Title: Feasibility Study Overview
1Feasibility Study Overview
Louisiana Coastal AreaEcosystem Restoration 19
September 2000
2Louisiana Coastal Area (LCA) Feasibility Study
- USACE Recon Report
- Supports Coast 2050 Plan
- Approved for feasibility study start May 99
- General Investigations study authorization
- LCA 1967 multi-purpose authority
- Current use ecosystem restoration (no B/C ratio)
- LA Dept. of Natural Resources non-Fed Sponsor
- Feb 00 study start 50/50 cost share
- Project authorization and funding vehicle
Water Resources Development Act (WRDA)
3Red River
Louisiana Coastal Area (LCA) Authorized Study Area
Texas
Louisiana
Mississippi
Mississippi River
Atchafalya River
I-10
I-12
I-10
Causeway
I-10
Hwy 1
Hwy 27
GIWW
GIWW
Hwy 27
Hwy 90
GIWW
Hwy 90
Hwy 46
Hwy 82
Bayou Lafourche
Hwy 301
GIWW
Hwy 23
Hwy 1
Gulf of Mexico
4LCA Study Organization
- DNR/COE Partnering
- Executive Committee
- Senior Management Committee
- Project Management Committee
- Multi-agency and stakeholder representation
- Technical Advisory Committee
- Study Data and Information Management
- USGS National Wetlands Research Center (NWRC)
5LCA Study EIS Partnering
- Agencies
- FWS, NMFS, WLF, MMS, DNR, EPA, COE
- Laws
- NEPA compliance
- FW Coordination Act
- Endangered Species Act
- Essential Fish Habitat
- Use of U.S. offshore sand resources
- Coastal Zone Management
6LCA Study Steps -- General
- Start with Coast 2050 Plan
- Develop Purpose and Need Statements for critical
strategies - Conduct public scoping to shape study
- Perform data collection
- Formulate alternative restoration plans
- Analyze alternative restoration plans
- Compare plans
- Recommendation Plan(s)
7LCA Study Interaction Process
- DNR/COE organizes/prepares for each step
- Ensures all facets to conduct work in place
- Keeps study on course
- Conduct Technical Advisory Committee workshops
- Team interaction on technical level
- Shapes study direction
- Conduct meetings with Barataria-Terrebonne
National Estuary Program - Receive valuable input on regional issues
- Shapes study direction
- Conduct public meetings
- Receive valuable input on public
concerns/interests - Shapes study direction
8Going Hi-Tech with NWRC
- GIS/Database Support
- Reservoir for data/info storage/recall
- Analytical tool for organized data/info queries
- Web Site Support
- 24-hr interface with public
- Study info posted
- Receipt of comments
- 24-hr interface with Technical Advisory Committee
- Draft study data posted
- Two-way transfer medium -- technical info
9Approach for Barataria Study
- Phase I Report
- Focus -- Coastal perimeter
- Wetland creation and restoration
- Barrier shoreline restoration
- River diversion
- Ecosystem Restoration Objectives
- Rebuild, protect shoreline, back marshes
- Provide support to basin interior for restoration
10Approach for Barataria Study
- Prep for Phase II Study
- Develop Hydrodynamic basin model
- Existing conditions
- Objective
- Prepare to analyze water-related
interior basin strategies
11Barrier Island Restoration, Marsh Creation, and
River Diversion, Barataria Basin
Phase I Study - current
Potential Addition
R2-11. Delta Building Diversion at Bastian Bay
R2-16. Dedicated Dredging for Marsh Creation
along Hwy. 1
R2-17. Dedicated Dredging for Marsh Building in
Caminada Bay
R2-22. Restore/maintain Barrier Shoreline,
Port Fourchon to Sandy Point
12(No Transcript)
13Alternatives for InvestigationMarsh Creation
Strategies
- Marsh Creation Alternatives
- Dredged materials placement
- Terracing
- Vegetative Plantings
- Borrow site alternatives
- Adjacent lakes and bays
- Offshore
- Three scales of analysis each alternative
14(No Transcript)
15Alternatives for Investigation Barrier Island
Restoration Strategy
- Barrier Island Restoration Alternatives
- Dredge and place (e.g. beach, dune, back marsh)
- Coastal structures (e.g. breakwaters, groins,
revetments, geotubes) - Borrow site sand alternatives
- Ship Shoal
- Mississippi River
- Barataria Basin ebb-tide shoals and relic
distributaries - Three scales of analysis each alternative
16(No Transcript)
17Alternatives for Investigation Diversion Strategy
- Location on lower river
- Converge LCA Study with prior study work
- Miss. River Sediment, Nutrient, and Freshwater
Redistribution Study (MRSNFR) - Barrier Shoreline Feasibility Study (BSFS)
18Study StatusBarataria Basin Phase I
- Data collection nearing completion
- Early stage of planning plan formulation workshops
Barataria Basin Phase II
- Early stage of initiating model development for
existing conditions
19Study Websitewww.coast2050.gov
20Barataria Basin Study Strategies
Phase II Study
Phase I Study - current
Phase I Study - to be added
R2-6. Enrich Existing Diversions with Sediment
R2-19. Gap Spoil Banks/Plug Canals in Lower Bay
Marshes
R2-4. Divert Through Existing Locks R2-5.
Manage Outfall of Existing Diversions R2-25.
Maintain Shoreline Integrity
R2-1. Small River Diversion
R2-26. Dedicated Dredging
R2-24. Preserve Land Bridge
R2-3a. Provide Diversion Related Flood Protection
R2-10. Delta Building Diversion at Myrtle Grove
R2-8 Small Diversions
R2-2. Restore Natural Drainage Patterns
R2-3b. Remove Flood Waters from the Upper Basin
R2-11. Delta Building Diversion at Bastion Bay
R2-18. Parallel Conveyance Channel and Delta
Lobe
R2-9. Sediment Trap for Marsh Creation
R2-20. Wave Absorbers and Reef Zone (R2-1)
R2-16. Dedicated Dredging for Marsh Creation
along Hwy. 1
R2-17. Dedicated Dredging for Marsh Building in
Caminada Bay
R2-22. Restore/maintain Barrier Shoreline,
Port Fourchon to Sandy Point
R2-23. Extend Barrier Shoreline, Sandy Point
to Southwest Pass