Update on Ontarios Clean Energy Standard Offer Program - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Update on Ontarios Clean Energy Standard Offer Program

Description:

Located in Ontario with commercial operating date after August 18, 2005. Installed generating ... By-product fuel-fired generation projects (e.g. flue-gas) ... – PowerPoint PPT presentation

Number of Views:37
Avg rating:3.0/5.0
Slides: 18
Provided by: heidip4
Category:

less

Transcript and Presenter's Notes

Title: Update on Ontarios Clean Energy Standard Offer Program


1
November 18, 2008
  • Update on Ontarios Clean Energy Standard Offer
    Program
  • Jim MacDougall

2
Presentation Overview
  • Clean Energy Standard Offer Program Background
  • Development of the CESOP
  • Going forward

3
Clean Energy Standard Offer Program
  • June 15, 2007 OPA directed to develop CESOP,
    with objective to launch by end of 2007
  • CESOP eligible projects are
  • Located in Ontario with commercial operating date
    after August 18, 2005
  • Installed generating gross nameplate capacity
    10MW
  • Project never subject to contract with Ontario
    Hydro, Province or OPA
  • Connected to an eligible local distribution
    company on IESO Grid, or to LDC load customer

4
CESOP Background
  • Stakeholder concerns raised during Fall 2007
    program development
  • fixed 8-month payment schedule excluded four
    shoulder months
  • revenue/cost uncertainty of fixed payments on top
    of HOEP revenues (HOEP-plus)
  • CHP projects with un-hedged NG risk will not sign
    fixed price Power Purchase Agreements (PPA)
  • OPA worked with consultant (Navigant Consulting
    Inc.) to revise pricing approach to address above
    concerns
  • Current approach value derived from avoid
    capacity, with appropriate adjustments

5
CESOP Approach
  • Guiding Principles for CESOP
  • The Program should be kept simple
  • Obtaining value for ratepayers
  • Adhere to distribution transmission limits
  • Consistency with RESOP and CHP II (where
    appropriate)
  • Expected Project Types
  • 10 MW projects, connect to eligible LDC on IESO
    grid
  • If using natural gas, must be combined heat
    power (CHP) projects
  • By-product fuel-fired generation projects (e.g.
    flue-gas)
  • Under-utilized energy (thermal or mechanical)
    projects

6
CESOP Approach
  • Payment schedule
  • Based on performance of representative NG-fired
    CHP e.g. Virtual Power Plant (VPP)
  • provide a 12-month market-sensitive schedule
    (replacing fixed 8-month schedule)
  • VPP deemed to run when economic, but only
    weekdays 7 AM - 11 PM (all year)
  • strong incentive to operate efficiently, no
    penalty for annual base-load operation
  • Separate PPA prices for non- NG-fired CHP
    projects
  • By-product and underutilized energy projects
    dont have NG fuel price risk costs largely
    fixed in money terms once financed and built
  • Higher incentive during weekday and a lower price
    during nights and weekends, without penalizing
    base load output

7
CESOP Payments
  • CESOP Approach CHP capacity payment derived from
    capacity value of CCGT
  • CCGT is used because
  • CCGT assumed to be marginal capacity
  • it has an output profile closest to NG-fired CHP
    (Frame CCGT costs taken from IPSP)
  • CESOP CHP value is a combination of
  • avoided cost of the marginal capacity it
    replaces/displaces (i.e. CCGT), plus
  • adders for differences in attributes between
    CESOP as distributed generation and central CCGT

8
CESOP CHP - Capacity Payments
  • Market prices are inadequate to attract
    investment for CHP or for CCGT
  • Derivation of CESOP capacity value includes four
    components
  • Deemed market revenue of the representative CCGT
  • Calculations use gas, electricity prices
    extrapolated from 2003-07
  • Capacity payments (based on the required
    above-market revenue of CCGT generation)
  • Avoided transmission losses adjustment
  • Avoided transmission capital costs adjustment

9
CHP Capacity Payments contd
  • Natural Gas Fuel-fired CHP (with NG price risk)
  • OPA calculates total revenue, from the market,
    plus the OPA top-up, that the reference CHP would
    require
  • This is called the Net Revenue Guarantee (NRG)
  • 17.25/kW-month for projects with COD after Aug.
    31, 2008 (approx 207,000/MW-yr)
  • 15.97/kW-month for projects with COD after Aug.
    18, 2005 and before Sept. 01, 2008 (approx
    192,000/MW-yr)

10
CHP Capacity Payments contd
  • When market revenues are insufficient for a
    reference combined heat power plant, all CHP
    projects will get a Contingent Support Payment
    (CSP).
  • Payment is based on the assumed operation of the
    reference combined heat power plant (or virtual
    power plant VPP)
  • OPA calculates Net Market Revenue (NMR) that the
    reference VPP would earn during a 16 hour
    business day, 12-month operating schedule
  • VPP deemed to run when economic, but only
    weekdays 7 AM - 11 PM (all year)
  • Difference between NRG and NMR is the support
    payment that OPA will provide to all CHP contract
    facilities
  • Facilities choose own operation

11
CSP to Gx NRG (fixed) minus NMR (deemed)


CSP (paid from OPA to actual physical generators)
NRG (fixed capacity payment) NMR (revenues
that OPA deems would have been earned by the
Virtual Power Plant
12
CESOP Requirements
  • Learn from RESOP experience with queue and
    contract prerequisites
  • Raise the bar for the distribution queue
  • Completion Security
  • Project milestones
  • Increase certainty around project progress and
    completion

13
CESOP Requirements
  • OPA will impose availability requirements
  • Cannot simply receive CSP if out of service
  • OPA will require 15 useful heat output from CHP
    projects
  • Mirrors CHP I and II
  • OPA will financially settle CHP contracts
  • Monthly production data not required
  • Payment derived from capacity payment less deemed
    market revenue
  • Regardless of actual operation, two 3 MW projects
    would earn same monthly revenue

14
Payments for PPA Projects
  • By-Product Fuel-Fired
  • By-products of industrial or manufacturing
    processes used as fuels
  • Under-utilized Energy Projects
  • Otherwise wasted thermal or mechanical energy

15
Payments for PPA Projects
  • Will be offered Power Purchase Agreements (PPAs),
    which are appropriate because
  • dont have NG fuel price risk
  • costs largely fixed in money terms once financed
    and built
  • Higher incentive during weekday days (7 am to 11
    pm)
  • 11.7/kWh
  • Lower price during nights and weekends
  • 5.1/kWh

16
CESOP Next Steps
  • Continued stakeholders engagement
  • Finalize gas price risk mitigation approach
  • We anticipate a positive industry response
  • Proposed changes should be aligned with the
    Government's policy priorities for distributed
    generation
  • Program needs to be consistent with September
    2008 IPSP Directive

17
For Additional Information
  • OPA Standard Offer Program Website
    www.powerauthority.on.ca/sop
  • OEB Website http//www.oeb.gov.on.ca for more
    information on connections and queuing
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com