Title: Methods of Project Delivery for Construction Lessons Learned


1
Methods ofProject Deliveryfor
ConstructionLessons Learned
  • November 2007
  • Presented by
  • Mary K. Crites, AIA
  • Parkhill, Smith Cooper, Inc

2
Introduction
  • Owners Desired methods for
  • Faster time
  • Less Cost, and earlier confirmation of cost
  • Improved quality
  • Less Conflicts/Litigation
  • Major variables in delivery selection include
  • Time sensitivity
  • Cost
  • Quality
  • Allocation of Risk
  • Lesson 1 No single best method for all
    projects
  • Lesson 2 Impact of each variable is different
    depending on the method and NO Method
    delivers fastest, cheapest, highest
    quality.
  • Lesson 3 Selection of Delivery Method should
    occur
  • before A/E selection

3
Competitive Bidding (design-bid-build)
  • Advantage
  • Potential for lowest construction price because
  • Contractor Competition
  • Defined Scope during bidding because design
    complete
  • Separate contracts enables A/E to be Owner
    Representative during Design Construction

4
Competitive Bidding (design-bid-build)
  • Disadvantages
  • Construction price not finalized until after
    design bid
  • Re-design re-bidding may be required to meet
    budget
  • Early change order can reduce scope
  • Provides lowest price WITHOUT respect to
    Contractor qualifications or Contractor
    workmanship
  • Linear schedule, Construction difficult prior to
    design completion
  • Limited contractor input during design

5
Competitive Bidding (design-bid-build)
  • Least Suited when
  • Project is complex /or large
  • Scope subject to change
  • Quality is important factor
  • Best Suited when
  • Project is not subject to change
  • Lowest price is most important
  • Quality is less important
  • Project is small in scale not complex
  • Lesson 4 Quality is important- dont have a
    dirt Contractor build a Courtroom!!

6
Competitive Sealed Proposal (CSP)
  • Advantages
  • Defined scope during bidding w/design complete
  • Separate contracts enables A/E to be Owner
    representative during Design Construction
  • Potential for best value-combination of price
    and qualifications
  • Owner determines what selection criteria are
    important
  • Owner may negotiate with selected GC prior to
    award

7
Competitive Sealed Proposal (CSP)
  • Disadvantages
  • Construction Price not finalized until after
    design bid
  • Re-design re-bidding may be required to meet
    budget
  • Negotiation prior to award can reduce scope
  • Linear schedule, Construction difficult prior to
    design completion
  • Limited contractor input during design

8
Competitive Sealed Proposal (CSP)
  • Least Suited when
  • Scope subject to change
  • Cost is most important
  • Best Suited when
  • Scope less subject to change
  • Price AND quality are both important
  • Lesson 5 Selection Criteria can be very
    sensitive, and subject to interpretation.
    Determine point system prior to proposal

9
Construction Manager-at Risk (CM-R)
  • Advantages
  • Separate contracts enables A/E to be Owner
    representative during Design Construction
  • Prime Contractor selection heavily based on
    qualifications
  • Allows contractor input during design phase
  • Roles responsibilities team approach (Owner,
    A/E, CM-R)
  • Proposals/selection of sub-contracts open to
    Owner A/E
  • Can have non-linear schedule, construction can
    start prior to design completion
  • Construction Cost can be established early with
    GMP

10
Construction Manager-at Risk (CM-R)
  • Disadvantages
  • Difficult to determine validity of
  • Costs associated with general conditions
  • CM-R may self perform portions of work, no
    competitiveness in pricing
  • UT System now requires audit at completion to
    determine validity
  • Contractor may increase GMP because of higher
    assumed risk
  • Final Price usually not established until after
    completed design

11
Construction Manager-at Risk (CM-R)
  • Least Suited when
  • Project is small
  • Cost is most important
  • Best Suited when
  • Project is large /or complex
  • Scope subject to change
  • Price AND quality are both important
  • Lesson 6 Contractors are risk averse, very
    early GMPs result in less SF or higher cost.

12
Design-Build (D-B)
  • Advantages
  • Single overall point of responsibility
  • D-B selection usually weighted towards
    qualifications
  • Heavy contractor input during design phase
  • Can have non-linear schedule, i.e. construction
    can start prior to design completion
  • Early cost guarantee may occur could be higher
    cost- cover risk

13
Design-Build (D-B)
  • Disadvantages
  • Difficult to determine validity of scope vs cost
  • Contractor may increase budget/GMP or Price to
    cover risk
  • D-B A/E unable to be Owner representative during
    design and construction. Contractor typically
    controls AE.
  • Selection of sub-contracts not open to Owner
  • Design Criteria package critical- or you may get
    no windows!
  • Requires high level of sophistication in Owner
    staff
  • Who will certify DB pay application?
  • DB AE less involved during CA, does not
    represent Owner

14
Design-Build (D-B)
  • Least Suited when
  • Scope is difficult to clearly define from the
    outset
  • Cost is most important
  • Best Suited when
  • Scope clearly defined in Design
  • Criteria Package
  • Minimum quality is acceptable
  • Lesson 7 Owner needs to realize impact of this
    method
  • a. AE as a sub limited in role of protecting
    Owner
  • b. Owner needs experienced staff/consultant to
    monitor project
  • c. quality only as good a design criteria
    package
  • Lesson 8 My preference is to be Owners AE,
    represent Owner,
  • monitor DB

15
Job Order Contracting (JOC)
  • Advantages
  • Potentially faster delivery time if JOC on-board
  • Owner could augment their own maintenance staff
  • Disadvantages
  • Cumbersome to verify cost when multiple
    trades/materials used
  • May not be competitive

16
Job Order Contracting (JOC)
  • Least Suited When
  • Multiple trades required
  • Large or medium or complex projects
  • Price sensitive
  • Best Suited When
  • Schedule sensitive
  • Small repairs
  • Not price sensitive
  • Lesson 9 Ronald Reagans rule applies trust
    but verify - Detailed pricing MUST be
    reviewed for accuracy, or you too can
    be charged for stainless steel duct work!

17
Construction Manager-Agent (CM-a)
  • Advantages
  • Could save Owner some General Contractor costs
  • Allows Owner to phase construction
  • Can evaluate each sub-contractor bid separately
  • Disadvantages
  • Owner assumes higher risk, no guarantee of cost
  • Least Suited when
  • Owner is risk averse
  • Best Suited when
  • Owner willing to assume risk
  • Lesson 10 Never ask client to assume more risk.
  • Some clients to save money will
    assume this risk.
  • My experience is that they usually
    regret it!

18
Most
19
Observations
  • Key points to remember
  • Selection of method should occur early
  • More unknowns represent more risk,
  • when Contractor assumes more risk increased
    Price
  • Crites Preference of methods
  • CSP (generally under 5 million)
  • CM-R (generally over 5 million)
  • Selection depends on size and complexity
  • No one delivery method is best for all projects!!