Scheduling%20Work - PowerPoint PPT Presentation

About This Presentation
Title:

Scheduling%20Work

Description:

Map network to a timeline (eg Gantt Chart) using the effort estimates. ... Gantt Chart producers. MS Project. Web access. Supports multiple projects. Dependencies ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 30
Provided by: steveda8
Category:

less

Transcript and Presenter's Notes

Title: Scheduling%20Work


1
Scheduling Work
  • I love deadlines.
  • I love the sound they make as they fly by.
  • -- Douglas Adams

2
Why is software late?
  • Under-Estimate of effort.
  • Unrealistic deadlines imposed by outsiders.
  • Changing requirements.
  • Risks that were not considered.
  • Technical problems that could not be foreseen.
  • Failure to recognized that the project is falling
    behind schedule and lack of action to correct the
    problem.
  • Software Engineering A Practitioners Approach
    by Pressman

3
How to build a schedule
  • Determine dependencies of activities found in
    WBS.
  • Use dependencies to build activity network
    diagram (eg PERT).
  • Determine critical path.
  • Map network to a timeline (eg Gantt Chart) using
    the effort estimates.
  • Use a software tool to help do this work.

4
Why Determine Dependencies?
  • Dependencies determine deadlines and when work
    can begin.
  • The WBS shows hierarchy, not dependency.
  • Planners must find all dependencies.
  • Surprises are very bad!

5
Dependency Types
  • External Dependency
  • Other projects
  • Stakeholders
  • Sub-Contractors
  • Internal Dependency
  • Audits (design, testing, documentation, )
  • Sign-Offs at end of phase

6
Dependency Types
  • Start Finish
  • FS - T2 cannot start until T1 is finished.
  • coding must wait on design to be finished
  • SS - T1 and T2 must start at same time.
  • documentation and coding start together
  • FF - T1 and T2 finish at same time.
  • configuration management ends when coding is done

7
Dependency Types
  • Lag T2 cannot start until a given amount of
    time after T1 is done.
  • Start on-site training one week after final demo
    to customer management group.
  • Soft T2 should start after T1, but it is not
    completely essential that T1 be finished.
  • Populate the new database after the database has
    been built. If the new database is not
    completely finished we can still populate the few
    finished tables.

8
Activity Networks
  • CPM Critical Path Method
  • activities are graph nodes (circles)
  • single estimate for duration of tasks
  • PERT Program Evaluation and Review Technique
  • activities are graph arcs (lines)
  • activity times are ranges and include
    probabilities

9
http//www.cs.unc.edu/stotts/COMP145/homes/map/im
ages/pert.gif
10
http//www.mckinnonsc.vic.edu.au/la/it/ipmnotes/ga
nttpert/pert_chart.gif
11
Example Activity Network Activity on Node
1wks
2wks
T5
T2
1wk
3wks
1wk
2wks
1wk
T1
T4
T6
T8
T9
4wks
T3
3wks
T7
  • Questions
  • Minimum time to complete the project?
  • Critical Path?
  • For T2, what are the earliest start time, latest
    start, earliest finish, latest finish?
  • es2ndwk ls4thwk ef3rdwk lf5thwk

12
Resulting Gantt Chart
1 2 3 4 5 6 7 8 9 10 11 12 13 14
T1
T2
T3
T4
T5
T6
T7
T8
13
Managing Uncertainty
  • Q How confident can we be in our milestone dates
    and the delivery date?
  • A Using confidence and Statistics
  • for each task, determine pessimistic and
    optimistic times
  • if PT-OT is small for all tasks, then great!!!
  • compute average PT-OT, and std dev
  • if a task's PT-OT is outside the std dev, worry
    about that task

14
Managing Uncertainty
  • Q Where do we schedule uncertainty time?
  • A1 spread it out by bumping each milestone.
  • used by Critical Path
  • A2 lump it together as one activity at end.
  • used by Critical Chain

15
Common PERT Problems
  • Missing dependencies
  • Misinterpretation

16
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
K
M
N
3
4
5
2
1
17
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
K
M
N
3
4
5
2
1
But wait, we can shorten the project if we write
the manual right after testing is finished. (L
and M can be done in parallel.) So
18
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
3
K
2
1
M
N
4
5
But wait, the system needs to be installed
before we can use it to train people. So
19
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
3
K
2
1
5
M
N
4
But what is that activity between dates 3 and 4?
So
20
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
3
K
2
1
5
M
N
4
Dashed line is a dummy activity.
21
Example
  • K integration testing
  • L Install Software
  • M Write Manual
  • N Train Users

L
K
N
M
Note dummies not needed with "activity on node"
graphs.
22
Resource Leveling
  • Activity Shifting
  • to avoid using resources during a peak time.
  • use slack in start and end dates
  • Activity Splitting
  • to shorten duration
  • break activity into pieces when more resources
    are available
  • Optimize the System, not individual tasks
  • Leveling usually yields longer projects

23
Example
B 2wk
C 2wks
D 2wks
H 3wks
I 2wks
A 3wks
E 2wks
F 5wks
G 3wks
  • What is the completion time?
  • Since F is so long, what would be the completion
    time if we break it into two parallel parts of
    2wks and 3wks?

24
Theory of Constraints
  • The Goal by Goldratt in 1997
  • Traditional approach is to divide and divide into
    manageable parts, then optimize these parts.
  • TOC looks at the whole system.
  • Identify In order to manage a constraint, it is
    first necessary to identify it.
  • Exploit Focus on how to get more production
    within the existing capacity limitations.
  • Subordinate Prevent the materials needed next
    from waiting in a queue at a non-constraint
    resource.
  • Elevate If, after fully exploiting this process,
    it still cannot produce enough products to meet
    market demand, find other ways to increase
    capacity.
  • Go back to Step 1.

25
Scheduling Tools
  • Gantt Chart producers
  • MS Project
  • Web access
  • Supports multiple projects
  • Dependencies
  • Billing support
  • Resources leveling
  • Gantt charts, activity network,

26
MS Project
27
Open WorkBench
28
ATC Professional
29
And finally
Write a Comment
User Comments (0)
About PowerShow.com