Measurement and Verification Guidelines for DemandSide Management Projects - PowerPoint PPT Presentation

1 / 36
About This Presentation
Title:

Measurement and Verification Guidelines for DemandSide Management Projects

Description:

Overall Picture: Post-Implementation. Combined Impact. Impact. Pre-Implementation (Baseline) ... POST-IMPLEMENTATION REPORT. PERFORMANCE ASSESSMENT. DSM Project ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 37
Provided by: Gid59
Category:

less

Transcript and Presenter's Notes

Title: Measurement and Verification Guidelines for DemandSide Management Projects


1
Measurement and Verification Guidelines for
Demand-Side Management Projects
Presenter Prof. LJ Grobler (CEM) Co-Author W
den Heijer (CEM)
Measurement and Verification Capacity Building
Workshop 30,31 August, 2005.
2
Challenge During Peak
3
Matching Supply and Demand
4
DSM Options
Consumption
5
Opportunities for DSM
  • Residential
  • Efficient lighting initiative
  • Residential hot water load control
  • Insulation of houses
  • Commercial
  • Energy efficiency and load management
  • Efficient lighting, air conditioning and water
    heating
  • Mining / Industrial
  • Process improvements
  • Efficient equipment (e.g.. Motors, Pumps)
  • Load control systems in conjunction with dynamic
    pricing signals

6
MV Requirements
  • MV must be able to quantify impacts on a
  • Project level
  • Regional level
  • National level
  • Technology level
  • The following stakeholders need to know what are
    being achieved
  • Eskom (Project, Regional, National, Technology)
  • NER (Project, Regional, National, Technology)
  • Government (Regional, National, Technology)
  • ESCo (Project)
  • Client (Project)

7
Background on MV
  • Based on available International MV protocols
  • 2000 International Performance Measurement and
    Verification Protocol (IPMVP)
  • Measurement and Verification for Federal Energy
    Project Guideline (FEMP)
  • A MV methodology was developed for the South
    African situation
  • MV processes streamlined and focused on project
    specific situations
  • MV implementation on various levels of
    complexity and effort
  • Basis of successful energy efficiency and
    demand-side management projects rest on the fact
    electricity reductions can be determined to a
    degree of accuracy and trust that is acceptable
    to all stakeholders.
  • Objectives of MV
  • Impartial
  • Credible
  • Transparent
  • Quantify and assess project impacts
  • Assess sustainability

8
MV Interaction
  • MV Stakeholders
  • Eskom
  • ESCo
  • Client
  • Task of saving assessment and quantification need
    to be performed by a party outside the group of
    principal project stakeholders.
  • MV team is active on all the levels between the
    various project stakeholders.

How much have been saved and are the savings
being sustained?
9
The Benefits of Effective MV
  • Quantify assess savings and various impacts
  • Impartial of stakeholders
  • Enable Tracking and Evaluation (TE) of DSM
    project performance and progress
  • Help to identify focus areas for DSM activities
  • Identify potential problems in DSM implementation
  • Evaluate DSM impacts against targets
  • Help with proper implementation of DSM
  • Encourage investment in projects
  • Help to manage risk for stakeholders

10
MV Rationale
Energy savings (Baseline energy use)
(Post-implementation energy use)
Adjustments
11
MV Rationale
  • Must represent energy demand and consumption for
    system as it was operational and sustained prior
    to the DSM intervention.
  • Must be accurate, dynamic, transparent,
    acceptable to stakeholders.

12
Project Type Commercial Lighting
13
Project Type Industrial / Warehouse Lighting
14
Project Type Street Lighting
15
Project Type Load Shifting
16
Project Type Residential Load Management
17
Determine Combined Impact
Overall Picture Pre-Implementation
18
Determine Combined Impact
Overall Picture Post-Implementation
19
Combined Impact
20
Combined Results
21
DSM Project Stages
22
MV Project Stages
23
DSM and MV Project Interaction
PROJECT IDENTIFICATION
MV Project
ENERGY AUDIT ASSUMPTIONS
SCOPING REPORT
DEVELOP MV PLAN
RECOMMENDATIONS FOR IMPLEMENTATION
Framework, Protocols, Guidelines
Refine MV Plan
No
Did you get BUY-IN?
APPROVAL FOR FUNDING
Yes
MV BASELINE REPORT
DSM Project Stages
DETAIL DESIGN
Refine MV Baseline report
No
Measurement equipment
Did you get BUY-IN?
POST-IMPLEMENTATION REPORT
Yes
IMPLEMENTATION
PERFORMANCE ASSESSMENT
COMISSIONING
MV PERFORMANCE TRACKING MONTHLY- AND ANNUAL
SAVINGS REPORTS
OPERATION MAINTENENCE
24
Impact of DSM
Pre DSM Baseline
25
Daily Electricity Consumption vs. Daily Water
Sales
26
What about Load Growth?
27
Baseline Correlation
28
Banking and Penalties
  • After ESCo implemented DSM measures
  • Eskom DSM issue Certificate of Completion
  • Project enters Performance Assessment phase
  • MV quantifies whether DSM project is delivering
    intended MWs
  • ESCo is at risk
  • Once project has demonstrated that it can deliver
    risk is transferred to Client
  • Client is responsible for maintaining and
    sustaining DSM performance
  • Client carries now the risk for non-performance
  • Note by CTADBanking section of the MV
    Guideline is under developmentand offers a
    proposed methodology to address the issues of DSM
    over-performance banking and underperformance
    penalties by the ESCoand the client. It is not
    an approved process.

29
Banking and penalties
30
Banking by ESCo
  • Only applicable during performance assessment
    phase
  • ESCo is responsible for payment of penalties in
    case of under-performance
  • Client is not held responsible for penalties
  • Penalties payable when achieved impact is less
    than 90 of intended DSM target
  • Under-performance of 10 allowed without penalty
    clause activation
  • Penalties are payable in R/MW
  • Under-performance - the ESCo will pay or offset
    the penalties and the intended DSM target will be
    adjusted for the Client before the project enters
    into its MV performance tracking phase

31
Banking by ESCo
  • ESCo may bank over-performance achieved in excess
    of 110 of intended DSM target
  • Bankable over-performance is calculated as the
    average MW reduction achieved during contracted
    performance period in the 3-month performance
    assessment period, exceeding 110 of the
    projects intended DSM target
  • A bank balance will be kept of all over- and
    under-performance of each project implemented by
    each specific ESCo
  • The ESCo retain ownership of its bank balance
    since the ESCo carries the risk of penalties
    during the performance assessment period
  • The ESCo may offset the under-performance of any
    of its DSM projects at the end of their
    respective performance assessment periods from
    the bank balance at its own discretion
  • Should the bank balance not be able to offset all
    under-performance of a project, the ESCo would be
    penalised in R/MW for each remaining MW that the
    bank balance could not offset
  • The bank balance does not have overdraft
    facilities
  • The bank balance of the ESCo is not redeemable
    for additional DSM investment into a project

32
Banking by Clients
  • Only applicable to the Client during the MV
    performance tracking phase
  • ESCo is held responsible for penalties during the
    performance assessment period
  • The responsibility is transferred to the Client
    after the performance assessment phase at which
    time the Client is held responsible for the
    payment of penalties in case of under-performance
  • Penalties are payable when the achieved impacts
    are less than 90 of intended DSM target
  • Under-performance of 10 allowed without penalty
    clause activation
  • Penalties is payable in R/MWh by the Client
  • Client may claim the penalties from the ESCo in
    cases where a back-to-back agreement is in place
    between the Client and the ESCo
  • Should a project under-perform during the MV
    performance tracking period, the Client will pay
    or offset the penalties
  • The intended DSM target will not be adjusted

33
Banking by Clients
  • The Client may bank over-performance impacts
    achieved in excess of 110 of the intended DSM
    target
  • Bankable over-performance is calculated as the
    cumulative MWh difference between intended and
    achieved reduction achieved during the contracted
    performance period for the duration of the MV
    performance tracking phase
  • A bank balance will be kept of all over- and
    under-performance of each project implemented on
    a project site(s) of the Client
  • The Client retain ownership of its bank balance
    since the Client carries the risk of penalties
    during the MV performance tracking phase
  • The Client may offset the under-performance of
    any of its DSM projects implemented on their
    sites at an annual or bi-annual interval from the
    bank balance at its own discretion
  • Should the bank balance not be able to offset all
    under-performance of a project, the Client would
    be penalised in R/MWh for each remaining MWh that
    the bank balance could not offset
  • The bank balance does not have any overdraft
    facilities
  • The bank balance of the Client is not redeemable
    for additional DSM investment into a project

34
Summary
  • MV Results reported to Eskom, NER, Government,
    ESCo and Clients
  • MV must provide results on Project-, Regional-,
    National- and Technology levels
  • Baselines must be developed to provide reference
    points in 30-min intervals for various TOU
    periods
  • Impacts must be determined in 30-min intervals
    for each of the various TOU periods
  • Above must be done for both load management and
    energy efficiency projects
  • Banking of the ESCo applicable to Performance
    Assessment Phase
  • Penalties payable on MW under performance
  • Banking based on average MW reduction during
    contracted performance period
  • Banking of Clients applicable to Performance
    Tracking Phase
  • Penalties payable on MWh under performance
  • Banking based on accumulated MWh deviation
    between intended and achieved impact.

35
Questions ?
36
For More Information
Write a Comment
User Comments (0)
About PowerShow.com