Title: CHAPTER 15 COST CONTROL
1CHAPTER 15COST CONTROL
2The mobile unit and a hardhat
Digital Hardhat
Using a whiteboard
Multimedia Information or MFR
3COST CONTROL
- Digital Hardhat System The digital Hardhat (DHH)
technology enables dispersed users to capture and
communicate multimedia field data to
collaboratively solve problem, and collect and
share information - The technology DHH is a pen-based personal
computer (PC) running a windows operating system,
which is used to collect multimedia information
such as text, sound, video and images
4COST CONTROL AS A MANAGEMENT TOOL
- The early detection of actual or potential cost
overruns in field construction activities is
vital to management. It provides the opportunity
to initiate remedial action and increases the
chance of eliminating such overruns or minimize
their impact - An important byproduct of an effective cost
reporting system is the information that it can
generate for management on the general cost
performance of field construction activities - The determination of current project status,
effectiveness of work progress, and preparation
of progress payment request requires data
generated by both project planning and cost
control reporting system - Project cost control data are important not only
to project management in decision making
processes but also to the companys estimating
and planning departments because this data
provides feedback information essential for
effective estimates and bids on new projects
5PROJECT COST CONTROL SYSTEMS
- The design, implementation and maintenance of a
project cost control system can be considered a
multi-step process - The five steps, shown schematically in fig. 15-1,
form the basis for establishing and maintaining a
cost control system - The following questions regarding each step in
the implementation of the cost control system
must be addressed - Chart of Cost Accounts what will be the basis
adopted for developing estimated project
expenditures and how will this basis be related
to the firms general accounts and accounting
functions? What will be the level of detailed
adopted to defining the project cost accounts and
how will they interface with other financial
accounts? - Project Cost Plan How will the cost accounts be
utilized to allow comparisons between the project
estimate and cost plan with actual cost as
recorded in the field? How will the project
budget estimate be related to the construction
plan and schedule in the formation of a project
cost control frame work? - Cost Data Collection How will cost data be
collected and integrated into the cost reporting
system? - Project Cost Reporting What project cost reports
are relevant and required by project management
in its cost management of the project? - Cost Engineering What cost engineering
procedures should project management implement in
it efforts to minimize costs?
6Figure 15-1 Steps in Cost Control
7COST ACCOUNTS
- The first step in establishing a cost control
system for a construction job is the definition
of project level cost centers - The primary function of the cost account section
of a chart of accounts is to divide the total
project into significant control units, each
consisting of a given type of work that can be
measured in the field (see fig. 15-2) - Once the job cost accounts are established, each
account is then assigned an identifying code
known as a cost data - Once segregated by associated cost centers, all
the elements of expense (direct labor, indirect
labor, materials, supplies, equipment costs,
etc.) constituting work units can be properly
recorded by cost code - The job accounting system is essentially an
accounting information system - Therefore, management is free to establish its
own chart of accounts
8Fig. 15-2 List of typical project expense (cost)
accounts
9COST CODING SYSTEMS
- A variety of cost coding systems exist in
practice and standard chart of accounts are
published by organization such as the American
Road Builders Association, AGC and CSI - In most construction firms, detailed project cost
accounts such as those shown in fig. 15-2 are
used. This method recognizes the fact that
construction work is project oriented and that to
achieve the cost management goal of maximizing
profit, projects must be accounted individually - One project may be a winner while another is
loosing money. Such situations may be masked in
the accounting system unless job cost accounts
are maintained on every project - The actual account descriptions or designations
vary in accordance with the type of construction
and the technologies and placement process
peculiar to that construction - Standard cost accounts published by the American
Road Builders Association emphasize there
accounts, while Uniform Construction Index (UCI),
published by CSI, emphasizes building oriented
accounts - A breakdown of the major classifications with the
UCI cost account system is shown in table 15-1 - A portion of the second level of classification
is shown in fig. 15-3
10Table 15-1 Classification of Accounts Major
Divisions in Uniform Construction Index
11Figure 15-3 Detailed codes for classification
within uniform Construction Index
12PROJECT COST CODE STRUCTURE
- UCI Master format RS means 3-level detail
- Highest level major subdivisions
- 30-level account
- Next level down
- Third and the lowest level
- Large and complex projects
13PROJECT COST CODE STRUCTURE
- The UCI Master format as used by the R.S. Means
Building Construction Cost Data identifies three
levels of detail - At the highest level major subdivisions with the
work category are established - For instance, 30-level accounts pertain to
concrete while 031 accounts are accounts
specifically dealing with concrete forming. In a
similar manner, 032 accounts are reserved for
cost activity associated with concrete
reinforcement - At the next level down, a designation of the
physical component or sub element of the
construction is established. This is done by
adding three digits to the work classification
two digit code. For instance, three digit code
for footing is 158. Therefore, the code 031158
indicates an account dealing with concrete
forming costs for footings - At the third and lowest level, digits specifying
a more precise definition of the physical sub
element are used. For instance, code of
0311585000 can indicate that this account records
costs for forming concrete footings of a
particular type (see fig. 15-4) - At this level the refinement of definition is
very great and the account can be made very
sensitive to the peculiarities of the
construction technology to be used - Large and complex projects in industrial and
energy related construction may require cost
codes that reflect additional information, such
as project designation, the year in which the
project was started, and the type of project. An
example of such code is shown in fig. 15-5
14Figure 15-4 UCI Cost (line item) Structure in the
Master Format Code
15Figure 15-5 Classification of Accounts Typical
Data Structure for a Computerized Cost Code
16COST ACCOUNTS FOR INTEGRATED PROJECT MANAGEMENT
- In large and complex projects, it is advantageous
to break the project into common building blocks
for both of the cost and time - The concept of a common unit within the project
that integrates both scheduling and cost control
had led to the development of the work breakdown
approach - The basic common denominator in this scheme is
the work packages, which is a sub element of the
project of which both the cost and time data are
collected for project status reporting - The collection of time and cost data based on
work packages has led to the term integrated
project management - That is, the status reporting function has been
integrated at the level of the work package - The set of work packages in a project constitutes
its work breakdown structure (WBS) - The work breakdown structure and work packages
for control of a project can be defined by
developing a matrix similar to one shown in fig.
15-6
17COST ACCOUNTS FOR INTEGRTED PROJECT MANAGEMENT
CONTD.
- The columns of this matrix are defined by
breaking down the project into physical
subcomponents. Thus we have a hierarchy of levels
that begin with the project as a whole and at the
lowest level subdivides the project into physical
end items such as foundations and areas. As shown
in fig. 15-6, the project is subdivided into
systems. The individual items are further divided
into disciplines (e.g. civil, mechanical,
electrical). The lowest level of the hierarchy
indicates physical end items (foundation 1, etc). - Work packages at the lowest level of the
hierarchy are called control accounts - The rows of the matrix are defined by technology
and responsibility. At the lowest level of this
hierarchy, the responsibilities are shown in
terms of tasks, such as concrete, framing and
earthwork. These tasks imply various craft
specialties and technologies - Typical work packages thus are defined as
concrete tasks or foundational and earthwork on
foundations 1 and 2. This approach can be
expanded to a three dimensional matrix by
considering the resources to be used on earthwork
package (see fig. 15-7)
18Fig. 15-6 Project Control Matrix
19Figure 15-7 Three-Dimensional Visualization of
Work-Package-Oriented Cost Accounts
20Figure 15-8 Basic Cost Code Structure
21Figure 15-9 Project Control Matrix with
Scheduling of Subtasks
22EARNED VALUE METHOD
- One widely accepted way of calculating progress
on complex projects using a work or account based
breakdown system is the earned value approach
or cost and schedule control systems criteria
(C/SCSC) - This system of determining project progress
addresses both schedule status (e.g. on schedule,
behind schedule, etc) and cost status (e.g. over
budget, under budget, etc) - The idea of earned value is based upon a rigorous
development of percent complete of the budgeted
costs associated with individual work packages or
line items - Each work package has an initial budget or
estimate which is defined as the budgeted cost at
completion or BCAC - As work proceeds on an individual work package or
account, assessment of the complete is made at
various study date - The level of expected production is often shown
as an S-curve plotting the cost or units of
production (e.g. units produced, work hours
expended, etc.) against time - This cost/production curve is referred to as the
baseline. At any given time (study date), the
units of cost/production indicated by the
baseline are called the Budgeted Cost of Work
Scheduled (BCWS) - The tracking system requires that field reports
provide information about the Actual Cost of Work
Performed (ACWP) and the Actual Quantity of Work
Performed (AQWP) - The earned value is the Budgeted Cost of Work
Performed (BCWP) - The relative values for a given work package or
account a a given point in time (see fig. 15-10)
provide information about the status in terms of
cost and schedule variance
23Figure 15-10 Control Values for Earned Value
Analysis
24EARNED VALUE METHOD CONTD
- The six (6) parameters which form the foundation
of the earned value concept are - BCWS budgeted cost of work scheduled value of
the baseline at a given time - ACWP actual cost of work performed measured in
the field - BCWP budgeted cost of work performed
complete x BAC - BCAC budgeted cost at completion contracted
total cost for the work package - AQWP actual quantity at completion value of
the qty. baseline as projected at a given point - In order to put these items into context,
consider the small project shown in fig. 15-11.
The project consists of two control accounts A
and B. A consists of two sub accounts A.1 and
A.2 - The study date (e.g. September 1, etc)
information for these work packages is given in
table 15-2, see pg. 262-265 for the problem at
hand - The earned value approach requires a
comprehensive knowledge of work packages,
budgeting and scheduling. It is a powerful tool - Without it, projects can quickly spiral out of
control
25Figure 15-11 A Simple Project Hierarchy
26Table 15-2 Study Date Data for simple project
27EARNED VALUE METHOD CONTD
- In order to put these items into context,
consider the small project shown in figure 15-11.
The projects consists of two accounts A and
B. A consists of two sub-accounts (A.1 and
A.2). The study date (e.g. September 1, etc.)
information for these work packages is given in
Table 15-2) - In this example, the budget is expressed I worker
hours so the baseline for control is in worker
hours. The estimated number or worked hours for
this scope of work is 215 (the sum of the
estimated worker hours for A.1, A.2, and B).
The BCWP or earned value for a given work package
is given as - BCWPi PCi x BCACi
- Where i is the work package or account label,
and PC is the percent complete as of the study
date. - The percent complete (PC) for work package is
based on the ratio of AQWP divided by BQAC based
on the latest quantity assessment. - If we know the original quantity estimate is 100
units but updated information indicates that a
total of 120 units will be required to complete
the work, completion of 50 units would indicate
50 complete. The correct PC would be 50/120
(e.g. AQWP/BQAC)
28EARNED VALUE METHOD CONTD
- Based on the information in table 15-2, the PC
for each package in the small project would be - PC (A.1) 35/105 0.333
- PC (A.2) 60/77 0.780
- PC (B) 100/125 0.8
- Then BCWP (Project) 0.333(100)0.78(50)0.8(65)
124.3 - Project PC (PPC) Total BCWP/Total BCAC
ECACi
Estimated Cost at Completion for work packagei
ACWPi/PCi - Therefore, the project percent complete (PPC)
for the small project is - PPC 124.3/215 x 100 57.8
- This simple example illustrates several points
- The PC for a given package is based on the ratio
of the AQWP/BQAC - The PPC is calculated by relating the total BCWP
(i.e. earned value) to the total BCAC for the
project scope of work. - The total work earned is compared to work
required. The values of units to be earned are
based on the originally budgeted units in an
account / work package and the percent earned is
based on the latest projected quantity of units
at completion
29EARNED VALUE METHOD CONTD
- Worker hours are used here to demonstrate the
development of the PPC. However, other cost
control units may be used according to the needs
of management. - It is very important to know that the schedule
and cost objectives are being achieved. Schedule
and cost performance can be characterized by cost
and schedule variances as well as cost
performance and schedule performance indices.
These values in C/SCSC are defined as follows - CV BCWP - ACWP
- SV BCWP - BCWS
- CPI BCWP/ACWP
- SPI BCWP/BCWS
- Figures 15-2 a, b, and c plot the values of BCWP,
ACWP and BCWS for the small project data given in
Table 15.2. If any given study date management
will want to know what are the cost schedule
variances for each work package
30Fig. 15-12 States of Control Account for Single
Project
31EARNED VALUE METHOD CONTD
- The variances can be calculated as follows
- CV (A.1) BCWP (A.1) - ACWP (A.1) 33.3 -
40 -6.7 - CV (A.2) BCWP (A.2) - ACWP (A.2) 39 - 35
4 - CV (B) BCWP (B) - ACWP (B) 59 - 50 2
- Since the CV values for A.2 and B are positive,
those accounts are within budget ( i.e. the
budget cost earned is grater than the actual
cost). In other words, less is being paid in the
field that was originally budgeted. The negative
variance for A.1 indicates it is overrunning the
budget. That is, the actual cost is greater than
the cost budgeted. - This is confirmed by the values of the CPI for
each package - CPI (A.1) 33/40 lt1.0 A value less that
1.0 indicates cost overruns of
budget - CPI (A.2) 39/35 gt1.0
- CPI (B) 52/50 gt1.0 A value greater
than 1.0 indicates actual cost is
less than the budgeted cost
32EARNED VALUE METHOD CONTD
- The schedule variances for each package is as
follows - SV (A.1) BCWP (A.1) - BCWS (A.1) 33.3 - 50
-16.7 - SV (A.2) BCWP (A.2) - BCWS (A.2) 39 - 32
7 - SV (B) BCWP (B) - BCWS (B) 52 - 45 7
- The positive values for A.2 and B indicate that
these items are ahead of schedule. The negative
value for A.1 indicate a scheduling problem. - The scheduling values will confirm this
assessment. Overall, it can be stated that A.2
and B are ahead of schedule and below cost while
A.1 is behind schedule and over cost. - Six scenarios for performance, ACWP, BCWP, and
BCWS are possible as established in the test.
The various combinations are shown in figure
15.13 and Table 15.3
33Fig. 15-13 Scenarios for permutations between
ACWP, BCWP and BCWS
34Table 15-3 Values of CPI, CV, and SPI, SV for the
Six Scenarios
35LABOR COST DATA COLLECTION
- The purpose of the payroll system is to
- Determine the amount of and disburse wages to
labor force - Provide for payroll deductions
- Maintain records for tax and other purposes
- Provide information regarding labor expenses
- The source document to collect data for payroll
is a daily or weekly time card for each hourly
employee similar to that shown in fig. 15-14 - The flow of data from the field through
preparation and generation of checks to cost
accounting and earnings accumulation is shown in
15-15
36Figure 15-14 Foremans Daily Labor Distribution
Report
37Figure 15-15 Payroll Data Structure
38CHARGES FOR INDIRECT and OVERHEAD EXPENSE
- Contractor incurs expenses associated with the
construction of a given facility relate to - Direct Cost consumed in the realization of a
physical sub element of the project (e.g. labor
and material costs involved in pouring a slab) - Production Support costs incurred by the project
related support resources or required by the
contractor (e.g. superintendents salary, site
office costs, various project related insurances)
costs associated with the operation and
management of the company as a viable business
entity (e.g. home office overhead, such as the
costs associated with preparation of payroll in
the home office, preparation of the estimate,
marketing, salaries of company officers) - The production support costs are typically
refereed to as project indirect costs - The home office charges are normally referred to
as home office overhead - All these costs must be recovered before income
to the firm is generated - The home office overhead or general and
administrative (GA) expense, can be treated as a
period cost and charged separately from the
project (direct costing) - On the other hand, they may be prorated to the
job and charged to the job cost overhead accounts
and the work-in-progress expense ledger accounts
39PROJECT INDIRECT COSTS
- Job related indirect costs such as these listed
in the labor cost report of fig. 15-16 (e.g. haul
trash) are typically incurred as part of the
on-site related cost associated with realizing
the project. A such, they are charged to
appropriate accounts within the job systems - Many contractors prefer to handle these charges
by adding a flat rate amount to cover them - Contractor calculates the direct costs and
multiplies these charges by a factor to cover
both project indirects and home office fixed
overhead - To illustrate, assume direct cost to be 200,000.
If the contractor applies a fixed factor of 20
to cover field indirects and home office
overhead, the required flat charge would be
40,000 - If he adds 10 profit, his total bid would be
264,000 - Fig. 13-3 establishes line items for indirects,
calculates them on an item-by-item basis (rather
than applying a flat rate)
40Figure 15-16 Labor Cost Report (some typical line
items)
41FIXED OVERHEAD
- Where as the project indirect charges are unique
to the job and should be estimated on a
job-by-job basis, home office overhead is a more
or less fixed expense that maintains a constant
level not directly tied to individual projects - In this case, the application of a rate to
prorate or allocate home office to a given
project is and accepted practice - The calculation of this home office overhead
allocation factor is based on - GA (home office) expenses incurred in the past
year - Estimated sales (contract) volume for the coming
year - Estimated gross margin (i.e. markup for the
coming year) - See example on page 270 and 271 for home office
overhead
42CONSIDERATIONS IN ESTABLISHING FIXED OVERHEAD
- In considering costs from a business point of
view it is common practice to categorize them as
variable costs or fixed costs - Variable costs are costs directly associated with
the production process - In construction they are direct costs for labor,
machines and materials as well as the field
indirect costs (i.e. production support costs).
These costs are considered variable since they
vary as a function of the volume of work
underway. - Fixed costs are incurred at a more or less
constant rate independent of the volume of work
in progress - In order to be in business, a certain minimum of
staff in the home office, space for home office
operations, telephones, supplies and the like
must be maintained and costs for these items are
incurred. These administrative costs are
generally constant over a given range of
sales/construction volume - As described in section 15-11, the level of GA
costs can be estimated by referring to the actual
costs incurred during the previous years
operation
43CONSIDERATIONS IN ESTABLISHING FIXED OVERHEAD
CONTD.
- Since, the fixed overhead incurred in the
previous year is typically available as a
percentage of the previous years total sales
volume, a simple conversion must ne made to
reflect it as a of the total direct cost. See
formula for this conversion on page 271 - If for instance, 800,000 is incurred as home
office GA expenses in a reference year in which
total volume billed was 4,000,000, the P value
would be 20. The calculated to be added to
direct costs estimates for the coming year to
cover GA fixed overhead would be 25 - If the direct cost estimate (e.g. labor,
materials, equipment and field indirects) for a
job is 1,000,000, 250,000 would be added to
cover fixed overhead. The profit would be added
to the total of field direct and indirects plus
fixed overhead - The fixed (variable) costs plus the fixed
overhead (GA) charge plus profit yield the bid
price - If the profit is 10 the total bid price would be
1,375,000 - Certain companies prefer to include a charge for
fixed overhead that is more responsive to source
of overhead support. The assumption here is that
home office support for management of certain
resources is greater or smaller, and this effect
should be included in charging for overhead
44CONSIDERATIONS IN ESTABLISHING FIXED OVERHEAD
CONTD.
- For instance, the cost of preparing payroll and
support for labor in the field may be
considerably higher than the support needed in
administering materials procurement and
subcontractors - Therefore, a 25 rate for fixed overhead is
applied to labor and equipment direct cost, while
a 15 rate on materials and subcontract costs is
used - If differing fixed overhead rates are used on
various subcomponents of the field (variable)
costs in the bid, the fixed overhead charge will
reflect the mix of resources need. This is shown
in table 15-4 - It can be seen that the fixed overhead amounts
using 15/15 approach are smaller on jobs 101 and
102 than the flat rate of 20 - This reflects the fact that the amount of labor
and equipment direct cost on these projects is
smaller than the materials and subcontract cost - In the example given (i.e., the 25/15 rate vs.
20) the 20 flat rate would yield a lower
overall charge for fixed overhead on labor and
equipment-intensive jobs