Title: Methods of Project Delivery for Construction Lessons Learned
1Methods ofProject Deliveryfor
ConstructionLessons Learned
- November 2007
- Presented by
- Mary K. Crites, AIA
- Parkhill, Smith Cooper, Inc
2Introduction
- Owners Desired methods for
- Faster time
- Less Cost, and earlier confirmation of cost
- Improved quality
- Less Conflicts/Litigation
- Major variables in delivery selection include
- Time sensitivity
- Cost
- Quality
- Allocation of Risk
- Lesson 1 No single best method for all
projects - Lesson 2 Impact of each variable is different
depending on the method and NO Method
delivers fastest, cheapest, highest
quality. - Lesson 3 Selection of Delivery Method should
occur - before A/E selection
3Competitive Bidding (design-bid-build)
- Advantage
- Potential for lowest construction price because
- Contractor Competition
- Defined Scope during bidding because design
complete - Separate contracts enables A/E to be Owner
Representative during Design Construction
4Competitive Bidding (design-bid-build)
- Disadvantages
- Construction price not finalized until after
design bid - Re-design re-bidding may be required to meet
budget - Early change order can reduce scope
- Provides lowest price WITHOUT respect to
Contractor qualifications or Contractor
workmanship - Linear schedule, Construction difficult prior to
design completion - Limited contractor input during design
5Competitive Bidding (design-bid-build)
- Least Suited when
- Project is complex /or large
- Scope subject to change
- Quality is important factor
- Best Suited when
- Project is not subject to change
- Lowest price is most important
- Quality is less important
- Project is small in scale not complex
- Lesson 4 Quality is important- dont have a
dirt Contractor build a Courtroom!!
6Competitive Sealed Proposal (CSP)
- Advantages
- Defined scope during bidding w/design complete
- Separate contracts enables A/E to be Owner
representative during Design Construction - Potential for best value-combination of price
and qualifications - Owner determines what selection criteria are
important - Owner may negotiate with selected GC prior to
award
7Competitive Sealed Proposal (CSP)
- Disadvantages
- Construction Price not finalized until after
design bid - Re-design re-bidding may be required to meet
budget - Negotiation prior to award can reduce scope
- Linear schedule, Construction difficult prior to
design completion - Limited contractor input during design
8Competitive Sealed Proposal (CSP)
- Least Suited when
- Scope subject to change
- Cost is most important
- Best Suited when
- Scope less subject to change
- Price AND quality are both important
- Lesson 5 Selection Criteria can be very
sensitive, and subject to interpretation.
Determine point system prior to proposal
9Construction Manager-at Risk (CM-R)
- Advantages
- Separate contracts enables A/E to be Owner
representative during Design Construction - Prime Contractor selection heavily based on
qualifications - Allows contractor input during design phase
-
- Roles responsibilities team approach (Owner,
A/E, CM-R) - Proposals/selection of sub-contracts open to
Owner A/E - Can have non-linear schedule, construction can
start prior to design completion - Construction Cost can be established early with
GMP
10Construction Manager-at Risk (CM-R)
- Disadvantages
- Difficult to determine validity of
- Costs associated with general conditions
- CM-R may self perform portions of work, no
competitiveness in pricing - UT System now requires audit at completion to
determine validity - Contractor may increase GMP because of higher
assumed risk - Final Price usually not established until after
completed design
11Construction Manager-at Risk (CM-R)
- Least Suited when
- Project is small
- Cost is most important
- Best Suited when
- Project is large /or complex
- Scope subject to change
- Price AND quality are both important
- Lesson 6 Contractors are risk averse, very
early GMPs result in less SF or higher cost.
12Design-Build (D-B)
- Advantages
- Single overall point of responsibility
- D-B selection usually weighted towards
qualifications - Heavy contractor input during design phase
- Can have non-linear schedule, i.e. construction
can start prior to design completion - Early cost guarantee may occur could be higher
cost- cover risk
13Design-Build (D-B)
- Disadvantages
- Difficult to determine validity of scope vs cost
- Contractor may increase budget/GMP or Price to
cover risk - D-B A/E unable to be Owner representative during
design and construction. Contractor typically
controls AE. - Selection of sub-contracts not open to Owner
- Design Criteria package critical- or you may get
no windows! - Requires high level of sophistication in Owner
staff - Who will certify DB pay application?
- DB AE less involved during CA, does not
represent Owner
14Design-Build (D-B)
- Least Suited when
- Scope is difficult to clearly define from the
outset - Cost is most important
- Best Suited when
- Scope clearly defined in Design
- Criteria Package
- Minimum quality is acceptable
- Lesson 7 Owner needs to realize impact of this
method - a. AE as a sub limited in role of protecting
Owner - b. Owner needs experienced staff/consultant to
monitor project - c. quality only as good a design criteria
package - Lesson 8 My preference is to be Owners AE,
represent Owner, - monitor DB
15Job Order Contracting (JOC)
- Advantages
- Potentially faster delivery time if JOC on-board
- Owner could augment their own maintenance staff
- Disadvantages
- Cumbersome to verify cost when multiple
trades/materials used - May not be competitive
16Job Order Contracting (JOC)
- Least Suited When
- Multiple trades required
- Large or medium or complex projects
- Price sensitive
- Best Suited When
- Schedule sensitive
- Small repairs
- Not price sensitive
- Lesson 9 Ronald Reagans rule applies trust
but verify - Detailed pricing MUST be
reviewed for accuracy, or you too can
be charged for stainless steel duct work!
17Construction Manager-Agent (CM-a)
- Advantages
- Could save Owner some General Contractor costs
- Allows Owner to phase construction
- Can evaluate each sub-contractor bid separately
- Disadvantages
- Owner assumes higher risk, no guarantee of cost
- Least Suited when
- Owner is risk averse
- Best Suited when
- Owner willing to assume risk
- Lesson 10 Never ask client to assume more risk.
- Some clients to save money will
assume this risk. - My experience is that they usually
regret it!
18Most
19Observations
- Key points to remember
- Selection of method should occur early
- More unknowns represent more risk,
- when Contractor assumes more risk increased
Price - Crites Preference of methods
- CSP (generally under 5 million)
- CM-R (generally over 5 million)
- Selection depends on size and complexity
- No one delivery method is best for all projects!!