Title: The National Energy SuperGrid
1The National Energy SuperGrid Value
Implementation
- Chaim Braun
- Presentation at the
- National Energy SuperGrid Conference
- Palo Alto, CA
- November 6-8, 2002
2The National Energy SuperGrid
3The National Energy SuperGrid Value Summary
- The Energy SuperGrid, by providing enhanced
inter-regional transmission interconnections,
will - Improve reliability of national transmission
system - Improve reliability of electricity supply
(limited increase in reserve margins) - Allow diurnal shifting of wholesale generation
blocks - Optimize regional power plants generating mixes
- Support transition to nuclear and renewable
energy technologies
4The National Energy SuperGrid Value Summary
(Cont.)
- Provide Regional Energy Storage capability
(Backup reserve margin) - Reduce electric price volatilities
- Reduce consequences of fossil fuels burning
- Support production of nuclear electrolytic
hydrogen - Support future transition to Hydrogen economy
- Provide long-distance tunnel- based
transportation corridors
5The National Energy SuperGrid Transition to New
Industry Structure
- Transition to new RTOs regime irreversible
- Transition resulting in loss of local vertical
market power, reduced control of future of
utility organization - Evolving National SuperGrid supports increased
regional interconnectivity and horizontal
re-aggregation - Emerging new power, wires, organizations could
use the SuperGrid to regain control of their
destiny through horizontal integration
6Regional Transmission Organizations in Operation
or Under Discussion (FERC 2002)
7The National Energy SuperGrid Relieving
Intermediate-Term Transmission Bottlenecks
- Near-term transmission fixes implemented by 2010
- National SuperGrid can provide new demonstration
projects in the 2020s time frame - A potential Eastern Interconnection SuperGrid
demonstration opportunity - enhancing
transmission link between PJM Interconnection and
NYISO - A potential Western Interconnection SuperGrid
demonstration opportunity - further expanding
Path 15 in California beyond the third 500 KV AC
overhead line - Energy SuperGrid will allow back-to-back AC-DC-AC
interlinking of neighboring RTOs (TVA-ECAR,
SERC(Southern) FRCC)
8The National Energy SuperGrid Relieving
Intermediate-Term Transmission Bottlenecks in the
Eastern Interconnection
9Regional System Interconnections NYISO
10Main Transmission Tie-Lines Between PJM
Interconnection and NYISO
11Power Transfer (MW) Histogram on the Branchburg
(PJM) Ramapo (NYISO) Line
12Power Transfer Levels (MW) Going East on the
Branchburg (PJM) Ramapo (NYISO) Line
13Power Transfer (MW) Frequency Distribution on the
Branchburg (PJM) Ramapo (NYISO) Line
14Power Transfer (MW) Histogram on the Three PJM
East New York City Tie Lines
15Power Transfer (MW) Frequency Distribution on the
Three PJM East New York City Tie Lines
16Regional System Interconnections U.S.
Southeast
17The National Energy SuperGrid Relieving
Intermediate-Term Transmission Bottlenecks in the
Western Interconnection
18The National Energy SuperGrid Economics
- Financing the National SuperGrid should be based
on selling U.S. Government (USG) bonds - Funding method similar to financing the Federal
Highway System - SuperGrid will be incrementally constructed
(spatially temporally) - A 500 KV overhead AC line costs 1.2 Million
/Mile, and requires 175 Feet of corridor width.
(NTGS) Transcontinental overhead AC line would
cost upwards of 4 Billion Dollars - Superconducting transmission lines could cost a
factor of 5-10 above cost of overhead lines - Full implementation of National SuperGrid require
several decades - Annual Budgetary impacts manageable
19The National Energy SuperGrid Benefits
- The National Energy SuperGrid benefits, over
time, will exceed implementation costs. Benefits
could include - Increase energy independence
- Reduce environmental consequences of fuels
extraction, refining, and transportation - Reduce fossil pollutant emissions from automotive
vehicles - Reduce fossil power plants pollutants emissions,
control costs, societal damages - Provide national security value by
- Compensating for regional electric supply
disruptions - providing alternative secure transportation
routes, using system of underground tunnels
20The National Energy SuperGrid - Reduced Demand
for Long Distance Fossil Fuels Transport Networks
- The National Electric SuperGrid could
additionally - Reduce need for Northern expansion of natural gas
pipeline network, from South Central region - Avoid need for large natural gas pipelines
construction from Canadian Rockies to U.S.
Midwest - Reduce need for oil, and natural gas imports from
Mexico - Avoid transporting coal by unit trains from
Powder River Basin, Mn, to Midwestern power
plants -
- Resolve the argument between electric utilities,
railroad companies, over coal by wire vs. coal
by rail in favor of the electric utilities - Lower coal hauling rates by railroads for
non-electric applications
21The National Energy SuperGrid Savings to
National Economy
- The accumulated savings related to implementation
of the Energy SuperGrid, will accrue from - Rationalizing generation transmission systems
- Reducing economic consequences of electricity
supply disruptions - Increasing electrification of the national energy
economy - Reducing price volatilities, increasing energy
prices stability - Increasing national energy independence
(political economic) - Reducing price pressures on fossil fuels
(Non-electric sector) - Providing lower costs electricity to all consumer
classes - Reducing the need for expanding alternative
energy infrastructure networks - Reducing costs of pollutant emissions from,
legacy fossil plants - Providing commodity electrolytic hydrogen
(Chemical, transportation sectors) - Such savings are not easily quantified, but will
accrue over time, exceeding the higher initial
costs of constructing the National Energy
SuperGrid
22The National Energy SuperGrid Risk of No Action
- Avoiding commitment to the National Energy
SuperGrid could result in - Perpetuating limited interconnectivity of
national electricity system and reduced
reliability of supply - Less than optimal regional generation mixes,
higher economic costs - Continued higher electric price volatilities
- Lack of regional electric energy storage
- Reduced penetration of nuclear renewable power
plants - Continued dependence on imported fossil fuels
(political, economic, security uncertainties) - Continued large scale pollutants emissions from
fossil power plants - Delayed transition to the hydrogen economy
23The National Energy SuperGrid
24The National Energy SuperGrid Relation to
Current Studies
- The Energy SuperGrid concept represents an
evolutionary extension of missions identified in - - The National Transmission Grid Study (NTGS)
- - The Transmission Grid Solutions study of the
DOEs Electricity Advisory Board - - Vice President Cheneys National Energy Policy
Report (NEPR) - - The Draft Hydrogen Economy Roadmap Study
- National Energy SuperGrid will be a
Federally-supported overlay to new RTO electric
grids - Current studies propose transmission grid
solutions for the next two decades.
Implementation of the National SuperGrid concept
will extend over several decades, building on
progress achieved in implementing recommendation
of current studies
25The National Energy SuperGrid Implementation by
Extension of Current Grids
- Implementation of the Energy SuperGrid concept
requires large scale engineering development.
Does not depend on new scientific breakthroughs - Large scale oil and natural gas pipeline already
exists. Limited hydrogen pipeline system now in
operation in U.S. and in Europe - Full scale implementation of the National Energy
SuperGrid will extend over several decades. -
- Annual impacts on the national budget will be
manageable - Energy SuperGrid will be the electric analog of
Federal Highway System - Energy SuperGrid has twice longer components
lifetime than current fossil power plants and
overhead transmission lines. - Energy SuperGrid concept could provide organizing
principle for large scale energy RD program
26U.S. Pipeline Technology That Hydrogen Can Build
On
Oil Pipelines
27The National Energy SuperGrid Funding Options
- The National Energy SuperGrid could be based on
regional, for profit, regulated, independent
transmission companies (ITCs) - ITCs will plan, finance, construct operate
SuperGrid transmission assets - Transmission assets could be funded from sale of
tax-exempt Federal and State bonds - ITC Ratemaking will be based of performance based
regulatory (PBR) approach -
- A price structure for SuperGrid transmission
services could include - - Fixed Access Charge on loads guaranteeing firm
capacity reservation - - Congestion Charge on generators injecting MW
into the SuperGrid - - Energy Transfer Charge on each MWh delivered
- All access and energy charges be price-capped and
adjusted for regulatory lags through PBR review
28The National Energy SuperGrid Funding Options
(Cont.)
- An early example of a for-profit ITC is the
American Transmission Company (ATC), established
on January 1, 2001, owning transmission
facilities in Wisconsin, Michigan Illinois,
with book value in excess of 500 Million Dollars.
ATCs transmission lines construction budget
till 2004 is 100 Million /Year. - For-profit ITCs could subcontract construction of
new lines in their systems to merchant
transmission companies, such as the proposed
Neptune Project that will connect Atlantic Canada
to New England, New York PJM, through 4,800 MW
high voltage direct current (HVDC) line. - Another proposed for-profit merchant transmission
project is the TransAmerica Grid, planning to
link mine-mouth coal-fired plants in Wyoming
through long distance DC lines to load centers in
the Chicago and Los Angeles areas - For-profit Merchant transmission projects could
by compensated by granting them rights to issue
Firm Transmission Rights (FTRs) (Capacity
reservations) on their line segments. FTR charges
should remain within the price ceilings
established by the PBR rate-setting process
29The National Energy SuperGrid New Plants
Interconnection to the Grid
- Construction of new nuclear and renewable power
plants connected to the National Energy
SuperGrid, could be initiated by large
utility/power developers/vendors consortia,
granted preferential terms Power Purchase
Agreements (PPAs), issued by large end-user
organizations, such as the USG, State
Governments, regional utilities, or direct
customers (Bilateral contracts) - The National superconducting SuperGrid will allow
direct power purchase contracting among further
removed plant owners and end-users, than would be
the case with the current AC transmission
networks, due to the SuperGrid ability to
transfer large power blocks over longer distances
with minimum losses - Preferential Term PPAs could provide electricity
sales prices incrementally higher than prevailing
regional market clearing prices (MCPs), for a set
period of years early in the plants operating
life. The early in life incremental revenues
above regional MCPs would be returned, with
interest, later in plants life, once generating
costs decline below prevailing market prices,
profitability improves, and the plant generates
adequate cash flows
30The National Energy SuperGrid Regional Energy
Transfers
- The National Energy SuperGrid will allow
large-scale inter-regional bulk power transfers,
corresponding to diurnal demand variations (East
to West transfers), and seasonal demand
variations (North-South transfers). Examples
could include - East to West inter-regional bulk power transfers
following diurnal peak demand variation among
time zones - South to North interconnection between the TVA
and So.ECAR North to South interconnection from
the TVA and Southern Company into FRCC - North-South seasonal transfer in the Midwest.
East North Central region - winter peaking
(Chicago, IL). East South Central region - summer
peaking (Dallas, TX) - North-South seasonal power transfers along
Pacific Coast. Pacific Northwest has excess hydro
generation during winter and spring seasons.
Southwest and California have excess capacity
during late summer and fall seasons