Title: DOWNViND - cost effective wind energy in deep waters
1DOWNViND - cost effective wind energy in deep
waters
- Presentation at OWEMES 2006
- Citavecchia April 20-22, 2006
- By
- Göran Dalén, E.ON Wind, Sweden
2DOWNViND stands for ..
- Distant Offshore Windfarms with No Visual Impact
in Deepwater - The Research programme is funded within FP 6
- Other main financial contributors are
- Talisman Energy
- Scotish Southern Energy
- DTI
- Scottish Executive
- Talisman Energy is the main coordinator
- E.ON, Sweden is coordinating the Research work
3Capital Cost 41.5 million Public sector
contribution 35 of capital costs EC contribution
6 million
4Objective Form the basis for the next generation
large offshore wind power plants in deep water.
5RTD sites Cromatry Firth and Utblicken
6Participant Number Participant Name
01 Talisman Energy (UK) Limited
02 SSE Generation
03 EDF
04 Eon Sweden
05 University of Aberdeen
06 Teknikgruppen
07 Hammarlund Consulting
08 PB Consultants
09 Risoe
10 ECN
11 KTH University
12 Stockholm University
13 Strathclyde University
14 Lund University
15 REpower Systems
16
17
18 Germanischer Lloyd WindEnergie
19 Nautilus Associates
Total 14 out of 17 Contractors in Downvind take
part in RTD
TEKNIKGRUPPEN
7WG1 - Environment
- Stockholm University
- Study on acoustic effects on fish and reef
effects on existing wind farm Utgrunden I - Before and After study summer 2007/8
- Lund University
- Analysis of birds, resting, feeding, migrating as
effects of existing Utgrunden I wind farm. - Aberdeen University
- Analysis of sensitive areas for dolphins and
birds, noise measuring compared - to models, before and after study on birds
and dolphins. - Hammarlund Consulting
- Guide for good communication strategies for
offshore wind farms.
8WG2 - Electrical
- SSE
- Issues on connecting large intermittent
generation resources/Beatrice 1GW - KTH (Royal Institute of Technology)
- Tech/econ feasibility of different solutions for
transmission system from 1 GW wind farm to shore
- Strathclyde University
- Conceptual design for offshore wind farm
electrical system - EdF
- Analyse fast transients and dynamic stability
9WG3 Operation Maintanance
10WG4 5.11 Wind Turbine Substructure
- Risoe
- Design Basis for Beatrice and Södra Midsjöbanken
- ECN and TG (Teknikgruppen)
- Offshore structure verification
- Germanischer Lloyd
- Recommendations for future design
11Test of Lidar at Fino 1 platform
12Talisman Energy Oil Platform Beatrice
13Key Participants in Demonstrator
- Engineering Project Mgt
- AMEC Group Ltd
- Supply of turbines
- REpower Systems AG
- Supply of cables
- JDR Cable Systems Ltd
- Substructures piles
- BiFab Ltd
- BOWTIS
- Engineering Business Ltd
- Installation
- Scaldis
- Cable installation
- Subsea 7
14Two wind turbines REpower 5M
- Rated power 5 MW
- Rotor diameter 126 m
- Hub height 120 m
15Installed wind turbine with OWEC Jacket Quadropod
- Hub height 88 m
- Rotor dia 126 m
- Weight of Nacelle 410 t
- Weight of tower 220 t
- Jacket abt 70 m high
- Jacket base 20x20 m
- Jacket weight 750 tons
- (incl transition piece)
- Pile length 44 m
- Pile dia 1.8 m
- Pile weight 115 tons each
16OWEC Jacket
- Piles secured by swedgeing
17Access system
- Designed for Eric
- and 4 metres of tide
- Two access points
18Soft Landing System
19Installation
20Images\2006-060-BWFP-WTG INSTALLATION_10000.png
May EIA approval
June, assembly WTG
15 Juli, installation fundations, and WTG
15 Augusti, Start-Up
21(No Transcript)