UK Rollout and Support Plan - PowerPoint PPT Presentation

1 / 7
About This Presentation
Title:

UK Rollout and Support Plan

Description:

Andrew McNab - Manchester HEP - 22 April 2002. UK Rollout and Support Plan ... Andrew McNab - Manchester HEP - 22 April 2002. Summary. UK Deployment Plan ... – PowerPoint PPT presentation

Number of Views:17
Avg rating:3.0/5.0
Slides: 8
Provided by: john1492
Category:

less

Transcript and Presenter's Notes

Title: UK Rollout and Support Plan


1
UK Rollout and Support Plan
  • Aim of this talk is to the answer question As a
    site admin, what are the steps between the
    situation today, and all interested UK sites
    being part of the Testbed.
  • Definite predictions limited by uncertain nature
    of the releases.

Andrew McNab - Manchester HEP - 22 April 2002
2
Constituencies
  • Sysadmins (represented in Sysman and by WP6)
  • Care about the integrity of their site (firewalls
    etc) and the maintenance load of Grid Testbed
    equipment may be under pressure to get a green
    dot on the relevant map.
  • Experiments (represented by GridPP EB)
  • Want sites up and running for application
    development and to run data challenges. Esp.
    concerned about sites hosting their farms.
  • Grid developers (represented by GridPP TB)
  • Concerned about getting functionality running in
    UK, esp. at sites where experts are.
  • Local HEP groups (represented on GridPP CB)
  • Want a transparent process that includes everyone.

Andrew McNab - Manchester HEP - 22 April 2002
3
UK Deployment Plan
  • Start with UK WP6 people ( other key experts)
  • Use tb-support_at_jiscmail.ac.uk mailing list, which
    anyone can join and is archived.
  • Once have some WP6 sites up and a procedure that
    should work for any site, then ask more sites to
    test installation procedure, docs etc.
  • Once this has stabilised, invite all interested
    sites to install Testbed software.
  • By this point, installation instuctions should be
    clear and not require previous grid experience,
    ad-hoc fixes etc.
  • Support will then be provided by tb-support
    mailing list on best-effort basis and Grid
    Support Centre with a formal ticket-based system.
  • (Likely that mailing list will be best place to
    get a quick answer.)
  • Need to repeat this every 2 months for EDG
    releases, although not all sites may have
    commitments (eg from experiments) to do this.

Andrew McNab - Manchester HEP - 22 April 2002
4
Testbed Joining Procedure
  • Procedure for joining EDG testbed is being
    defined by WP6.
  • For UK sites, WP6 UK will propose sites to rest
    of WP6.
  • WP6-UK will provide help with testing UK sites
  • Have GridPP VO, Resource Broker and MDS so can
    add sites to UK Testbed and validate
    functionality ourselves before trying in the EDG
    Testbed.
  • We dont want to propose sites without testing
    them ourselves and cautious sites can put
    themselves up for validation within GridPP
    without risking embarrassment at a European
    level.
  • Will use same validation criteria as WP6.

Andrew McNab - Manchester HEP - 22 April 2002
5
Installation Procedure
  • This needs to be based around LCFG because of
    complex configuration process, which is published
    as automatic LCFG configuration objects.
  • Sites will almost certainly need to dedicate
    machines to be installed this way.
  • LCFG itself has been non-trivial to install and
    configure.
  • However, once your local LCFG server is working,
    installing CE etc is automated (similar to RedHat
    kickstart.)
  • Steve has been installing LCFG at RAL and has
    written up the procedure. Also contributed
    updated scripts back to WP6. So the situation is
    much better now.

Andrew McNab - Manchester HEP - 22 April 2002
6
More information
  • EDG Testbed talk from earlier today.
  • WP6 website at http//marianne.in2p3.fr/
  • GridPP Technical Board http//www.gridpp.ac.uk/tb/
  • tb-support_at_jiscmail.ac.uk mailing list
  • http//www.gridpp.ac.uk/tb-support/ has
  • mailing list information
  • Steves recipe for LCFG-installing Computing
    Element, Storage Element, User Interface machine
    and Worker Node.

Andrew McNab - Manchester HEP - 22 April 2002
7
Summary
  • UK Deployment Plan largely defined
  • but depends on timing and quality of EDG releases
  • Testbed joining procedure defined
  • aim to use UK resources to smooth path for UK
    sites to join EDG Testbed.
  • Deployment to non-expert sites largely limited by
    current installation procedures
  • this has improved a lot and is pretty much ready
    to go.

Andrew McNab - Manchester HEP - 22 April 2002
Write a Comment
User Comments (0)
About PowerShow.com