Criteria, Functions and Features
- Raw Score Assigned Weight
- A- Expenditures 8 10
- B- Flight Duration 6 8
- C- Entertainment 5 4
- D- Weather 3 3
- E- Historical Places 2 2
- F- Natural Scene 1 1
- Scoring Matrix
- B C D E F
- A A/B A/C A-3 A-1 A-2
- B B-1 B/D B-2 B-1
- C C/D C-3 C-1
- D D/E D/F E E-1
- How Important
18Cont.
- Evaluation Matrix
- Natural Scenes
- Historical Places
- Weather
- Entertainment
- Flight Duration
- Expenditure
-
-
-
Total Rank - Abha 2 5 2 4
1 3 85 5 - Dubai 2 5 4 1
1 1 82 6 - Beirut 3 4 5 5
4 4 109 3 - Cairo 4 4 4 3
5 3 110 2 - Ankara 5 2 5 5
5 4 115 1 - Salalah 3 3 2 4
4 5 87 4 -
10 8 4 3 2 1
19Cont.
- Savings
- on this study it shows that there was no saving,
but the main faunction has been satisfied and
maximized with an additional amount of money - Item Initial Cost
- 1- Abha SR19,800
- 2- Ankara SR23,250
- Addition in initial cost SR3,450
- 17 Addition
- Life Cycle Cost Results
- Expenditures were assumed to be considered as
life cycle cost in this trip - Idea Expenditures
- 1- Abha SR16,800
- 2- Ankara SR14,450
- Saving in Life Cost Cycle
SR2,350 13.98reduction -
- cont.
202.5- Development Phase
- Value Study Summary (Ranked-1 Proposal)
- The ranked 1 proposal has alternative benefits
superior on the others which lead to the choosing
of this proposal and such profits are as follows - 1- Entertainment is more.
- 2- Expenditure is decreasing, so in case the
family want to extend the vacation it will not
cost more money. - 3- Historical Places visited are old and
multi-cultural. - 4- Natural Scenes are better than those in Abha.
-
- For that, the proposed ranked-1 idea will meet
the project criteria although extra money to be
added but the main function were maximized.
-
- cont.
21Cont.
- Implementation Phase
- Alternative questions to be implemented to
ensure VE implementation properly. These
questions are as follows - 1- How should it be implemented?
- The proposed case to be presented to the family
members for their review and approval. - 2- What should be changed and in what sequence?
- The proposed idea after being presented and
explained in comparison to other ideas and on
the basis of actual facts and gathered
information from friends, the package should be
changed to Ankara and made all required
reservations -
cont.
22Cont.
- 3- Who should do it?
- The traveling agency should change package to
Ankara. - 4- How long should it take to implement the
proposal? - it is only one day visit to the agency office.
- 5- Any deadline required
- as earlier as possible since seats are
available.
232.6- Audit Phase
- The audit phase will be taking place within the
family members to go ahead and purchase the
package and a final project report to be
submitted to the father.
24Thank youQA