Title: Louisiana Coastal Area (LCA) Project Status Report
1Louisiana Coastal Area (LCA) Project Status
Report
Presentation to the Governors Advisory
Commission on Coastal Protection, Restoration,
and Conservation October 6, 2009
2History and Milestones
- 1997 Coast 2050 Toward a Sustainable Coastal
Louisiana - Interagency plan with coastwide coverage
outlining restoration strategies - 2002 LCA Coastwide Comprehensive Ecosystem
Restoration Study initiated - 2004 Administration requests the LCA
Comprehensive Study be reduced to a near-term
plan - January 2005 Chiefs Report signed for LCA
Ecosystem Restoration Program (Near-term Plan) - November 2007 Water Resources Development Act
authorized LCA Program
3WRDA 2007 Title VII
- Sec. 7003 Louisiana Coastal Area
- Sec. 7005 Project Modifications 10,000,000
- Sec. 7006 Construction
- (a) Science and Technology 100,000,000
- (b) Demonstration Projects 100,000,000
- (c) Initial Projects (5) 828,300,000
- (d) Beneficial Use of Dredged
Material 100,000,000 - (e) Additional Projects (10) 728,200,000
- Sec. 7007 Non-Federal Cost Share
- Sec. 7008 Project Justification
- TOTAL (auth. for construction) 1,866,500,000
4Additional Six Projects
- The Secretary of the Army may carry out
these projects if a favorable report of the
Chief is completed by not later than December 31,
2010. -
- Terrebonne Basin Barrier Shoreline Restoration
- Small Diversion at Convent/Blind River
- Amite River Diversion Canal Modification
- Multi-purpose Operation of the HNC Lock
- Medium Diversion at Whites Ditch
- Convey Atchafalaya River Water to Northern
Terrebonne Marshes -
5Six Project Schedule
MILESTONE
DATE
- FCSA Execution Nov 2008
- Kickoff Meetings Jan 2009
- NEPA initiation (Notice of Intent publication)
Dec 2009 - Public scoping meetings Feb 2009
- Develop Screen Initial Alternatives Array
April 2009 - Submit Feasibility Scoping Meeting
Materials June 2009 - Feasibility Scoping Meeting July 2009
- Rights of Entry, Data Collection Sept 2009
- Evaluate Final Alternatives Array Nov 2009
- Identify Draft Tentatively Selected Plan Jan
2010 - Alternative Formulation Briefing Report
(HQ/MVD) Mar 2010 - Public comment period June 2010
- Respond to comments July 2010
- Washington review Sept 2010
- Sign Chiefs Report Dec 2010
6Additional Four Projects
- Not later than December 31, 2009 the Secretary
of the Army shall submit feasibility reports on
these projects - Maintain Land Bridge Between Caillou Lake and
Gulf of Mexico - Stabilize Gulf Shoreline at Point Au Fer Island
- Modification of Caernarvon Diversion
- Modification of Davis Pond Diversion
7Four Project Schedule
MILESTONE
DATE
FCSA Execution Jun 2009 Kickoff Meetings
Jul 2009 NEPA initiation (Notice of Intent
publication) Aug 2009 Public scoping meetings
Sep 2009 Develop Screen Initial
Alternatives Array Oct 2009 Submit Feasibility
Scoping Meeting Materials Jan 2010 Feasibility
Scoping Meeting Mar 2010 Final Array ROE
Data Collection Jun 2010 Evaluate Final
Alternatives Array Sep 2010 Identify Draft
Tentatively Selected Plan Nov 2010 Alternative
Formulation Briefing Report (HQ/MVD) Mar
2011 Public comment period May 2011 Respond
to comments June 2011 Washington
review Aug 2011 Sign Chiefs Report Nov
2011
8Initial Projects
- Small Diversion at Hope Canal
- Pursuing through CWPPRA
- 30 design milestone in Dec 2008
- USACE conducting gap analysis
- Addressing 30 design comments
- Moving forward to 95 design under CWPPRA
9Initial Projects
- Barataria Basin Barrier Shoreline Restoration
- Draft report/EIS complete
- Feasibility Review Conference Oct 2009
- Public review external peer review Jan 2010
- Engineering and design May 2010
- Construction to begin 2012
10Initial Projects
- Small Bayou Lafourche Reintroduction
- Bayou LaFourche Freshwater District pursuing
project with state technical and financial
support - Cooperative agreement signed November 2008
- Engineering and design complete in May 2009
- Construction to begin November 2009
- Developing MOU with USACE for work in kind credit
11Initial Projects
- Medium Diversion at Myrtle Grove with Dedicated
Dredging - PMP under development 2-3 yr. schedule
- to Chiefs Report
- State/NGO modeling initiated 2009
- Preliminary sediment data is collected
finalizing data report - Additional modeling components being started
- Infrastructure features GIS being developed
12Initial Projects
- Mississippi River Gulf Outlet (MRGO)
Environmental Restoration - Being pursued at 100 federal expense
13Program Components
- Beneficial Use of Dredged Material Program
- Science and Technology (ST) Program
- Demonstration Project Program
- Investigations into Modifications of Existing
Structures
14Program Execution Summary
- Initial Projects all 5 underway
- Additional Projects all 10 underway
- Beneficial Use of Dredged Material Program
underway - Science and Technology Program underway
- 17 active of 20 total program components
15Questions?
16Program Components
- Large-Scale and Long-Term Studies
- Acadiana Bay Estuarine Restoration Study
- Upper Atchafalaya Basin Study
- Chenier Plain Freshwater Management and
Allocation Reassessment Study - Mississippi River Delta Management Study
- Mississippi River Hydrodynamic Study
- Third Delta Study