Life Safety Improvements Turner - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Life Safety Improvements Turner

Description:

Stevenson 3rd & 4th Floors are Complete and Occupied. ... Increased Damage to Plaster Resulting From Water Seepage. Continued Deterioration of Plumbing ... – PowerPoint PPT presentation

Number of Views:20
Avg rating:3.0/5.0
Slides: 25
Provided by: charle228
Category:

less

Transcript and Presenter's Notes

Title: Life Safety Improvements Turner


1
Life Safety ImprovementsTurner Stevenson Halls
April 14, 2009
2
Background
  • A.E. Stevenson Hall
  • 162,180 Square Foot,
  • Five Story, Masonry
  • Building Constructed in
  • 1966.

Turner Hall 97,118 Square Foot, Three
Story, Masonry Building Constructed in 1963
3
Project Status
  • Stevenson 3rd 4th Floors are Complete and
    Occupied.
  • Stevenson Basement Mechanical Areas Complete
  • Stevenson 1st 2nd Floors Will Be Substantially
    Complete In June 2009
  • Turner Construction Will Begin in July 2009 and
    Finish in July 2010
  • Project is Currently 67 Complete

4
Background Original Project
  • Code Compliance Fire Alarm, Sprinklers, Return
    Air System
  • Asbestos Abatement
  • Repair Deteriorated Infrastructure Electrical,
    Heating, Air Conditioning, Ventilating, Plumbing
    and Communications
  • Energy Efficiency Lighting, Mechanical Systems
  • Replace Finishes Removed for Abatement and
    Construction Ceilings, Flooring, Paint
  • Classroom Equipment

5
Background - Budget
  • Original Project Budget of 22,145,000
  • Programming Identified
  • Life Safety Compliance of 11,675,000
  • Infrastructure Deficiencies/Energy Conservation
    of 5,650,000
  • Other Code Compliance of 1,740,000
  • Classroom Technology of 1,000,000
  • Using Agency Requests of 86,000
  • State Added 1.286 Million for a total Budget at
    Bidding of 23,431,000

6
Background Not in Project
  • Work Identified During Programming But Not
    Included in Project Because of Lack of Funds
  • Non-Exposed Water (In the Walls) and Wastewater
    Piping
  • Windows
  • Improvement of Finishes (Except Those Removed as
    Part of Abatement or Construction)
  • Upgrade of Existing Pneumatic Controls
  • Programmatic Improvements

7
Issues Becoming Significant During Construction
  • Impact of Windows and Storefronts On Occupants
  • Maintaining Temperatures in Perimeter Offices
  • Stair Tower Offices At Class Changes
  • Increased Damage to Plaster Resulting From Water
    Seepage
  • Continued Deterioration of Plumbing
  • New Water Leaks Almost Weekly
  • No Hot Water Because of Leaks
  • Unusable Urinals Because of Clogged Sanitary
    Piping
  • Most Water Fountains Disabled

8
Using Agency Requested Additions
  • Replacement of Windows and Storefront
  • Replacement of Failing Plumbing Systems and
    Renovation of Restrooms

9
Curtain Wall and Storefront
Replacing 6,775 SF of Curtain Wall and 2,050 SF
of Storefront
All Windows Have Single Pane Glass
Turner Hall
Stevenson Hall Similar at Each of Four Building
Entrances at Stevenson Hall
10
Windows
All Windows Have Single Pane Glass
Replacing 312 Windows in the Two Buildings
11
Window Conditions
12
Plumbing
Classroom Wall Opened to Repair Leaking
Galvanized Water Pipe
Attempt to Clear Clogged Drain Lines By ISU
Maintenance Staff
13
Required Demolition
14
Restroom Conditions
Existing Tile Falling Off
Mismatched Tile
15
Benefits of the Requested Work
  • Increase Energy Efficiency
  • Reduce Building Maintenance Costs

16
Restroom Design
1966 Restrooms At Stevenson Hall
Schroeder Hall Restrooms
17
Restroom Design
1966 Restrooms
Schroeder Hall Restrooms
18
Funding
  • Anticipated Cost
  • Restrooms 1,300,000
  • Window Replacement 1,200,000
  • Entrance Modifications 300,000
  • Total 2,800,000
  • Source of Funds
  • Project Contingency 600,000
  • ISU Deferred Maintenance 872,000
  • ISU Non-Recurring Funds 1,328,000
  • Total 2,800,000

19
Other ISU Funded Scope Modifications
  • Modifications Providing Programmatic Improvements
  • Stevenson 250 Computer Teaching Suite
  • Turner Technology Department Suite
  • Turner Classroom 121BC
  • Fully Funded by ISU
  • Each Project Below 100,000

20
Proposed Schedule
  • Request Approval Today
  • A/E Modification No. 4 (253,900)
  • Proceed Order for Windows and Storefront
    (1,240,000)
  • Proceed Order for Restroom Asbestos Abatement
    (180,000)
  • Present For Approval June 9, 2009
  • Proceed Orders for Entrance Modifications
    (Multiple Contracts)
  • Proceed Orders for Restrooms All Other
    Contracts
  • Change Order for Windows
  • Change Order for Asbestos

21
Proposed Schedule
  • Present For Approval August 2009
  • Change Orders for Entrance Modifications
    (Multiple Contracts)
  • Change Orders for Restrooms All Other Contracts

22
Why Approve Proceed Orders Today?
  • Windows
  • Need to Complete Stevenson Windows Before Weather
    Stops Work in the Fall of 2009 (Building Fully
    Occupied January 2010)
  • Need to Complete South Half of Turner Windows
    Before December 2009 (Occupied January 2010)
  • Remainder of Turner Windows by July 2010
  • Asbestos Abatement for Restrooms
  • Will Allow Abatement of Stevenson Floors 1 3
    Before Classes Begin in August 2009
  • Building Occupants Extremely Sensitive to
    Asbestos Abatement Work

23
Conclusion
  • ISU Faculty, Staff and Board of Trustees Consider
    These Infrastructure Enhancement Scope Items
    Important to the Mission of the University
  • Time is of the Essence for the Successful
    Completion of the Project

24
Life Safety ImprovementsTurner Stevenson Halls
April 14, 2009
Write a Comment
User Comments (0)
About PowerShow.com