Title: Life Safety Improvements Turner
1Life Safety ImprovementsTurner Stevenson Halls
April 14, 2009
2Background
- A.E. Stevenson Hall
- 162,180 Square Foot,
- Five Story, Masonry
- Building Constructed in
- 1966.
Turner Hall 97,118 Square Foot, Three
Story, Masonry Building Constructed in 1963
3Project Status
- Stevenson 3rd 4th Floors are Complete and
Occupied. - Stevenson Basement Mechanical Areas Complete
- Stevenson 1st 2nd Floors Will Be Substantially
Complete In June 2009 - Turner Construction Will Begin in July 2009 and
Finish in July 2010 - Project is Currently 67 Complete
4Background Original Project
- Code Compliance Fire Alarm, Sprinklers, Return
Air System - Asbestos Abatement
- Repair Deteriorated Infrastructure Electrical,
Heating, Air Conditioning, Ventilating, Plumbing
and Communications - Energy Efficiency Lighting, Mechanical Systems
- Replace Finishes Removed for Abatement and
Construction Ceilings, Flooring, Paint - Classroom Equipment
5Background - Budget
- Original Project Budget of 22,145,000
- Programming Identified
- Life Safety Compliance of 11,675,000
- Infrastructure Deficiencies/Energy Conservation
of 5,650,000 - Other Code Compliance of 1,740,000
- Classroom Technology of 1,000,000
- Using Agency Requests of 86,000
- State Added 1.286 Million for a total Budget at
Bidding of 23,431,000
6Background Not in Project
- Work Identified During Programming But Not
Included in Project Because of Lack of Funds - Non-Exposed Water (In the Walls) and Wastewater
Piping - Windows
- Improvement of Finishes (Except Those Removed as
Part of Abatement or Construction) - Upgrade of Existing Pneumatic Controls
- Programmatic Improvements
7Issues Becoming Significant During Construction
- Impact of Windows and Storefronts On Occupants
- Maintaining Temperatures in Perimeter Offices
- Stair Tower Offices At Class Changes
- Increased Damage to Plaster Resulting From Water
Seepage - Continued Deterioration of Plumbing
- New Water Leaks Almost Weekly
- No Hot Water Because of Leaks
- Unusable Urinals Because of Clogged Sanitary
Piping - Most Water Fountains Disabled
8Using Agency Requested Additions
- Replacement of Windows and Storefront
- Replacement of Failing Plumbing Systems and
Renovation of Restrooms
9Curtain Wall and Storefront
Replacing 6,775 SF of Curtain Wall and 2,050 SF
of Storefront
All Windows Have Single Pane Glass
Turner Hall
Stevenson Hall Similar at Each of Four Building
Entrances at Stevenson Hall
10Windows
All Windows Have Single Pane Glass
Replacing 312 Windows in the Two Buildings
11Window Conditions
12Plumbing
Classroom Wall Opened to Repair Leaking
Galvanized Water Pipe
Attempt to Clear Clogged Drain Lines By ISU
Maintenance Staff
13Required Demolition
14Restroom Conditions
Existing Tile Falling Off
Mismatched Tile
15Benefits of the Requested Work
- Increase Energy Efficiency
- Reduce Building Maintenance Costs
16Restroom Design
1966 Restrooms At Stevenson Hall
Schroeder Hall Restrooms
17Restroom Design
1966 Restrooms
Schroeder Hall Restrooms
18Funding
- Anticipated Cost
- Restrooms 1,300,000
- Window Replacement 1,200,000
- Entrance Modifications 300,000
- Total 2,800,000
- Source of Funds
- Project Contingency 600,000
- ISU Deferred Maintenance 872,000
- ISU Non-Recurring Funds 1,328,000
- Total 2,800,000
19Other ISU Funded Scope Modifications
- Modifications Providing Programmatic Improvements
- Stevenson 250 Computer Teaching Suite
- Turner Technology Department Suite
- Turner Classroom 121BC
- Fully Funded by ISU
- Each Project Below 100,000
20Proposed Schedule
- Request Approval Today
- A/E Modification No. 4 (253,900)
- Proceed Order for Windows and Storefront
(1,240,000) - Proceed Order for Restroom Asbestos Abatement
(180,000) - Present For Approval June 9, 2009
- Proceed Orders for Entrance Modifications
(Multiple Contracts) - Proceed Orders for Restrooms All Other
Contracts - Change Order for Windows
- Change Order for Asbestos
21Proposed Schedule
- Present For Approval August 2009
- Change Orders for Entrance Modifications
(Multiple Contracts) - Change Orders for Restrooms All Other Contracts
22Why Approve Proceed Orders Today?
- Windows
- Need to Complete Stevenson Windows Before Weather
Stops Work in the Fall of 2009 (Building Fully
Occupied January 2010) - Need to Complete South Half of Turner Windows
Before December 2009 (Occupied January 2010) - Remainder of Turner Windows by July 2010
- Asbestos Abatement for Restrooms
- Will Allow Abatement of Stevenson Floors 1 3
Before Classes Begin in August 2009 - Building Occupants Extremely Sensitive to
Asbestos Abatement Work
23Conclusion
- ISU Faculty, Staff and Board of Trustees Consider
These Infrastructure Enhancement Scope Items
Important to the Mission of the University - Time is of the Essence for the Successful
Completion of the Project
24Life Safety ImprovementsTurner Stevenson Halls
April 14, 2009