Title: HM


1
HME StandardizationExCommWorking Group One
23 OCTOBER 2006
2
Mission
  • Establish standardization mechanisms and
    incentives to be used during acquisition phase
  • Promote HME standardization for the acquisition
    of new systems during new construction
  • Apply HME policy, processes, and approaches in
    new construction contracts

3
HME Standardization WG 1 Members New
Construction
4
30 120 Day Update
  • Completed items last 30 days
  • Collected SY Process Maps for new construction
    equipment procurement
  • Collected internal NG standardization procedures
    and distributed to senior Governance Board
    member.
  • Transitioned co-chair position.
  • Identified spec language being invoked on new
    construction ship contracts.
  • Established key points of contact at shipyards
    and NAVICP to further investigate standard
    procurement of commodities.
  • Next 120 days
  • Refine action plan to engage S/Ys, NAVICP, new
    construction PM reps.
  • Conduct HME ExComm awareness meeting with new
    construction SYs
  • Determine metrics and goals for standardization
    within DDG-1000 and CVN-21 programs.
  • Conduct review with NAVICP, Shipyards, and new
    construction PMs to investigate use of supply
    system for commodity buys.
  • Formalize NAVSEA C clause to be used in new
    construction contracts.
  • Develop award fee criteria for new construction
    contracts.

5
HME Standardization WG 1 Members Action
Plan
6
Standardization at the Shipbuilders
  • NGSS
  • For the LHD 8 Program, a standardization program
    was established for equipment designers which
    requires them to perform a standardization review
    prior to vendor selection
  • Requires a review of
  • Hull, Mechanical and Electrical Equipment Data
    Research System (HEDRS)
  • Supportable Equipment Lists (SELs)
  • Ship-specific Allowance Parts Lists (APLs) and
    Coordinated Shipboard Allowance Lists (COSALs)

Analyze Designand Performance Requirements
Develop Procurement Spec and TPR/SOW
Accomplish Logistic Standardization Reviews
Forward to Potential Bidders
Receive/Review Supplier Proposals, Complete
Logistics Supplier Evaluations
Determine Equipment/ Component and Supplier
Selection
Develop Purchase Order Ensure Standardization
Requirements
Transmit to Supplier
7
Standardization as a Specification
  • For the DDG 1000 Program, Standardization has
    been contractually mandated within the Design,
    Build and Process Specification (DBPS 080
    Support System)
  • The requirement to have standardization for DDG
    1000 has been invoked since the initial stages of
    the program
  • Language is common with spec language on CVN-21
    contract

8
Promoting Standardization through Class Common
Equipment
  • DDG 1000 has a CCE list of 119 items
  • Ensures that equipment will be common at both
    shipyards for these items
  • List includes items known to be standardization
    offenders
  • Pumps
  • Motors
  • Valves
  • Load centers and switchboards
  • Includes items unique to DDG 1000
  • Propellers
  • Advanced Degaussing
  • Steering Gear
  • Includes high cost items
  • LV and HV Ships Service power
  • Auxiliary Gas Turbine Generator

Design Requirements, COTS and New Technology
Drives the Use of Some Non-standard Parts
9
DDG 1000 Bridge to Other Platforms
  • CG(X)
  • Will re-use much of the same equipment and weapon
    systems
  • Will likely be built by the same yards so process
    improvements, tools and catalogues will be
    re-used
  • CVN 21
  • Using same screening techniques and tools
  • Re-use of DDG 1000 Dual Band Radar and other
    elements of mission system software
  • Advocating intra ship commonality
  • Advocating intra carrier commonality
  • Advocating intra fleet commonality

10
CVN 21 Standardization
  • Goal Reduce TOC
  • Key features of CVN 21 Program
  • Use common fleet-wide systems/equipment/components
    where practicable
  • Use existing logistic support products vice
    development of new technical data
  • Non Standard COTS must be approved by WBS 2.8
    Team before using
  • Embedded in CVN 21 Supportability Plan
  • Requirements established by Program Office
  • Implemented by Shipbuilder (WBS Working Groups)
  • Quarterly review of LDY (NGNN) Proposed
    equipment/component standardization lists against
    HEDRS
  • Formal meetings with LDY to ameliorate differences

11
CVN 21 Standardization
  • The CVN 21 approach to standardization is based
    on fostering intra-Navy and intra-ship
    commonality of systems, equipment, and components
  • The CVN 21 Standardization Program requirements
    invoked during concept development and design
    phase and will be administered during
    construction in accordance with the CVN 78
    Specifications and Special Provisions of the
    Contract. These include
  • Maximizing the use of standard equipment for
    similar functions in the ship (intra-ship
    standardization)
  • Attaining the optimal level of commonality and
    standardization of systems/equipment/components
    by maximizing the use of items already installed
    in operational carriers (intra-class
    standardization)
  • Achieving optimal standardization of
    systems/equipment/components by maximizing the
    use of items already installed in ships of the
    fleet (intra-navy standardization)
  • By-products of standardization include reduction
    of unique technical data, and increased
    transferability of operational and maintenance
    skills

12
Summary Recommended Way Ahead
  • New construction PMs are including
    standardization requirements in contracts
  • Shipbuilders are improving established
    standardization processes
  • DDG 1000 offers opportunity to demonstrate
    improved standardization process with CVN-21 to
    follow
  • Identify common metrics to be used on all new
    construction platforms

13
Backup
14
Parts Standardization Process
No
Start Catalog Activities
Process Activities
Submit Parts to NGSS for Concurrence in TcC log
BIW PSB NGSS PSB Catalog Group
Yes
Approved
Identify Std Parts
Pull From TcC log, Review Parts at NGSS for
Concurrence Submit decision to log
No
Create DDG 1000 applic. part in CPC Add cat No to
TcC log,
Create CPC equivalency Notify completion in TcC
log
Exist?
Make applic to DDG 1000 Add Cat No to TcC log,
Yes
Determine if Catalog item exists
Systems/Data
CPC Enovia TcC Log 2nd Shipyard
Outputs
15
Ship Delivery Schedule through 2015
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
J
A
J
O
DDG 1000/100105-12
DDG 100201-14
DDG 100307-15
LCS 10/1103-11
LCS 22/2303-13
LCS 26/2709-13
LCS 3403-15
LCS 5/608-09
LCS 7/803-10
LCS 14/1509-11
LCS 18/1906-12
LCS 30/3106-14
LCS 37/3809-15
LCS 106-07
LCS 906-10
LCS 311-08
LCS 403-08
LCS 12/1306-11
LCS 16/1703-12
LCS 20/2109-12
LCS 24/2506-13
LCS 28/2903-14
LCS 32/3309-14
LCS 35/3606-15
LCS 211-07
DDG 10109-06
DDG 10411-07
DDG 10607-08
DDG 10801-09
DDG 10909-09
DDG 11211-10
DDG 10012-06
DDG 10301-08
DDG 10511-08
DDG 10707-09
DDG 11007-10
DDG 10203-07
DDG 11104-10
LPD 18 12-06
LPD 1903-07
LPD 2012-07
LPD 2104-08
LPD 2206-10
LPD 2310-10
LPD 2403-11
LPD 2510-11
LHD 812-07
LHA 612-11
CVN 7811-08
CVN 7909-15
SSGN 72712-06
SSGN 72909-07
SSN 77603-07
SSN 77706-08
SSN 77804-09
SSN 77904-10
SSN 78004-11
SSN 78104-12
SSN 78204-13
SSN 78304-14
SSN 78404-15
KEY
BIW Delivery
NGSS Delivery
Shipbuilder TBD (NGSS/BIW)
Other