Title: Measurement and Verification Guidelines for DemandSide Management Projects
1Measurement and Verification Guidelines for
Demand-Side Management Projects
Presenter Prof. LJ Grobler (CEM) Co-Author W
den Heijer (CEM)
Measurement and Verification Capacity Building
Workshop 30,31 August, 2005.
2Challenge During Peak
3Matching Supply and Demand
4DSM Options
Consumption
5Opportunities for DSM
- Residential
- Efficient lighting initiative
- Residential hot water load control
- Insulation of houses
- Commercial
- Energy efficiency and load management
- Efficient lighting, air conditioning and water
heating - Mining / Industrial
- Process improvements
- Efficient equipment (e.g.. Motors, Pumps)
- Load control systems in conjunction with dynamic
pricing signals
6MV Requirements
- MV must be able to quantify impacts on a
- Project level
- Regional level
- National level
- Technology level
- The following stakeholders need to know what are
being achieved - Eskom (Project, Regional, National, Technology)
- NER (Project, Regional, National, Technology)
- Government (Regional, National, Technology)
- ESCo (Project)
- Client (Project)
7Background on MV
- Based on available International MV protocols
- 2000 International Performance Measurement and
Verification Protocol (IPMVP) - Measurement and Verification for Federal Energy
Project Guideline (FEMP) - A MV methodology was developed for the South
African situation - MV processes streamlined and focused on project
specific situations - MV implementation on various levels of
complexity and effort - Basis of successful energy efficiency and
demand-side management projects rest on the fact
electricity reductions can be determined to a
degree of accuracy and trust that is acceptable
to all stakeholders. - Objectives of MV
- Impartial
- Credible
- Transparent
- Quantify and assess project impacts
- Assess sustainability
8MV Interaction
- MV Stakeholders
- Eskom
- ESCo
- Client
- Task of saving assessment and quantification need
to be performed by a party outside the group of
principal project stakeholders. - MV team is active on all the levels between the
various project stakeholders.
How much have been saved and are the savings
being sustained?
9The Benefits of Effective MV
- Quantify assess savings and various impacts
- Impartial of stakeholders
- Enable Tracking and Evaluation (TE) of DSM
project performance and progress - Help to identify focus areas for DSM activities
- Identify potential problems in DSM implementation
- Evaluate DSM impacts against targets
- Help with proper implementation of DSM
- Encourage investment in projects
- Help to manage risk for stakeholders
10MV Rationale
Energy savings (Baseline energy use)
(Post-implementation energy use)
Adjustments
11MV Rationale
- Must represent energy demand and consumption for
system as it was operational and sustained prior
to the DSM intervention. - Must be accurate, dynamic, transparent,
acceptable to stakeholders.
12Project Type Commercial Lighting
13Project Type Industrial / Warehouse Lighting
14Project Type Street Lighting
15Project Type Load Shifting
16Project Type Residential Load Management
17Determine Combined Impact
Overall Picture Pre-Implementation
18Determine Combined Impact
Overall Picture Post-Implementation
19Combined Impact
20Combined Results
21DSM Project Stages
22MV Project Stages
23DSM and MV Project Interaction
PROJECT IDENTIFICATION
MV Project
ENERGY AUDIT ASSUMPTIONS
SCOPING REPORT
DEVELOP MV PLAN
RECOMMENDATIONS FOR IMPLEMENTATION
Framework, Protocols, Guidelines
Refine MV Plan
No
Did you get BUY-IN?
APPROVAL FOR FUNDING
Yes
MV BASELINE REPORT
DSM Project Stages
DETAIL DESIGN
Refine MV Baseline report
No
Measurement equipment
Did you get BUY-IN?
POST-IMPLEMENTATION REPORT
Yes
IMPLEMENTATION
PERFORMANCE ASSESSMENT
COMISSIONING
MV PERFORMANCE TRACKING MONTHLY- AND ANNUAL
SAVINGS REPORTS
OPERATION MAINTENENCE
24Impact of DSM
Pre DSM Baseline
25Daily Electricity Consumption vs. Daily Water
Sales
26What about Load Growth?
27Baseline Correlation
28Banking and Penalties
- After ESCo implemented DSM measures
- Eskom DSM issue Certificate of Completion
- Project enters Performance Assessment phase
- MV quantifies whether DSM project is delivering
intended MWs - ESCo is at risk
- Once project has demonstrated that it can deliver
risk is transferred to Client - Client is responsible for maintaining and
sustaining DSM performance - Client carries now the risk for non-performance
- Note by CTADBanking section of the MV
Guideline is under developmentand offers a
proposed methodology to address the issues of DSM
over-performance banking and underperformance
penalties by the ESCoand the client. It is not
an approved process.
29Banking and penalties
30Banking by ESCo
- Only applicable during performance assessment
phase - ESCo is responsible for payment of penalties in
case of under-performance - Client is not held responsible for penalties
- Penalties payable when achieved impact is less
than 90 of intended DSM target - Under-performance of 10 allowed without penalty
clause activation - Penalties are payable in R/MW
- Under-performance - the ESCo will pay or offset
the penalties and the intended DSM target will be
adjusted for the Client before the project enters
into its MV performance tracking phase
31Banking by ESCo
- ESCo may bank over-performance achieved in excess
of 110 of intended DSM target - Bankable over-performance is calculated as the
average MW reduction achieved during contracted
performance period in the 3-month performance
assessment period, exceeding 110 of the
projects intended DSM target - A bank balance will be kept of all over- and
under-performance of each project implemented by
each specific ESCo - The ESCo retain ownership of its bank balance
since the ESCo carries the risk of penalties
during the performance assessment period - The ESCo may offset the under-performance of any
of its DSM projects at the end of their
respective performance assessment periods from
the bank balance at its own discretion - Should the bank balance not be able to offset all
under-performance of a project, the ESCo would be
penalised in R/MW for each remaining MW that the
bank balance could not offset - The bank balance does not have overdraft
facilities - The bank balance of the ESCo is not redeemable
for additional DSM investment into a project
32Banking by Clients
- Only applicable to the Client during the MV
performance tracking phase - ESCo is held responsible for penalties during the
performance assessment period - The responsibility is transferred to the Client
after the performance assessment phase at which
time the Client is held responsible for the
payment of penalties in case of under-performance - Penalties are payable when the achieved impacts
are less than 90 of intended DSM target - Under-performance of 10 allowed without penalty
clause activation - Penalties is payable in R/MWh by the Client
- Client may claim the penalties from the ESCo in
cases where a back-to-back agreement is in place
between the Client and the ESCo - Should a project under-perform during the MV
performance tracking period, the Client will pay
or offset the penalties - The intended DSM target will not be adjusted
33Banking by Clients
- The Client may bank over-performance impacts
achieved in excess of 110 of the intended DSM
target - Bankable over-performance is calculated as the
cumulative MWh difference between intended and
achieved reduction achieved during the contracted
performance period for the duration of the MV
performance tracking phase - A bank balance will be kept of all over- and
under-performance of each project implemented on
a project site(s) of the Client - The Client retain ownership of its bank balance
since the Client carries the risk of penalties
during the MV performance tracking phase - The Client may offset the under-performance of
any of its DSM projects implemented on their
sites at an annual or bi-annual interval from the
bank balance at its own discretion - Should the bank balance not be able to offset all
under-performance of a project, the Client would
be penalised in R/MWh for each remaining MWh that
the bank balance could not offset - The bank balance does not have any overdraft
facilities - The bank balance of the Client is not redeemable
for additional DSM investment into a project
34Summary
- MV Results reported to Eskom, NER, Government,
ESCo and Clients - MV must provide results on Project-, Regional-,
National- and Technology levels - Baselines must be developed to provide reference
points in 30-min intervals for various TOU
periods - Impacts must be determined in 30-min intervals
for each of the various TOU periods - Above must be done for both load management and
energy efficiency projects - Banking of the ESCo applicable to Performance
Assessment Phase - Penalties payable on MW under performance
- Banking based on average MW reduction during
contracted performance period - Banking of Clients applicable to Performance
Tracking Phase - Penalties payable on MWh under performance
- Banking based on accumulated MWh deviation
between intended and achieved impact.
35Questions ?
36For More Information