Title: Chapter 3' Project Management
1Chapter 3. Project Management
- A project is series of related jobs usually
directed toward some major output and requiring a
significant period of time to perform - Building a bridge
- Project Management
- The management activities of planning, directing,
and controlling resources (people, equipment,
material) to meet the technical, cost, and time
constraints of a project. - A systematic approach to plan and control
projects that are somewhat unique. - Structuring Projects
- Work Breakdown Structure
- Project Control Charts
- Critical Path Scheduling
- CPM with a Single Time
- CPM with Three Activity Time Estimates (a.k.a.
PERT)
2Different organizational approaches
- Functional Project
- Team member can work on several
projects.Technical expertise is maintained within
the functional area. - The functional area is a home after the project
is completed. - Critical mass of specialized knowledge
- BUT motivation of team members is often weak.
- Needs of the client are secondary and are
responded to slowly.
- Matrix
- Enhanced inter-functional communications.
- Pinpointed responsibility.
- Duplication of resources is minimized.
- Functional home for team members.
- Policies of the parent organization are followed
- BUTToo many bosses.
- Depends on project managers negotiating skills.
- Potential for suboptimization.
- Pure Project
- The project manager has full authority over the
project - Team members report to one boss
- Shortened communication lines, etc
- A BUTthere are some disadvantages
- Duplication of resources
- Organizational goals and policies are ignored.
- Team members have no functional area "home
3Work Breakdown Structure
- WBS is a hierarchical structure to organize
activities (tasks). - The simple goal is to identify what must be done
to complete the project. - Breakdown the complex project into smaller and
manageable tasks. - Establish resource requirements, time estimates,
and precedence for all tasks at the lowest level.
4Network-Planning Models
- A project is made up of a sequence of activities
that form a network representing a project. - The path taking longest time through this network
of activities is called the critical path. - The critical path provides a wide range of
scheduling information useful in managing a
project. - Critical Path Method (CPM) helps to identify the
critical path(s) in the project networks. - CPM with a Single Time Estimate
- Used when activity times are known with
certainty. - Used to determine timing estimates for the
project, each activity in the project, and slack
time for activities. - CPM with Three Activity Time Estimates (a.k.a.
PERT) - Used when activity times are uncertain.
- Used to obtain the same information as the Single
Time Estimate model and probability information. - Time-Cost Models
- Used when cost trade-off information is a major
consideration in planning. - Used to determine the least cost in reducing
total project time.
5Example 1. CPM with Single Time Estimate
Consider the following consulting project
- Develop a critical path diagram (network) and
determine the duration of the critical path and - slack times for all activities
- Draw the network
- Compute early starts and early finish times
(forward pass) - Compute late starts and late finish times
(backward pass) - Compute Slack (LS-ES) per activity and Critical
Path(s)
6Example 2. CPM with Three Activity Time Estimates
Compute the expected time and variance for each
activity
- Develop a critical path diagram (network) and
determine the duration of the critical path and - slack times for all activities
- Draw the network
- Compute early starts and early finish times
(forward pass) - Compute late starts and late finish times
(backward pass) - Compute Slack (LS-ES) per activity and Critical
Path(s) - What is the probability of finishing this project
in less than 53 days? - What is the probability that the project duration
will exceed 56 days?
More about the bridge ? Gantt Charts
7What is the probability of finishing this project
in less than 53 days?
t
8Time-Cost Models
- Sometimes it is possible to "crash" (expedite)
some activities thus reducing the overall
completion time for the entire project. - Crashing an activity implies spending additional
funds (e.g., overtime costs, hiring more workers,
and so on) to get the task done earlier. - On many occasions reducing the project completion
time that in turn reduces the fixed cost outlays
can generate substantial savings. - Draw the CPM network, identify the CP
- Identify the least cost activity(ies) on the
critical path(s) - Shorten the project completion time (CP) at the
least cost - Repeat until no more crashing is possible (or
cost exceeds the benefits) - In class work out the small example on p. 89
9Another Example
- Assume fixed costs 1,000 day.
- Find the optimum time-cost schedule.
10CPM Assumptions/Limitations
- Project activities can be identified as entities.
(There is a clear beginning and ending point for
each activity.) - Project activity sequence relationships can be
specified and networked. - Project control should focus on the critical
path. - The activity times follow the beta distribution,
with the variance of the project assumed to equal
the sum of the variances along the critical path.
Project control should focus on the critical
path. - Practice problems 1, 3, 5, 6, 7
11MS Project
- MS Project is a very popular and inexpensive
project management software. - It is constantly improved (upgraded).
- Many independent software firms have developed
add-ons to further improve or help users
(managers) take full advantage of its
capabilities. - For example, probabilistic analysis (PERT
approach) is not directly available in MS
Project. - CAUTION PERT in MS Project refers to the AON
network representation, and simplistic project
duration calculations done by using either
optimistic or most likely or pessimistic time
estimates for all activities. - Risk developed by C/S Solutions is a
comprehensive risk analysis tool that integrates
seamlessly with Microsoft Project to quantify
the cost and schedule uncertainty associated with
your project plans. - http//www.cs-solutions.com/products/?ProductRisk
20Plus - Screen capture
12Reliable Construction Company Project
- This is a mini case/group exercise.
- The Reliable Construction Company has just made
the winning bid of 5.4 million to construct a
new plant for a major manufacturer. - The contract includes the following provisions
- A penalty of 300,000 if Reliable has not
completed construction within 47 weeks. - A bonus of 150,000 if Reliable has completed the
plant within 40 weeks. - Questions
- How can the project be displayed graphically to
better visualize the activities? - What is the total time required to complete the
project if no delays occur? - When do the individual activities need to start
and finish? - What are the critical bottleneck activities?
- For other activities, how much delay can be
tolerated? - What is the probability the project can be
completed in 47 weeks? - Is it worth to expedite the activities to finish
the project in 40 weeks? - Assume activities with 7 or more weeks can be
shortened by two weeks and the rest can be
reduced by only one week. - For simplicity assume that cost per week to
expedite any activity is 30,000. - In answering part 7, show your steps, and defend
your final conclusion.
13Activity List for Reliable Construction
14Three Time Estimates for the Project