Title: MDoE Presentation Select Committee on Finance
1MDoE Presentation Select Committee on Finance
2Focus of presentation
- Organisational context
- Conditional grants
- Life Skills Programme
- National School Nutrition Programme
- FET Colleges Recapitalisation Programme
- Infrastructure
3Organisational Context
4 Enrolments
- Total Learner enrolments increased by 0,7 from
845 910 in 2004 to 1 044 187 in 2008 - 600 680 learners are in Public Primary Schools
and 387 740 in Public Secondary Schools - 42 729 learners enrolled for Grade R
- 4 953 students enrolled for the new NC(V)
programmes at 3 FET Colleges - Female enrolments in the system remains less at
49,64 to a 50,36 male.
5Conditional Grants And Capital Expenditure
Trends
6Conditional Grants outcome for 2005/06
7Economic Classification 2005/06 CAPEX
8Conditional Grants outcome for 2006/07
9Economic Classification 2006/07 CAPEX
10Conditional Grants 2007/08
Conditional Grant Adjustment Budget 2007/08 Total Transfers 2007/08 Exp as at 31March 2008 Exp
HIV 13,010 13,010 12,443 95.6
NSNP 108,056 108,056 110,504 102.3
FET 48,267 48,267 48,271 100
Infrastructure 246,368 142,382 36,895 15
Total 415,710 311,724 208,113 50.1
11Economic Classification 2007/08 CAPEX
12Conditional Grants 2008/09 First Quarter (Under
spending/ overspending)
Conditional Grant Adjustment Budget 2008/09 Exp as at 30 June 2008 Projected Until 31/03/9 Spent)
HIV 13,848 3,462 10,386 25
NSNP 136,606 34,152 102,454 25
FET 39,099 19,550 19,549 50
Infrastructure 171,673 42,918 128,755 25
Total 361,226 100,082 261,144 36.1
13Economic Classification 2008/09 CAPEX
142008/9 1st Quarter Performance
15LIFE SKILLS
16LIFE SKILLS CONDITIONAL GRANT
Budget Allocation Expenditure R13 848 R3
462
- 926 Educators out of 3600 empowered on Sexuality,
Care and Support. - 561 Grade 10 Learners out of 2000 capacitated on
a Peer Support programme as Peer Educators. - 75 Members of SMTs out of 400 empowered on HIV AD
AIDS policy development in schools - 33 Clusters of SGBs out of 72 clusters empowered
on Life Skills HIV and AIDS related programmes. - 122 Schools out of 400 turned into Nodes of Care
and Support of Orphaned and Vulnerable Children
17Monitoring
- 15 officials monitor the implementation of the
programme by visiting the schools and submitting
reports to the Provincial office. - Regional reports are consolidated monthly and a
provincial report sent to NDoE on a monthly basis - Quarterly and Annual reports are compiled and
sent to NDoE and National Treasury - A Provincial evaluation team consisting of the
members from the 3 grants (NSNP, Life Skills and
FET Recap) conduct pre-evaluation of 10-20
schools before the final evaluation by the NDoE
is conducted at the end of each financial year. - Evaluation reports are compiled by the Provincial
evaluation team at the end of each financial
year. -
18SCHOOL NUTRITION
19National School Nutrition Programme
Budget Expenditure R136 606 R34 152
- 573 000 beneficiaries are participating in school
feeding in schools ranked within Quintile 1 to 4.
- 3 227 food handlers receive honoraria at R400 per
month. - 33 new food gardens established in schools
- The per capita expenditure is R1, 20 per learner
per day, which is lower than the R1.50 national
norm - The whole grant covers the cost of food and no
funds left for administration.
20Monitoring
- 26 NSNP monitors monitor the implementation of
the programme by visiting the schools and
submitting reports to the Provincial office. - Regional reports are consolidated monthly and a
provincial report sent to NDoE on a monthly basis - Quarterly and Annual reports are compiled and
sent to NDoE and National Treasury - A Provincial evaluation team consisting of the
members from the 3 grants (NSNP, Life Skills and
FET Recap) conduct pre-evaluation of 10-20
schools before the final evaluation by the NDoE
is conducted at the end of each financial year. - Evaluation reports are compiled by the Provincial
evaluation team at the end of each financial
year. -
21INFRASTRUCTURE
22Project Summary
Budget Number of Projects Planning Phase Current Projects Completed and closed projects Closed Projects
04/05 364 0 13 351 (113) 238
05/06 498 0 25 464 (209) 255
06/07 367 0 43 324 (207) 117
07/08 176 26 123 18 0
08/09 21 21 0 0 0
Totals 1408 47 204 1157 (547) 610
23Expenditure
Capital and Professional Fees
24MDoE Expenditure as at 30 June 2008
- Equitable shares 33.5
- Infrastructure Grant 34,3
- The overall expenditure was 33.9
- The over expenditure could be attributed to
- Payments that could not be processed before the
end of the last financial year, because of the
transition in financial systems. These were paid
in this financial year 2008/09. - Roll- over of incomplete project expenditure from
previous financial years
Source BAS
25Provision of Services
- Local Government appointed service provider under
the Water for All Flagship to provide water to
schools without water. Project to commence in
August 2008.
26IDIP Impact
- Process mapping completed
- Controls in place to monitor expenditure
- Preparation for 2007/08 and 08/09 done to reduce
implementation challenges - Training sessions conducted for skills transfer
- Alternative delivery methods under consideration
- Information not volunteered by IA now accessible
thru IDIP - Creation of project files
27Monitoring and Evaluation
- Limited internal capacity available to drive
systems - With the aid of Provincial Technical Assistant
Teams (PTATs) and Operational Support Teams
(OSTs) the monitoring capacity has improved. - The establishment of the Program Operation
Management Meetings (POMM) and the Joint
Operation Committee (JOC) which are joint
meetings of Department of Education and Public
Works established specifically for the monitoring
of infrastructure projects is working in support
of the departmental monitoring capacity. - The Department is in the process of appointing
Works Inspectors in all four regions. The impact
of those appointed could not be felt during the
first term because they were being orientated.
28FET Colleges Recapitalisation Conditional Grant
29Cost Drivers
- Curriculum development and support
- Infrastructure (upgrading and building)
- Upgrading of college sites
- Human resource development
- Development of systems and procedures
30Allocations over three years
College 2006/7 2007/8 2008/9
Ehlanzeni 8 000 13 776 12 009
Gert Sibande 7 000 11 000 15 190
Nkangala 17 000 23 499 11 900
Total 32 000 48 275 39 099
31Achievements
Performance Areas
Achievements
Curriculum development and support Infrastruc
ture (upgrading and building) Human
resource development
- Cumulative purchase of 7 Textbooks for 6854
students - 5 Computer Aided Drawing programmes
- 570 tables and chairs, 120 drawing boards, 164
computers - 3 Hostels upgraded
- 3 learner support centre developed
- 6 workshops renovated
- 12 admin offices refurbished
- Ramps built in 12 campuses
- 12 rest rooms
- 11 dormitories converted into classrooms
- 8 workshops built
- 44 Classrooms were built
- 611 staff members trained for the implementation
and support of the NC(V)
32Achievements
Performance Areas
Achievements
- Development of systems and procedures
- Equipment
- 2 Colleges connected to WAN and LAN
- Administration and Financial Systems developed in
all campuses - Websites developed for all colleges
-
- The following equipment were bought
- 40 computers, 63 data projectors, 20 White boards
30 Drawing tables, 30 drawing chairs 23
lecturers chairs 720 Audio Typing Equipment
Equipment for Engineering and related design
(L23) - Equipment and furniture for finance, economic,
accounting and office administration (L23)
Equipment for civil engineering and construction
(L23) Equipment for electrical infrastructure
construction (L23) Equipment for Information
technology (L3) - Equipment for hospitality (L2) Ehlanzeni
Tractor and ploughing equipment bought Bakkie
acquired. Nkangala Horticulture equipment bought
for Middelburg Civil Engineering equipment
bought for CN Mahlangu 10 Lathes bought for
Middelburg Auto assembly and electrical
equipment bought
332008/9 Q1 Achievements
Transfer R19 549 500 Expenditure R8 027 396
Student support Curriculum Support Resourcing Training
4329 students received Bursaries out of 4953 Student (buddy) tutoring support programme has been implemented in all colleges Exemplar assessment tasks Guidelines for assessing practical work Subject committees Provincial curriculum management committee Guidelines in managing curriculum Textbooks are available for 97 of the learners 18 classrooms, 2 workshops, 2offices and 2 store rooms completed Workshop equipment purchased 85 lecturers trained for the implementation on NC(V) Level 4
34 We Thank You