Title: Technical Characteristics 1
1Technical Characteristics (1)
- Performance
- Fusion power amplification gt 10 with inductive
current drive (ignition not precluded). - Fusion power amplification gt 5 using
non-inductive current drive. - Typical fusion power level 500 MW
- Testing
- Integrate and test all essential fusion reactor
technologies and components. - Design
- Use existing technology and physics database to
give confidence but be able to access advanced
operational modes. - Operation equivalent to a few 10000 inductive
pulses of 300-500 s. - Average neutron flux 0.5 MW/m2
- Average fluence 0.3 MWa/m2
2Technical Characteristics (2)
- Operation
- Address all aspects of plasma dominated by alpha
particle (helium) heating through burning plasma
experiments. - Low fluence functional tests of DEMO-relevant
blanket modules early high reliability tests
later. - Device operation 20 years. Tritium to be
supplied from external sources.
3ITER Parameters
- Total fusion power 500 MW (700MW)
- Q fusion power/auxiliary heating power 10
- Average neutron wall loading 0.57 MW/m2 (0.8
MW/m2) - Plasma inductive burn time 300 s
- Plasma major radius 6.2 m
- Plasma minor radius 2.0 m
- Plasma current (Ip) 15 MA (17.4 MA)
- Vertical elongation _at_95 flux surface/separatrix 1
.70/1.85 - Triangularity _at_95 flux surface/separatrix 0.33/0
.49 - Safety factor _at_95 flux surface 3.0
- Toroidal field _at_ 6.2 m radius 5.3 T
- Plasma volume 837 m3
- Plasma surface 678 m2
- Installed auxiliary heating/current drive
power 73 MW (100 MW)
4Inductive Operation (1)
The figure shows observed energy confinement time
(s) in various experiments versus value derived
from the scaling law
tE,th 0.0562 HH Ip0.93 BT0.15 P-0.69 ne0.41
M0.19 R1.97 e0.58 Ka0.78
where Ip plasma current (MA) BT on-axis
toroidal field (T) P internal external
heating power (MW) ne electron density
(1019m-3) M atomic mass (AMU) R major
radius (m) e inverse aspect ratio
(a/R) KaSo/pa2, So plasma x-sectional area.
HH, the confinement time enhancement factor,
measures the quality of confinement ( 1 for the
dotted line in the figure).
5Inductive Operation (2)
Fusion power (Pfus) versus auxiliary power (Paux)
for a range of currents and for HH 1 and
ne/nGreenwald 0.85. Minimum fusion power is
limited to a factor 1.3 above the expected power
at which transition to L-mode would occur, namely
PLH 0.75 M-1 BT0.82 ne0.58 R1.00 a0.81
6Inductive Operation (3)
- Flexibility in reaching Q10
The combination of a range of plasma parameters
will allow Q10 to be obtained. The figures show
the operational domain in terms of fusion power
and HH, plus the various limiting boundaries that
are thought to apply. Q10 is maintained
within the shaded region by adjusting auxiliary
power and density.
7Inductive Operation (4)
The results show the flexibility of the
design, show its capacity to respond to
factors that degrade confinement, show its
ability to maintain the goal of extended burn
Q10 operation, imply the ability to explore
higher Q operation, provided energy confinement
times consistent with the confinement scaling are
maintained.
8Steady State/Hybrid Operation
Hybrid modes of operation are being evaluated as
a promising route towards establishing true
steady-state modes of operation. There, in
addition to inductively driven current, a
substantial fraction of the plasma current is
driven by external heating and the bootstrap
effect, leading to extension of the burn
duration. This form of operation would be well
suited to systems engineering tests. For a given
value of fusion power (and hence Q), as the
confinement enhancement factor, HH, increases
(simultaneously decreasing plasma density and
increasing bN), the plasma loop voltage falls
towards zero. For example, operation with
Vloop 0.02 V and Ip 12 MA, which corresponds
to a flat-top length of 2500 s, is expected at HH
1, Q 5, ne/nGreenwald 0.7, and bN 2.5.
True steady-state operation at Q 5 can be
achieved with HH 1.2 and bN 2.8.
- Operation space for Ip 12 MA and PCD 100 MW,
in terms of fusion power versus confinement
enhancement factor, and the transition from
hybrid to true steady-state operation.
9Design - Main Features (1)
Central Solenoid
Blanket Module
Vacuum Vessel
Outer Intercoil Structure
Cryostat
Toroidal Field Coil
Port Plug (EC Heating)
Poloidal Field Coil
Machine Gravity Supports
Torus Cryopump
10Design - Main Features (2)
- Superconducting toroidal field coils (18 coils)
- Superconductor Nb3Sn in circular stainless
steel (SS) jacket in grooved radial plates - Structure Pancake wound, in welded SS case,
wind, react and transfer technology - Superconducting Central Solenoid (CS)
- Superconductor Nb3Sn in square Incoloy jacket,
or in circular Ti/SS jacket inside SS
U-channels - Structure Pancake wound, 3 double or 1
hexa-pancake, wind react and transfer
technology - Superconducting poloidal field coils (PF 1-6)
- Superconductor NbTi in square SS conduit
- Structure Double pancakes
- Vacuum Vessel (9 sectors)
- Structure Double-wall welded ribbed shell,
with internal shield plates and
ferromagnetic inserts - Material SS 316 LN structure, SS 304 with 2
boron
11Design - Main Features (3)
- First Wall/Blanket (421 modules) (Initial DT
Phase) - Structure Single curvature faceted separate FW
attached to shielding block which is fixed
to vessel - Materials Be armour, Cu-alloy heat sink, SS
316 LN structure - Divertor (54 cassettes)
- Configuration Single null, cast or welded
plates, cassettes - Materials W alloy and C plasma facing
components, copper alloy heat sink, SS 316
LN structure - Cryostat
- Structure Ribbed cylinder with flat ends
- Maximum inner dimensions 28 m diameter, 24 m
height - Material SS 304L
- Heat Transfer Systems (water-cooled)
- Heat released in the tokamak duringnominal
pulsed op. 750 MW at 3 and 4.2 MPa water
pressure, 120C
12Design - Main Features (4)
- Cryoplant
- Nominal average He refrig. /liquefac. rate for
magnets divertor cryopumps (4.5K) 55 kW
/ 0.13 kg/s - Nominal cooling capacity of the thermal shields
at 80 K 660 kW - Additional Heating and Current Drive
- Candidate systems Electron
Cyclotron, Ion Cyclotron, Lower Hybrid ,
Negative Ion Neutral Beam - Electrical Power Supply
- Pulsed Power supply from grid total
active/reactive power demand 500 MW / 400 MVAr - Steady-State Power Supply from grid total
active/reactive power demand 110 MW/ 78 MVAr
13Design - Magnets and Structures (1)
- The superconducting magnet system has three main
subsystems - 18 toroidal field (TF) coils which produce the
confining/stabilizing toroidal field - 6 poloidal field (PF) coils which contribute to
the plasma positioning and shaping - a central solenoid (CS) coil which provides the
main contribution to inducing current in the
plasma. - Correction coils (located above, outboard of and
below the TF coils) are also required to correct
error fields that arise due to imperfections in
the actual PF and TF coil configuration, and to
stabilize the plasma against resistive wall mode
instabilities. - The magnet system weighs, in total, about 8,700
t.
14Design - Magnets and Structures (2)
- The CS and TF coils use Nb3Sn as superconductor,
and the technology of wind, react and transfer,
whereas the PF and correction coils use NbTi. All
coils are cooled by supercritical helium at
4.5K. - The TF coil case is the main structural component
of the magnet system and the machine core. The
PF coils and vacuum vessel are linked to the TF
coils such that all interaction forces are
resisted internally in the system. - The TF coil inboard legs are wedged all along
their side walls in operation and they are all
linked at their two ends to two strong coaxial
rings which provide toroidal compression and
resist the local de-wedging of those legs under
load. - At the outboard leg, the out-of-plane support is
provided by intercoil structures integrated with
the TF coil cases.
15RD - CS Model Coil (L-1) (1)
- Objectives
- verify conductor performance under
ITER-relevant conditions - demonstrate the major steps in manufacturing
the conductor and ITER CS coil. - The main coil consists of two modules nested
inside each other. To test conductor,insert
coils can be fitted within its bore. Three
insert coils relevant for ITER are foreseen. - Significant advances on present superconducting
coil manufacturing technology were required - substantial quantities of Nb3Sn strand to a
uniform quality - jacketing of a cable of this strand to provide
structural support against magnetic forces - accurate conductor bending to the winding
shape - heat treatment in a controlled atmosphere,
insulation in an unspringing process before
stacking to form the winding, and then
impregnation with epoxy resin.
16RD - CS Model Coil (L-1) (2)
Outer module, manufactured by Toshiba, being
placed outside the inner module, which has
already been installed in the vacuum chamber.
- Transfer of a layer onto a coil assembly to form
the inner module at Lockheed Martin.
17RD - CS Model Coil (L-1) (3)
In April 2000, the maximum field of 13 T with a
cable current of 46 kA and magnetic stored energy
of 640 MJ were successfully achieved in the test
facility. Pulsed operation has been experienced
under conditions (ramp-up to 13 T at 0.4 T/s,
ramp-down at 1.2 T/s) more severe than for
ITER-FEAT operation. One insert coil has been
tested at 13 T and charged/discharged 10,000
times. More tests are underway.
- Model coil and insert coil installed at the test
facility in JAERI Naka. In the background is the
vacuum chamber lid.
18RD - TF Model Coil (L-2) (1)
- Objective
- validation of design and analysis,
- demonstration of industrial manufacturing
methods, - testing of performance of each component
integrated in the magnet, - testing and demonstration of reliable
operation. - The model consists of a race-track shaped
sub-size coil, about 4 m high and 3 m wide, and
two full-size sections of the outer housing. The
coil includes the key technical features and
manufacturing approaches foreseen for the actual
ITER TF coils. - Although the conductor will not be fully tested
for superconducting properties (done in L-1) the
manufacturing defines appropriate tolerance
targets, procedures and quality control steps.
The test of the sub-size coil will create
realistic magnetic loads to demonstrate the
structural concept.
19RD - TF Model Coil (L-2) (2)
- Conductor after heat treatment, opened out by
unspringing to give space to wrap with
insulation without damaging the superconductor.
The insulation has been applied to the lower
turns. (Ansaldo Energia)
Machining of the radial plate which reinforces
the conductor. The conductor is fitted into
grooves in this plate. (Mecachrome/Nöll)
20RD - TF Model Coil (L-2) (3)
- The top of the groove is closed by a cover plate
which is laser welded into position. (RTM)
Inner leg case section during forging as a hollow
tube, before cutting into two U sections. (Kind)
21RD - TF Model Coil (L-2) (4)
The model coil is about to be moved to the TOSKA
facility at Karlsruhe, Germany, which has been
adapted to accommodate the coil and its test
programme.
- The coil with the final surface finish (sand
blasted and with interface surfaces machined)
while it is leak tested and the inlet headers are
preassembled on top of the coil (Alstom).
22Design - Vessel, Blanket Divertor (1)
- The double-walled vacuum vessel is lined by
modular removable components, including blanket
modules composed of a separate first wall mounted
on a shield block, divertor cassettes, and
diagnostics sensors, as well as port plugs such
as the limiter, heating antennae, and test
blanket modules. All these removable components
are mechanically attached to the VV. - These vessel and internal components absorb most
of the radiated heat from the plasma and protect
the magnet coils from excessive nuclear
radiation. This shielding is accomplished by a
combination of steel and water, the latter
providing the necessary removal of heat from
absorbed neutrons. A tight fitting configuration
of the VV to the plasma aids the passive plasma
vertical stability, and ferromagnetic material in
the VV located under the TF coils reduces the TF
ripple and its associated particle losses.
23Design - Vessel, Blanket Divertor (2)
- The initial blanket acts solely as a neutron
shield, and tritium breeding experiments are
confined to the test blanket modules which can be
inserted and withdrawn at radial equatorial
ports. The blanket module design consists of a
separate faceted first wall (FW) built with a Be
armour and a water cooled copper heat sink
attached to a SS shielding block. This minimises
radioactive waste and simplifies manufacture. The
blanket is cooled by channels mounted on the
vessel. - The divertor is made up of 54 cassettes. The
target and divertor floor form a V-shape and the
large opening between the inner and outer
divertor legs to allow an efficient exchange of
neutral particles. These choices provide a large
reduction in the target peak heat load, without
adversely affecting helium removal. - The current design uses carbon at the vertical
target strike points. Tungsten is being
considered as a backup, and both materials have
their advantages and disadvantages. The best
judgement of the relative merits can be made by
the time of procurement. Carbon has the best
behaviour to withstand large power density pulses
(ELMs, disruptions), but gives rise to tritiated
dust. Procedures for the removal of tritium
codeposited with carbon by a number of schemes
are under consideration and need further
development.
24RD - Vacuum Vessel (L-3) (1)
- Objective
- To provide input required to complete the design,
especially regarding critical issues of
fabrication technology dimensional accuracy,
welding distortions and achievable tolerances. - The ITER vessel will be more than twice the
linear dimensions and over 16 times the mass of
the largest existing tokamak vessel. The key
issues can only be properly resolved by building
a model at full scale. - The dominant feature of the project is a
full-scale sector model (sized for the larger
1998 ITER design), manufactured by the Japanese
Home Team. Hitachi and Toshiba each built half
sectors. The distributed manufacturing offered
opportunities to test and compare different
candidate weld schemes. - After the half sectors were fabricated, they were
leak, pressure and mechanically tested to
determine their structural characteristics. The
welding together of the two half sectors
demonstrated the automatic welding techniques and
verified the ability to undertake joint
inspection by ultrasonic testing. - In parallel, the Russian Federation Home Team
manufactured a full-scale model equatorial port
extension, developing and demonstrating
fabrication technologies to the required
specifications and tolerances and related
inspection techniques and procedures. The US Home
Team developed a fully remotized welding/cutting
system. This technology has now been transferred
to the Japanese Home Team and has been used to
join the port extension to the sector model.
25RD - Vacuum Vessel (L-3) (2)
- View of full-scale sector model of ITER vacuum
vessel completed in September 1997 with
dimensional accuracy of 3 mm
26RD - Vacuum Vessel (L-3) (3)
- Field joint welding test of VV sector
27RD - Vacuum Vessel (L-3) (4)
- Equatorial port extension shipped from RF to the
test site at JAERI Naka for integration test
Inner shell welding demonstration using full
scale sector and port extension
The manufacture of the full-scale sector of the
1998 ITER design gives a sound basis for the
present design. To reduce the vessel fabrication
cost, forging, powder HIPing and/or casting is
being investigated particularly for the blanket
module support housings.
28RD - Blanket Module (L-4) (1)
- Objectives
- to develop and fabricate prototype components
for the shielding blanket, in order to assess
their manfacturing feasibility, - to assemble them together and develop bolting,
welding and cutting tools for the remote removal
of the components, - demonstrate the performance by testing
representative parts of the components under
relevant conditions, - obtain confirmation of the design choices by
results from accompanying RD on materials,
joining techniques and neutronics using a fast
neutron source. - Full scale prototypes include multi-layered first
walls made of stainless steel (as structural
material), copper alloy (as heat sink) and Be or
C (as protection material), massive stainless
steel shields and flexible supports. - The feasibility of installation and removal of a
blanket module with mechanical attachments has
been demonstrated and tested in a prototype
assembly. A hydraulic, remotely driven bolting
tool has been developed, which achieves high
pre-loading using heating rods. High quality
remotized hydraulic laser-welded connections have
also been made through a 30 mm penetration hole
in the front of the module.
29RD - Blanket Module (L-4) (2)
- Joining Techniques
- Be/Cu joints of high heat flux components (e.g.
limiter) fast amorphously CuInSiNi-brazed small
tiles on curved Cu surface (RF), withstood 4500
cycles at 12 MW/m2. - Be/Cu joints of lower heat flux components
(e.g. first wall) hot isostatic pressing (HIP)
of Be tiles with Ti interlayer at (EU), withstood
13000 cycles at 0.7 MW/m2. - Joining of Cu/SS parts with high
precisionsolid-solid HIP of the first wall (e.g.
JA) withstood 2500 cycles at up to 7 MW/m2.
30RD - Blanket Module (L-4) (3)
31RD - Blanket Module (L-4) (4)
Flexible supports (RF)
Shield block prototype - powder HIP (EU)
Assembly test rig (EU)
In the frame of this RD, innovative technologies
have been developed and existing technologies
have been improved, giving confidence in the
feasibility and robustness of the chosen blanket
design.
Module cut for inspection (JA)
Port Limiter (RF)
32RD - Divertor Cassette (L-5) (1)
- Objective
- To develop the technology needed to construct
full-scale armoured components capable of
providing adequate armour, armour-heat sink joint
(CfC-Cu W-Cu), and heat sink lifetime, and
sustaining thermo-hydraulic and
electro-mechanical loads, whilst utilising the
most cost effective and reliable manufacturing
processes. - Major issues include
- the bonding of different plasma facing
materials on the same component, - the selection of the heat sink material (CuCrZr
now preferred), and the - demonstration that it maintains its properties
after manufacturing.
33RD - Divertor Cassette (L-5) (2)
Results of CfC/Cu high heat flux component testing
- Component test results shows that various tile
geometries can meet the ITER requirements.
However, the monoblock has proved to be the most
reliable with no complete detachment of tiles.
Tungsten brush type armour proved to be a
solution to having a Cu-W joint able to withstand
the large difference in thermal expansion of the
two materials under the high heat flux loads.
34RD - Divertor Cassette (L-5) (3)
CfC monoblock and W brush armoured vertical
target (EU)
- W and Be armour fast brazing to liner CuCrZr heat
sink (RF)
Pure Cu-clad DSCu tube armoured vertical target
with saddle block CfC and CVD-W armours (JA).
35RD - Divertor Cassette (L-5) (4)
An additional aim of the project was to integrate
key plasma facing components together onto a
realistic prototype of the cassette body.
Following the decision of the US to pull out of
ITER, the EU has also constructed an integration
prototype. It is not essential to use all the
real materials for these prototypes, and dummy
components have been made - thermohydraulic
equivalents of the real components.
- Outboard integration mockup prior to installation
of liner (EU)
Inboard divertor channel integration mockup
undergoing flow tests (US)
Several middle and large scale CfC and W-armoured
divertor mock-ups have been successfully tested
at heat fluxes 20 MW/m2 x 1000 cycles, which is
consistent with ITER operational needs.
36Design - In-vessel Remote Handling
Systems near the plasma will become radioactive
and will require remote maintenance, with special
remote handling equipment. An in-vessel
transporter system is used for the removal and
reinstallation of blanket modules, multifunction
manipulators for divertor cassette removal, and
specialised manipulators to handle vacuum vessel
port plugs. Special casks, which dock
horizontally to the access ports of the vacuum
vessel, are designed to house such equipment and
to transport radioactive items from the tokamak
to the hot-cell where refurbishment or waste
disposal operations can be carried out. Docking
of these casks to the vessel and the hot cell
flanges is tight, to avoid spreading of
contamination. Hands-on assisted maintenance is
used wherever justifiable, following the ALARA
principles.
- The remote handling strategy for ITER has been
confirmed by a comprehensive RD programme which
has successfully demonstrated that key
maintenance operations such as blanket and
divertor replacement can be achieved using common
remote handling technology. - Several crucial issues such as vacuum vessel
remote cutting and re-welding, viewing, materials
and components radiation hardness have been
addressed and demonstrated.
37RD - Blanket Remote Handling (L-6) (1)
- Objective
- To develop and demonstrate the ability to
remotely maintain blanket modules, including
manipulating a 4 t module at a distance of 8 m
with an accuracy of 2 mm. A rail-mounted
vehicle system has been developed to handle the
heavy blanket module within the limited space and
with the required precision. - After development and prototype demonstration of
the main systems and techniques, full-scale
testing and verification were successfully
completed in 1998 on the Blanket Test Platform
(BTP) constructed at JAERIs Naka laboratory. - This platform comprises module handling
equipment, port handling equipment, auxiliary
remote handling tools and a blanket mock-up
structure to reproduce the physical environment
of a 180 ITER in-vessel region. A suppression
control system to reduce dynamic deflection and
vibration of the arm to negligible levels has
subsequently been developed and successfully
tested. - The blanket on ITER requires very precise
positioning ( 0.25 mm) with respect to keys and
pins. Module insertion tests have therefore been
carried out to check the ability to handle
misalignments between modules and keys during
installation. The module has been successfully
inserted with a misalignment of 10 mm, using the
passive compliance of the manipulator, and
chamfered keyways. Development of a sensor-based
control system with this positioning accuracy is
now underway. - Tests also show that the rail can be deployed 90
around the torus in about 30 minutes.
38RD - Blanket Remote Handling (L-6) (2)
- In-vessel transporter design
Rail-mounted vehicle and telescopic arm
39RD - Blanket Remote Handling (L-6) (3)
40RD - Divertor Remote Handling (L-7) (1)
- Objective demonstrate that the following
operations are feasible - replacing and refurbishing all or individual
divertor components several times during the
machine life - positioning high heat flux components (HHFCs)
so the maximum step between those on adjacent
cassettes would be under 4 mm and the maximum
variation around the whole torus would be within
10 mm - locking and securing the supports, making water
pipe connections, assembling electrical
connectors, and handling port plugs - replacing all cassettes in less than 6 months
and replacing a single cassette in under 8 weeks.
- Two full-scale test facilities - the Divertor
Test Platform (DTP) and the Divertor
Refurbishment Platform (DRP) - have been set up
at the ENEA Research Centre of Brasimone (Italy).
- The key elements of the divertor maintenance
procedure are - radial insertion of the cassettes from the
chamber, - toroidal manoeuvring,
- lowering of cassettes into position on wheeled
and jacking forks, - remote attachment to rails.
41RD - Divertor Remote Handling (L-7) (2)
- Tests on the DTP confirm
- the maintenance concept,
- its integration inside the vessel,
- accuracy of cassette positioning,
- adequacy of nominal gaps and tolerances,
- payload capabilities.
- Improvements are being investigated to reduce
costs and to implement lessons learnt in the
early tests to improve man-machine interface,
sensors, and time, as well as to improve sliding
components and to investigate rescue scenarios if
components become jammed. - The DRP is for simulating the most critical
operations to be undertaken in the hot cell. Only
those parts of the mock-up which are critical for
HHFC mounting have been machined accurately.
Tests so far show that the remote measurement
system can be operated accurately enough (0.01
mm) that components can be correctly machined to
fit. A target mockup has been installed on the
cassette with the required accuracy, but further
work is needed to streamline procedures to
shorten the time taken.
42RD - Divertor Remote Handling (L-7) (3)
43RD - Divertor Remote Handling (L-7) (4)
- Divertor Refurbishment Platform