Title: CMGC Lessons Learned
1CMGC Lessons Learned
- Presented by
- Reuel Alder Robert Stewart
- Innovative Contracting Engineers
2Presentation Outline
Why Innovative Contracting
- Why is UDOT using Innovative Contracting?
- What lessons has UDOT learned with CMGC?
- Where are we going?
3Traditional Cost Curve for Construction Projects
Why Innovative Contracting
4User Costs vs. Time in Work Zones
Why Innovative Contracting
Doesnt include inflation / material increase /
temporary environmental impacts
5Project Cost Curve
Why Innovative Contracting
6Innovative Methods Learning Curve
Why Innovative Contracting
7Innovation to Reduce Total Cost
Why Innovative Contracting
Design Build
ABC
CMGC/CM at Risk
Warranties
AB
Lane Rental
8Design Build
Why Innovative Contracting
Plan
UDOT
Design
Contractor
9Design Build
Why Innovative Contracting
- Benefits
- Early known cost
- Lower time/cost growth
- Reduce delivery time
- Reduce design errors
- Improve constructability
- Identify and manage risk
- Encourage innovation
- Less detail required in design
- Expands UDOT resources
- Risks
- Proposal costs (stipend )
- Innovation limited to contractor experience
- Third Party Delay
- Control in design
- Financing
10Design Build Strategy
Why Innovative Contracting
- Projects where in-house resources not sufficient
- Projects that can benefit from fast-tracking
- Projects with high need for innovation
- Projects on Interstate (mitigated 3rd-party
delay) - Risks known and transferable
11CMGC Process
Why Innovative Contracting
Plan
UDOT
Design
Contractor
Negotiate
UDOT
Build
Bid Build
Contractor
12CMGC
Why Innovative Contracting
- Risks
- Sole source contract
- Unable to negotiate on project cost
- Benefits
- UDOT controls design
- UDOT selects innovation
- Reduce design errors
- Lower cost/time growth
- Improved constructability
- Identify and manage risk
- Detail in design to level needed by Contractor
- Early Procurement
- Early start on critical path
13Strategy for CMGC
Why Innovative Contracting
- Projects that UDOT needs Contractor involvement,
but desires to control design - Projects with high need for innovation
- Projects that can benefit from early procurement
- Projects with adequate time for design
- Projects with third-party risk
14Risk
Why Innovative Contracting
15Why is UDOT using Innovative Contracting?
Why Innovative Contracting
- Times have changed
- Use the experience of construction industry
- Early mitigation of risk
16CMGC Project Reports
Lessons Learned
Reuel Alder Innovative Contracting
17CMGC Federal
Lessons Learned
18CMGC State
Lessons Learned
19GMGC PMs
Lessons Learned
20Contracting Method Evaluation Guide
Lessons Learned
- Use in Concept Development
- Use with Risk Assessment
21Review Questions forCMGC Projects
Lessons Learned
- Design benefits/challenges
- Constructability
- Innovations
- Schedule
- Risks identified and managed
- Learning opportunities
- Environmental stewardship
22Anticipated Benefit
Lessons Learned
UDOT Controls Design UDOT selects Innovation
23The Experience
Lessons Learned
- The contractor understood and applied new
Technology - The SPMT contractor was able to understand the
slope and limitations of the area
24Anticipated Design Benefit
Lessons Learned
- Contractor participation is expected to
- improve constructability,
- reduce errors and change orders,
- identify and manage risk, and
- reduce overruns
25Design Experience Cont
Lessons Learned
- Contractors have experienced more designs
- Allowed us to meet the rapid design schedule
- Contractor design changes saved time and effort
- Helped establish the detail needed on plans
- Helped prioritized utilities and right-of-way
- Design customized to contractors means and
methods - Optimized construction and reduced cost
26Design Experience Cont
Lessons Learned
- Early involvement on challenging issues
- Resolve railroad crossing, groundwater and
drainage - Time to discuss the storm drain design details as
well as utility impacts - Understanding design and meet UDOT standards
- Contractor worked with the designer on rock
blasting
27Design ExperienceRiverdale Rd
Lessons Learned
- Approximately 280,000 in savings thus far
- Designer assumed the contractor would not want to
construct the storm drain laterals - Designer identified several trunk lines
- Contractor suggested to increase sized of main
trunk line and replace laterals - This avoided several utility disruptions and
saved approximately 8,000 feet of pipe
28Constructability Experience Redwood Rd
Lessons Learned
- Unforeseen constructability issues addressed
- Sinking caissons and unknown foundations
- Helped optimize design and reduce cost
- Pavement material
- Decorative fencing
29Constructability Experience I-80
Lessons Learned
- Contractor participates in weekly meetings to
simplify construction methods, reduce cost and
reduce schedule - ABC components
- Placement of sign structures
- Placement of ATMS lines
- Sign foundations and
- Treatments to the abutments
30Constructability Experience Lisa Wilson
Lessons Learned
- Constructability of the projects went well
- Constructability issues were brought forward by
the contractor in the design - Storm drain and the depth of the crossings
- Driveways were redesigned at the contractors
request
31Anticipated Innovation Benefits
Lessons Learned
- UDOT can select innovation independent of
contractor experience or abilities - Contractor participation is expected to encourage
innovation - Contractor participation is expected to moderate
the risk of new technology innovations
32Innovations
Lessons Learned
- Redwood Rd innovations
- Hydraulic improvements (trunk lines)
- Visual tools to express expected delay to the
traveling public - I-80 innovations
- Accelerated Bridge Construction
- Steel girders used for ease of movement in the
ABC process - Moveable barriers
33Innovations Cont
Lessons Learned
- Riverdale innovation
- Accelerated Bridge Construction (ABC)
- Movable crossings
- Precast concrete panels for driveways
- Business bucks
34Ford Motor Company
35After ReengineeringNo Invoice
36Anticipated Schedule Benefits
Lessons Learned
- Shorten time between design and construction
- Compress project schedule by early start
- Early procurement of long lead items
- Begin at risk before Utilities and R/W are
completed
37Schedule Experience
Lessons Learned
- Redwood Rd
- Design schedule shortened
- Construction time lengthened
- Scope expanded in design
- I-80
- Anticipate saving one construction season by
running parallel activities
38Schedule Experience Cont
Lessons Learned
- 4500 S _at_ I-215 ABC
- Saved a construction season
- Hired contractor early
- Early bid package for steel
- 5600 W
- Design shorted by two months
- Phasing construction to preclude railroad work
saved 1 construction season
39Schedule Experience Cont
Lessons Learned
- I-80 Aria Blvd
- Mistakes in plans
- Design schedule longer
- Riverdale
- Anticipate an early start on earthwork and bridge
materials
40Schedule Experience Cont
Lessons Learned
- Parrish Lane _at_ I-15
- Having the contractor in the design process
allowed the team to meet the rapid design schedule
41Anticipated Risk Benefits
Lessons Learned
- Contractor will help identify and manage risk
- Contractors relationship with 3rd parties helps
mitigate risk - R/W after design reduces errors and rework
(compared to DB)
42Risk Experience
Lessons Learned
- Contractor helped to identify risk in ABC, R/W,
Utilities and Schedule for I-80 - Critical in prioritizing utilities for Redwood Rd
- Contractor pot holed and identified utility
locations on 5600 West - Contractor input on rock blasting at I-80 Aria
- Self Propelled Modular Transporter (SPMT)
43Lessons LearnedRedwood Rd 1st CMGC
Lessons Learned
- This process helped all parties understand
financial consequences - Good exchange with contractor
- The scope expanded during design
- Meetings were not structured well until project
end - Need an independent schedule or time estimate as
well as an ICE - Add Anticipate typical urban construction items
to RFP
44Lessons LearnedLisa Wilson Projects
Lessons Learned
- Projects are done quicker
- Design plans are improved
- Construction information is better communicated
- Excessive information is minimized
- We will not use all of our design budget
45Lessons LearnedLisa Wilson Projects
Lessons Learned
- Subcontractor and supplier input is critical
- Third party estimator is essential
- Designer and contractor reconcile quantities so
estimators have common understanding - Bid items are less complex
46Lessons LearnedLisa Wilson Projects
Lessons Learned
- Contractor performed potholing
- Field awareness
- Improved work with Utilities
- Solutions other than relocation
- Quick turn around at project end because designer
had contractor input to work out cleanup issues
47Lessons LearnedParrish Lane
Lessons Learned
- Quality of Plans improved
- Contractor gets needed information
- Subcontract and material supplier input crucial
- Third party estimator needs to meet with designer
48Faster Better Cheaper
- Innovation
- Eliminate unnecessary work
- Eliminate delays between steps
- Parallel process
- Pre process
- New Technology
- Defined repeatable process
- Tasks are known
- Gain speed with experience
- Continually analyze and improve
- Training, Training, Training
Process
Technology
People
49AGC Benefits
Lessons Learned
- Minimize Risk
- Improve Schedule
- Coordinate with Designer
- Partnership instead of Adversarial Relationship
- Best Method to Try New Innovations
50Where are we going?
Where are we going?
- Project Selection
- Proposal Phase
- Design Phase
- Process Improvements
51Project Selection
Where are we going?
- Select method in the concept phase
- Need to look at entire program.
52Proposal Phase
Where are we going?
- Project Approach
- Need to better define goals and what is expected.
- Focus more attention to these goals in
pre-proposal meetings - Innovations
- Outline those ideas that UDOT already has.
- Describe those ideas UDOT has ruled out.
53Price History
- Selected on technical capabilities
- Contractors complaint beauty contest
- Price added as a selection criteria
- Contractors complaint buying the project
- Statistical average for price
- Contractors at AGC accepted the approach
54Price Benefits
- Brings cost innovation to the table
- Brings cost competition to the table
- Brings cost accountability to the table
- Provides validation of good price for public trust
55Proposal Phase
Where are we going?
- Price
- Continue to use the average target
- Perhaps use low-bid on projects where significant
design occurs - Find a way to include a time element (incentives
/ lane rental / AB / etc.) - Approach to Price
- Emphasize during pre-proposal
- Change the format
56Design
Where are we going?
- Get Contractor on board as early as possible
- Include the Independent Cost Estimator
- Phasing
- Recommendation from Region Director
- Phases truly must be independent!
57Phasing (PDBS / ePM)
Where are we going?
- PDBS is not set up for multiple phases
- Each phase acts as a separate project
- Separate
- Checklist
- Eng. Estimate / Red Flag Analysis
- Insurance/bonds
- Project book / contract
- Award / NTP
- Project and PIN
58End
- Why is UDOT using Innovative Contracting?
- What has UDOT learned with CMGC?
- Where are we going?
59AGC Subcommittee
- Proposal Phase
- Price and Quals.
- Avg. Bid preferred if price included.
- Perhaps use low bid on small projects (especially
if majority of design is done) - Get Contractor input on bid items to be included
in RFP.
60Faster Better Cheaper
- Innovation
- Eliminate unnecessary work
- Eliminate delays between steps
- Parallel process
- Pre process
- New Technology
- Defined repeatable process
- Tasks are known
- Gain speed with experience
- Continually analyze and improve the process
- Training, Training, Training
Process
Technology
People
61Project Development Goals
- Reduce the time to contract
- Reduce Project time
- Reduce impact on the public
- Deliver higher quality for less total cost
62AGC Subcommittee cont.
- RFP
- Need to make requirements clearer
- Goals
- Scoring
- What isnt expected
- Decrease submittal size on small projects
- How are user costs perceived?
- Stipend?
63AGC Subcommittee cont.
- Selection Process
- Interviews
- Only potential winners
- Limit interview team to PM, Estimator, and those
involved on project - Design Phase
- Get Contractor on board earlier in design phase
- Perhaps pick Contractor before Designer
- Provide more time in design
64AGC Subcommittee cont.
- Construction Phase
- Price Negotiations
- Get ICE involved in project meetings
- Post winning bids
65Early Involvement
66Design Build and CMGC
67CMGC
68Design Build