Title: Select Committee on Finance
1Department Of Education
- Select Committee on Finance
- 16/09/2009
2Content
- Year-on-year comparison
- Conditional Grants
- Background
- National School Nutrition Grant
- HIV and Aids Grant
- Infrastructure
- Monitoring
- Key challenges
3Year-on-year comparisonAllocations 2008 2009
4Year-on-year comparisonExpenditure to 30 June
2008 2009
5Conditional Grants
6Expenditure to 30/06/2009
7Year-on-Year comparison Allocations 2008 2009
8Year-on-Year comparisonExpenditure to 30 June
2008 2009
9Background
- During 2008/09 the department overspent the COE
budget with R414 million - This impacted on the cash flow and payments for
goods and services, conditional grants, transfers
and capital payments were held back - Major impact on the budget for 2009/10 financial
year as invoices to the amount of R292 million
were paid from April to July 2009
10Background
- The following accruals were registered for
2008/09 - Goods and services R202 m
- Transfers and subs R5 m
- Buildings R58 m
- Equipment R24 m
- Intangible assets R3 m
- This impact is visible throughout the 1st quarter
reports of the department in terms of actual vs
planned outputs and expenditure as service
providers refused to take new orders from the
Department due to non-payment
11Background
- The Department implemented cost curtailment
measures to absorb the impact of the R292 million
accruals - Moratorium was placed on filling of non-educator
posts - Delegations to acquire goods and services were
withdrawn - Thresholds for all administrative functions were
implemented
12National School Nutrition Grant
13Progress report April - June 2009 (A)
Strategic objective To supply food to needy
learners through National School Nutrition
Programme Budget 2009/10 R229.534 million
14Progress report April - June 2009 (A1)
Planned Annual Output Operational and administrative costs. Planning session conducted
1st Quarter planned output Operational costs and consumable stores and 1st planning session conducted
1st Quarter Actual Output Operational costs and consumable stores and 1st planning session conducted
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R3 761 000
1st Q actual spending R1 604 620
14
15Progress report April - June 2009 (A2)
Planned Annual Output 574,725 primary and 48,588 secondary school learners to access programme for 198 days
1st Quarter planned output 574,725 learners in primary and 48,588 secondary school learners to access the nutrition programme for 48 days
1st Quarter Actual Output 574,725 primary and 48,588 secondary school learners participated in the programme for 48 days
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R52 979 000
1st Q actual spending R63 910 380
15
16Reach
- The programme is currently accessed by Primary
and Secondary School Learners in the following
categories
Primary Schools No. of Schools No. of Learners
Quintile 1 360 113 343
Quintile 2 395 162 581
Quintile 3 332 175 728
Quintile 4 167 88 703
Quintile 5 57 27 565
Unranked 78 6 805
Total 1 389 574 725
17Reach
Sec. Schools No. of Schools No. of Learners
Quintile 1 78 48 588
TOTAL (Primary Secondary) 623 313
- Why feed Q4 Q5 ?
- Farm schools and schools serving informal
settlements are ranked in the higher categories. - In terms of Cabinet Memo of 2002, the above
category of schools should receive priority.
17
18Cost per meal
- The meals cost R1.50 and R1.83 for Primary and
Secondary schools respectively (exclusive of 17c
cooking cost) - National norm R1.80 and R2.35 (inclusive of
cooking cost) - Realistically speaking, the per capita
expenditure can only provide food that meets the
basic requirements - Fortified maize products, beans, soya products,
cooking oil, condiments, rice and fresh vegetable
are not cheap, but are provided
18
19HIV and AIDS Grant
20Progress report April - June 2009 (B)
Strategic objective To educate learners on Life
Skills, HIV and Aids and to give care and support
to those infected and affected by HIV and
Aids Budget 2009/10 R10.093 million
21Progress report April - June 2009 (B1)
Planned Annual Output Operational and administrative costs. Planning sessions conducted
1st Quarter planned output Operational costs and consumable stores and 1st planning session conducted
1st Quarter Actual Output Operational costs and consumable stores and 1st planning session coordinated
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R219 000
1st Q actual spending R44 000
21
22Progress report April - June 2009 (B2)
Planned Annual Output 1,800 educators empowered on Sexuality Education, Drug and Substance Abuse
1st Quarter planned output 600 Educators empowered on Sexuality Education, Drug and Substance Abuse
1st Quarter Actual Output 600 Educators empowered on Sexuality Education, Drug and Substance Abuse
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R685 000
1st Q actual spending R577 000
22
23Progress report April - June 2009 (B3)
Planned Annual Output 600 Schools turned into Nodes of Care and Support and 1 Jamboree held (Leth'impilo)
1st Quarter planned output 150 Schools turned into nodes of Care and Support
1st Quarter Actual Output 45 Schools turned into Nodes of Care and Support
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R250 000
1st Q actual spending R75 000
23
24Progress report April - June 2009 (B4)
Planned Annual Output 1,800 educators empowered on Care and Support
1st Quarter planned output 600 educators empowered on Care and Support of OVCs
1st Quarter Actual Output 689 Educators empowered on Care and Support of OVC's
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R593 000
1st Q actual spending R393 000
24
25Progress report April - June 2009 (B5)
Planned Annual Output 2,000 learners in 100 schools empowered on Peer Support programme including Soul Buddyz Congress
1st Quarter planned output 800 learners empowered on a Peer Support programme
1st Quarter Actual Output 640 Learners empowered on Peer Support Programme
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R1 170 000
1st Q actual spending R705 000
25
26Progress report April - June 2009 (B6)
Planned Annual Output 600 SMTs empowered on Policy Development by EMGD
1st Quarter planned output 150 SMTs empowered on Policy Development
1st Quarter Actual Output 150 SMT's empowered on HIV and AIDS Policy Development
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R206 000
1st Q actual spending R174 000
26
27Progress report April - June 2009 (C)
Strategic objective To make all role players and
stakeholders advocates of HIV and AIDS Budget
2009/10 R4.533 million
27
28Progress report April - June 2009 (C1)
Planned Annual Output All Life Skills, HIV and AIDS programmes advocated to relevant stakeholders
12 open discussion workshops between parents and learners (Peer Educators) on HIV and AIDS 48 clusters of SGB's 54 Traditional Leaders Wives 4 clusters of Traditional Healers 4 clusters of FBOs 48 Calendar Events celebrated
1st Quarter planned output 3 Open discussion workshops between parents and learners (peer education) on HIV and AIDS conducted 12 Clusters of SGBs 12 Candle Light Memorial Events celebrated
28
29Progress report April - June 2009 (C1)
1st Quarter Actual Output 3 Open discussion workshops between parents and learners on HIV and AIDS conducted 12 Candle Light Memorial Events celebrated
Challenges/reasons for non-achievement/ outcomes Operational 12 Clusters of SGB's not capacitated due to the election period of new SGB's Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Operational Capacitation of SGB's to be done in the 2nd quarter after elections of new SGB's Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R422 000
1st Q actual spending R202 000
29
30Progress report April - June 2009 (C2)
Planned Annual Output 156 Schools monitored and supported
1st Quarter planned output 38 Schools monitored and supported
1st Quarter Actual Output 19 Schools monitored and supported by regional officials, 15 schools evaluated by the Provincial and National Team
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R268 000
1st Q actual spending R91 000
30
31Progress report April - June 2009 (C3)
Planned Annual Output LTSM for learners and educators procured
1st Quarter planned output Relevant LTSM for 1,500 educators and 7,500 learners procured (resource guides and activity books)
1st Quarter Actual Output Relevant LTSM for 1,289 educators and 640 learners procured (resource guides and activity books)
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R539 000
1st Q actual spending R392 000
31
32Infrastructure
33Progress report April - June 2009 (D)
Strategic objective To improve the physical
conditions and appearance of schools Budget
2009/10 R246.590 million
34Progress report April - June 2009 (D1)
Planned Annual Output 3 New Schools
1st Quarter planned output Commence with the three new schools in this programme
1st Quarter Actual Output Operational Magudu at 40 Cyril Clarke and Khunjuliwe have not commenced
Challenges/reasons for non-achievement/ outcomes Operational Allocation of site at Khunjuliwe Cyril Clarke School design option not finalized
Plans to Address challenges Negotiation are in progress for Khunjuliwe Decision on Cyril Clarke fast tracked.
1st Q projected budget R71 000 000
1st Q actual spending R39 073 000
35Progress report April - June 2009 (D2)
Planned Annual Output Special and Inclusive Schools. There are 4 school prioritised for 2009/10
1st Quarter planned output To commerce the upgrading of schools for learners with special needs
1st Quarter Actual Output No progress registered
Challenges/reasons for non-achievement/ outcomes Operational Reprioritisation process have contributed to the delays
Plans to Address challenges Operational DPWRT to refocus on this programme
1st Q projected budget R29 000 000
1st Q actual spending Nil
36Progress report April - June 2009 (D3)
Planned Annual Output 100 historical projects to be completed
1st Quarter planned output Fast tracking process to be instituted in 100 projects
1st Quarter Actual Output Slow progress registered in 100 projects
Challenges/reasons for non-achievement/ outcomes Financial Invoices submitted for payment not processed due to accrual payments and cash flow
Plans to Address challenges Financial Revised cash flow schedule was submitted to Treasury
1st Q projected budget R38 929 000
1st Q actual spending R56 227 000
37Progress report April - June 2009 (D4)
Planned Annual Output Mud and unsafe Schools
1st Quarter planned output There are 14 schools in this programme.
1st Quarter Actual Output Planning and design completed. Preparation of tender documents.
Challenges/reasons for non-achievement/ outcomes Operational Delay with tendering process by DPWRT
Plans to Address challenges Operational Matter discussed in a POMM and challenges resolved
1st Q projected budget R29 000 000
1st Q actual spending Nil
38Progress report April - June 2009 (D5)
Planned Annual Output Kitchens and Grade R centres
1st Quarter planned output Commence the plan and design
1st Quarter Actual Output Planning and design in process
Challenges/reasons for non-achievement/ outcomes Operational No feedback from implementing agent
Plans to Address challenges Operational Follow-up with implementing agent prioritised
1st Q projected budget R10 000 000
1st Q actual spending None
39Monitoring of the grants (NSNP and HIV and AIDS)
- Monitoring is done as a compliance requirements
within the DORA and PFMA - This is done within the broader monitoring
process led by the Department of Basic Education - 11 Life Skills Regional Officials and 26 NSNP
monitors monitor the implementation of the
programme by visiting the schools and submitting
reports to the Provincial office for effective
monitoring and providing adequate support to
reach all the schools - More Regional officials are needed to execute
their duties effectively - Regional reports are consolidated monthly and
sent to NDoE
40Monitoring of the grants (NSNP and HIV and AIDS)
- Quarterly and Annual reports compiled and sent to
NDoE and NT reporting on financial and
non-financial indicators - Provincial evaluation team conduct pre-evaluation
of 10-20 schools before final evaluation by
national department is conducted at end of each
financial year - Evaluation reports are compiled by the Provincial
evaluation team at the end of each financial year - Quarterly meetings are held with the NSNP
suppliers to deal with any challenge within the
programme
41Monitoring of the grants (Infrastructure)
- The MDoE has limited internal resources to
conduct effective monitoring - Work Inspectors posts at HO are vacant due to
promotion of incumbents - Reliance on the presence of the Service Provider
Teams, i.e. PTAT, OST TA - Service Provider Teams are also small as PTAT has
one person, OST one person at HO and one per
Region (except BBR Region) and one TA - The latter individual monitors specific projects
- Works Inspectors posts at the Regional Offices
have just been filled
42Summary of key challenges
- Limitation on achievement of goals due to
outstanding payments to service providers - Accrual payments impacting on budget for 2009/10
- Utilization of grant funds for Compensation of
employees - NSNP R44 537 437.44
- Infrastructure R14 186 703.98
- HIV and AIDS R 1 177 000.00
- Inability to provide nutrition to 67 541 poor
learners in farm schools ranked Q4 and ungazetted
Q1 Secondary Schools in BBR
43Summary of key challenges
- In terms of infrastructure
- Some contractors have deserted sites while others
have scaled down operations - Service providers not paid on time due to
insufficient cash - Delay in the procurement of service providers by
the implementing agent - Inaccurate reports from the implementing agent
that are provided to the department - Unavailability of sites in some municipalities
- Inadequate capacity in the department
44The end