Title: CHAPTER 15 COST CONTROL


1
CHAPTER 15COST CONTROL
2
The mobile unit and a hardhat
Digital Hardhat
Using a whiteboard
Multimedia Information or MFR
3
COST CONTROL
  • Digital Hardhat System The digital Hardhat (DHH)
    technology enables dispersed users to capture and
    communicate multimedia field data to
    collaboratively solve problem, and collect and
    share information
  • The technology DHH is a pen-based personal
    computer (PC) running a windows operating system,
    which is used to collect multimedia information
    such as text, sound, video and images

4
COST CONTROL AS A MANAGEMENT TOOL
  • The early detection of actual or potential cost
    overruns in field construction activities is
    vital to management. It provides the opportunity
    to initiate remedial action and increases the
    chance of eliminating such overruns or minimize
    their impact
  • An important byproduct of an effective cost
    reporting system is the information that it can
    generate for management on the general cost
    performance of field construction activities
  • The determination of current project status,
    effectiveness of work progress, and preparation
    of progress payment request requires data
    generated by both project planning and cost
    control reporting system
  • Project cost control data are important not only
    to project management in decision making
    processes but also to the companys estimating
    and planning departments because this data
    provides feedback information essential for
    effective estimates and bids on new projects

5
PROJECT COST CONTROL SYSTEMS
  • The design, implementation and maintenance of a
    project cost control system can be considered a
    multi-step process
  • The five steps, shown schematically in fig. 15-1,
    form the basis for establishing and maintaining a
    cost control system
  • The following questions regarding each step in
    the implementation of the cost control system
    must be addressed
  • Chart of Cost Accounts what will be the basis
    adopted for developing estimated project
    expenditures and how will this basis be related
    to the firms general accounts and accounting
    functions? What will be the level of detailed
    adopted to defining the project cost accounts and
    how will they interface with other financial
    accounts?
  • Project Cost Plan How will the cost accounts be
    utilized to allow comparisons between the project
    estimate and cost plan with actual cost as
    recorded in the field? How will the project
    budget estimate be related to the construction
    plan and schedule in the formation of a project
    cost control frame work?
  • Cost Data Collection How will cost data be
    collected and integrated into the cost reporting
    system?
  • Project Cost Reporting What project cost reports
    are relevant and required by project management
    in its cost management of the project?
  • Cost Engineering What cost engineering
    procedures should project management implement in
    it efforts to minimize costs?

6
Figure 15-1 Steps in Cost Control
7
COST ACCOUNTS
  • The first step in establishing a cost control
    system for a construction job is the definition
    of project level cost centers
  • The primary function of the cost account section
    of a chart of accounts is to divide the total
    project into significant control units, each
    consisting of a given type of work that can be
    measured in the field (see fig. 15-2)
  • Once the job cost accounts are established, each
    account is then assigned an identifying code
    known as a cost data
  • Once segregated by associated cost centers, all
    the elements of expense (direct labor, indirect
    labor, materials, supplies, equipment costs,
    etc.) constituting work units can be properly
    recorded by cost code
  • The job accounting system is essentially an
    accounting information system
  • Therefore, management is free to establish its
    own chart of accounts

8
Fig. 15-2 List of typical project expense (cost)
accounts
9
COST CODING SYSTEMS
  • A variety of cost coding systems exist in
    practice and standard chart of accounts are
    published by organization such as the American
    Road Builders Association, AGC and CSI
  • In most construction firms, detailed project cost
    accounts such as those shown in fig. 15-2 are
    used. This method recognizes the fact that
    construction work is project oriented and that to
    achieve the cost management goal of maximizing
    profit, projects must be accounted individually
  • One project may be a winner while another is
    loosing money. Such situations may be masked in
    the accounting system unless job cost accounts
    are maintained on every project
  • The actual account descriptions or designations
    vary in accordance with the type of construction
    and the technologies and placement process
    peculiar to that construction
  • Standard cost accounts published by the American
    Road Builders Association emphasize there
    accounts, while Uniform Construction Index (UCI),
    published by CSI, emphasizes building oriented
    accounts
  • A breakdown of the major classifications with the
    UCI cost account system is shown in table 15-1
  • A portion of the second level of classification
    is shown in fig. 15-3

10
Table 15-1 Classification of Accounts Major
Divisions in Uniform Construction Index
11
Figure 15-3 Detailed codes for classification
within uniform Construction Index
12
PROJECT COST CODE STRUCTURE
  • UCI Master format RS means 3-level detail
  • Highest level major subdivisions
  • 30-level account
  • Next level down
  • Third and the lowest level
  • Large and complex projects

13
PROJECT COST CODE STRUCTURE
  • The UCI Master format as used by the R.S. Means
    Building Construction Cost Data identifies three
    levels of detail
  • At the highest level major subdivisions with the
    work category are established
  • For instance, 30-level accounts pertain to
    concrete while 031 accounts are accounts
    specifically dealing with concrete forming. In a
    similar manner, 032 accounts are reserved for
    cost activity associated with concrete
    reinforcement
  • At the next level down, a designation of the
    physical component or sub element of the
    construction is established. This is done by
    adding three digits to the work classification
    two digit code. For instance, three digit code
    for footing is 158. Therefore, the code 031158
    indicates an account dealing with concrete
    forming costs for footings
  • At the third and lowest level, digits specifying
    a more precise definition of the physical sub
    element are used. For instance, code of
    0311585000 can indicate that this account records
    costs for forming concrete footings of a
    particular type (see fig. 15-4)
  • At this level the refinement of definition is
    very great and the account can be made very
    sensitive to the peculiarities of the
    construction technology to be used
  • Large and complex projects in industrial and
    energy related construction may require cost
    codes that reflect additional information, such
    as project designation, the year in which the
    project was started, and the type of project. An
    example of such code is shown in fig. 15-5

14
Figure 15-4 UCI Cost (line item) Structure in the
Master Format Code
15
Figure 15-5 Classification of Accounts Typical
Data Structure for a Computerized Cost Code
16
COST ACCOUNTS FOR INTEGRATED PROJECT MANAGEMENT
  • In large and complex projects, it is advantageous
    to break the project into common building blocks
    for both of the cost and time
  • The concept of a common unit within the project
    that integrates both scheduling and cost control
    had led to the development of the work breakdown
    approach
  • The basic common denominator in this scheme is
    the work packages, which is a sub element of the
    project of which both the cost and time data are
    collected for project status reporting
  • The collection of time and cost data based on
    work packages has led to the term integrated
    project management
  • That is, the status reporting function has been
    integrated at the level of the work package
  • The set of work packages in a project constitutes
    its work breakdown structure (WBS)
  • The work breakdown structure and work packages
    for control of a project can be defined by
    developing a matrix similar to one shown in fig.
    15-6

17
COST ACCOUNTS FOR INTEGRTED PROJECT MANAGEMENT
CONTD.
  • The columns of this matrix are defined by
    breaking down the project into physical
    subcomponents. Thus we have a hierarchy of levels
    that begin with the project as a whole and at the
    lowest level subdivides the project into physical
    end items such as foundations and areas. As shown
    in fig. 15-6, the project is subdivided into
    systems. The individual items are further divided
    into disciplines (e.g. civil, mechanical,
    electrical). The lowest level of the hierarchy
    indicates physical end items (foundation 1, etc).
  • Work packages at the lowest level of the
    hierarchy are called control accounts
  • The rows of the matrix are defined by technology
    and responsibility. At the lowest level of this
    hierarchy, the responsibilities are shown in
    terms of tasks, such as concrete, framing and
    earthwork. These tasks imply various craft
    specialties and technologies
  • Typical work packages thus are defined as
    concrete tasks or foundational and earthwork on
    foundations 1 and 2. This approach can be
    expanded to a three dimensional matrix by
    considering the resources to be used on earthwork
    package (see fig. 15-7)

18
Fig. 15-6 Project Control Matrix
19
Figure 15-7 Three-Dimensional Visualization of
Work-Package-Oriented Cost Accounts
20
Figure 15-8 Basic Cost Code Structure
21
Figure 15-9 Project Control Matrix with
Scheduling of Subtasks
22
EARNED VALUE METHOD
  • One widely accepted way of calculating progress
    on complex projects using a work or account based
    breakdown system is the earned value approach
    or cost and schedule control systems criteria
    (C/SCSC)
  • This system of determining project progress
    addresses both schedule status (e.g. on schedule,
    behind schedule, etc) and cost status (e.g. over
    budget, under budget, etc)
  • The idea of earned value is based upon a rigorous
    development of percent complete of the budgeted
    costs associated with individual work packages or
    line items
  • Each work package has an initial budget or
    estimate which is defined as the budgeted cost at
    completion or BCAC
  • As work proceeds on an individual work package or
    account, assessment of the complete is made at
    various study date
  • The level of expected production is often shown
    as an S-curve plotting the cost or units of
    production (e.g. units produced, work hours
    expended, etc.) against time
  • This cost/production curve is referred to as the
    baseline. At any given time (study date), the
    units of cost/production indicated by the
    baseline are called the Budgeted Cost of Work
    Scheduled (BCWS)
  • The tracking system requires that field reports
    provide information about the Actual Cost of Work
    Performed (ACWP) and the Actual Quantity of Work
    Performed (AQWP)
  • The earned value is the Budgeted Cost of Work
    Performed (BCWP)
  • The relative values for a given work package or
    account a a given point in time (see fig. 15-10)
    provide information about the status in terms of
    cost and schedule variance

23
Figure 15-10 Control Values for Earned Value
Analysis
24
EARNED VALUE METHOD CONTD
  • The six (6) parameters which form the foundation
    of the earned value concept are
  • BCWS budgeted cost of work scheduled value of
    the baseline at a given time
  • ACWP actual cost of work performed measured in
    the field
  • BCWP budgeted cost of work performed
    complete x BAC
  • BCAC budgeted cost at completion contracted
    total cost for the work package
  • AQWP actual quantity at completion value of
    the qty. baseline as projected at a given point
  • In order to put these items into context,
    consider the small project shown in fig. 15-11.
    The project consists of two control accounts A
    and B. A consists of two sub accounts A.1 and
    A.2
  • The study date (e.g. September 1, etc)
    information for these work packages is given in
    table 15-2, see pg. 262-265 for the problem at
    hand
  • The earned value approach requires a
    comprehensive knowledge of work packages,
    budgeting and scheduling. It is a powerful tool
  • Without it, projects can quickly spiral out of
    control

25
Figure 15-11 A Simple Project Hierarchy
26
Table 15-2 Study Date Data for simple project
27
EARNED VALUE METHOD CONTD
  • In order to put these items into context,
    consider the small project shown in figure 15-11.
    The projects consists of two accounts A and
    B. A consists of two sub-accounts (A.1 and
    A.2). The study date (e.g. September 1, etc.)
    information for these work packages is given in
    Table 15-2)
  • In this example, the budget is expressed I worker
    hours so the baseline for control is in worker
    hours. The estimated number or worked hours for
    this scope of work is 215 (the sum of the
    estimated worker hours for A.1, A.2, and B).
    The BCWP or earned value for a given work package
    is given as
  • BCWPi PCi x BCACi
  • Where i is the work package or account label,
    and PC is the percent complete as of the study
    date.
  • The percent complete (PC) for work package is
    based on the ratio of AQWP divided by BQAC based
    on the latest quantity assessment.
  • If we know the original quantity estimate is 100
    units but updated information indicates that a
    total of 120 units will be required to complete
    the work, completion of 50 units would indicate
    50 complete. The correct PC would be 50/120
    (e.g. AQWP/BQAC)

28
EARNED VALUE METHOD CONTD
  • Based on the information in table 15-2, the PC
    for each package in the small project would be
  • PC (A.1) 35/105 0.333
  • PC (A.2) 60/77 0.780
  • PC (B) 100/125 0.8
  • Then BCWP (Project) 0.333(100)0.78(50)0.8(65)
    124.3
  • Project PC (PPC) Total BCWP/Total BCAC
    ECACi
    Estimated Cost at Completion for work packagei
    ACWPi/PCi
  • Therefore, the project percent complete (PPC)
    for the small project is
  • PPC 124.3/215 x 100 57.8
  • This simple example illustrates several points
  • The PC for a given package is based on the ratio
    of the AQWP/BQAC
  • The PPC is calculated by relating the total BCWP
    (i.e. earned value) to the total BCAC for the
    project scope of work.
  • The total work earned is compared to work
    required. The values of units to be earned are
    based on the originally budgeted units in an
    account / work package and the percent earned is
    based on the latest projected quantity of units
    at completion

29
EARNED VALUE METHOD CONTD
  • Worker hours are used here to demonstrate the
    development of the PPC. However, other cost
    control units may be used according to the needs
    of management.
  • It is very important to know that the schedule
    and cost objectives are being achieved. Schedule
    and cost performance can be characterized by cost
    and schedule variances as well as cost
    performance and schedule performance indices.
    These values in C/SCSC are defined as follows
  • CV BCWP - ACWP
  • SV BCWP - BCWS
  • CPI BCWP/ACWP
  • SPI BCWP/BCWS
  • Figures 15-2 a, b, and c plot the values of BCWP,
    ACWP and BCWS for the small project data given in
    Table 15.2. If any given study date management
    will want to know what are the cost schedule
    variances for each work package

30
Fig. 15-12 States of Control Account for Single
Project
31
EARNED VALUE METHOD CONTD
  • The variances can be calculated as follows
  • CV (A.1) BCWP (A.1) - ACWP (A.1) 33.3 -
    40 -6.7
  • CV (A.2) BCWP (A.2) - ACWP (A.2) 39 - 35
    4
  • CV (B) BCWP (B) - ACWP (B) 59 - 50 2
  • Since the CV values for A.2 and B are positive,
    those accounts are within budget ( i.e. the
    budget cost earned is grater than the actual
    cost). In other words, less is being paid in the
    field that was originally budgeted. The negative
    variance for A.1 indicates it is overrunning the
    budget. That is, the actual cost is greater than
    the cost budgeted.
  • This is confirmed by the values of the CPI for
    each package
  • CPI (A.1) 33/40 lt1.0 A value less that
    1.0 indicates cost overruns of
    budget
  • CPI (A.2) 39/35 gt1.0
  • CPI (B) 52/50 gt1.0 A value greater
    than 1.0 indicates actual cost is
    less than the budgeted cost

32
EARNED VALUE METHOD CONTD
  • The schedule variances for each package is as
    follows
  • SV (A.1) BCWP (A.1) - BCWS (A.1) 33.3 - 50
    -16.7
  • SV (A.2) BCWP (A.2) - BCWS (A.2) 39 - 32
    7
  • SV (B) BCWP (B) - BCWS (B) 52 - 45 7
  • The positive values for A.2 and B indicate that
    these items are ahead of schedule. The negative
    value for A.1 indicate a scheduling problem.
  • The scheduling values will confirm this
    assessment. Overall, it can be stated that A.2
    and B are ahead of schedule and below cost while
    A.1 is behind schedule and over cost.
  • Six scenarios for performance, ACWP, BCWP, and
    BCWS are possible as established in the test.
    The various combinations are shown in figure
    15.13 and Table 15.3

33
Fig. 15-13 Scenarios for permutations between
ACWP, BCWP and BCWS
34
Table 15-3 Values of CPI, CV, and SPI, SV for the
Six Scenarios
35
LABOR COST DATA COLLECTION
  • The purpose of the payroll system is to
  • Determine the amount of and disburse wages to
    labor force
  • Provide for payroll deductions
  • Maintain records for tax and other purposes
  • Provide information regarding labor expenses
  • The source document to collect data for payroll
    is a daily or weekly time card for each hourly
    employee similar to that shown in fig. 15-14
  • The flow of data from the field through
    preparation and generation of checks to cost
    accounting and earnings accumulation is shown in
    15-15

36
Figure 15-14 Foremans Daily Labor Distribution
Report
37
Figure 15-15 Payroll Data Structure
38
CHARGES FOR INDIRECT and OVERHEAD EXPENSE
  • Contractor incurs expenses associated with the
    construction of a given facility relate to
  • Direct Cost consumed in the realization of a
    physical sub element of the project (e.g. labor
    and material costs involved in pouring a slab)
  • Production Support costs incurred by the project
    related support resources or required by the
    contractor (e.g. superintendents salary, site
    office costs, various project related insurances)
    costs associated with the operation and
    management of the company as a viable business
    entity (e.g. home office overhead, such as the
    costs associated with preparation of payroll in
    the home office, preparation of the estimate,
    marketing, salaries of company officers)
  • The production support costs are typically
    refereed to as project indirect costs
  • The home office charges are normally referred to
    as home office overhead
  • All these costs must be recovered before income
    to the firm is generated
  • The home office overhead or general and
    administrative (GA) expense, can be treated as a
    period cost and charged separately from the
    project (direct costing)
  • On the other hand, they may be prorated to the
    job and charged to the job cost overhead accounts
    and the work-in-progress expense ledger accounts

39
PROJECT INDIRECT COSTS
  • Job related indirect costs such as these listed
    in the labor cost report of fig. 15-16 (e.g. haul
    trash) are typically incurred as part of the
    on-site related cost associated with realizing
    the project. A such, they are charged to
    appropriate accounts within the job systems
  • Many contractors prefer to handle these charges
    by adding a flat rate amount to cover them
  • Contractor calculates the direct costs and
    multiplies these charges by a factor to cover
    both project indirects and home office fixed
    overhead
  • To illustrate, assume direct cost to be 200,000.
    If the contractor applies a fixed factor of 20
    to cover field indirects and home office
    overhead, the required flat charge would be
    40,000
  • If he adds 10 profit, his total bid would be
    264,000
  • Fig. 13-3 establishes line items for indirects,
    calculates them on an item-by-item basis (rather
    than applying a flat rate)

40
Figure 15-16 Labor Cost Report (some typical line
items)
41
FIXED OVERHEAD
  • Where as the project indirect charges are unique
    to the job and should be estimated on a
    job-by-job basis, home office overhead is a more
    or less fixed expense that maintains a constant
    level not directly tied to individual projects
  • In this case, the application of a rate to
    prorate or allocate home office to a given
    project is and accepted practice
  • The calculation of this home office overhead
    allocation factor is based on
  • GA (home office) expenses incurred in the past
    year
  • Estimated sales (contract) volume for the coming
    year
  • Estimated gross margin (i.e. markup for the
    coming year)
  • See example on page 270 and 271 for home office
    overhead

42
CONSIDERATIONS IN ESTABLISHING FIXED OVERHEAD
  • In considering costs from a business point of
    view it is common practice to categorize them as
    variable costs or fixed costs
  • Variable costs are costs directly associated with
    the production process
  • In construction they are direct costs for labor,
    machines and materials as well as the field
    indirect costs (i.e. production support costs).
    These costs are considered variable since they
    vary as a function of the volume of work
    underway.
  • Fixed costs are incurred at a more or less
    constant rate independent of the volume of work
    in progress
  • In order to be in business, a certain minimum of
    staff in the home office, space for home office
    operations, telephones, supplies and the like
    must be maintained and costs for these items are
    incurred. These administrative costs are
    generally constant over a given range of
    sales/construction volume
  • As described in section 15-11, the level of GA
    costs can be estimated by referring to the actual
    costs incurred during the previous years
    operation

43
CONSIDERATIONS IN ESTABLISHING FIXED OVERHEAD
CONTD.
  • Since, the fixed overhead incurred in the
    previous year is typically available as a
    percentage of the previous years total sales
    volume, a simple conversion must ne made to
    reflect it as a of the total direct cost. See
    formula for this conversion on page 271
  • If for instance, 800,000 is incurred as home
    office GA expenses in a reference year in which
    total volume billed was 4,000,000, the P value
    would be 20. The calculated to be added to
    direct costs estimates for the coming year to
    cover GA fixed overhead would be 25
  • If the direct cost estimate (e.g. labor,
    materials, equipment and field indirects) for a
    job is 1,000,000, 250,000 would be added to
    cover fixed overhead. The profit would be added
    to the total of field direct and indirects plus
    fixed overhead
  • The fixed (variable) costs plus the fixed
    overhead (GA) charge plus profit yield the bid
    price
  • If the profit is 10 the total bid price would be
    1,375,000
  • Certain companies prefer to include a charge for
    fixed overhead that is more responsive to source
    of overhead support. The assumption here is that
    home office support for management of certain
    resources is greater or smaller, and this effect
    should be included in charging for overhead

44
CONSIDERATIONS IN ESTABLISHING FIXED OVERHEAD
CONTD.
  • For instance, the cost of preparing payroll and
    support for labor in the field may be
    considerably higher than the support needed in
    administering materials procurement and
    subcontractors
  • Therefore, a 25 rate for fixed overhead is
    applied to labor and equipment direct cost, while
    a 15 rate on materials and subcontract costs is
    used
  • If differing fixed overhead rates are used on
    various subcomponents of the field (variable)
    costs in the bid, the fixed overhead charge will
    reflect the mix of resources need. This is shown
    in table 15-4
  • It can be seen that the fixed overhead amounts
    using 15/15 approach are smaller on jobs 101 and
    102 than the flat rate of 20
  • This reflects the fact that the amount of labor
    and equipment direct cost on these projects is
    smaller than the materials and subcontract cost
  • In the example given (i.e., the 25/15 rate vs.
    20) the 20 flat rate would yield a lower
    overall charge for fixed overhead on labor and
    equipment-intensive jobs