Title: GLAST Large Area Telescope:
1GLAST Large Area Telescope Integration and
Test Two Tower Integration Readiness
Review Integration, Facilities, Configuration
and Test (IFCT) Department Ken Fouts / Brian
Grist
2IFCT Outline
- Operations Readiness
- EGSE
- Integration Facility
3IFCT Part I. Operations Readiness
- Summary of 2 tower IT Operations and AIDS
- Mapping of AIDS to schedule / PMCS
- AIDS and Time Estimates Overview
- Grid Installation and Survey
- Calorimeter Receiving and Post-Ship Test
- TEM/TPS Receiving
- Tracker Receiving and Post-Ship Test
- Calorimeter and TEM/TPS IT
- Test Bay IT
- Grid Bay IT
- Bays 8 9 IT
4Two Tower IT Operations
Receive Tracker Flight Unit A
Receive Calorimeter, TEM/TEM PS Flight Units A
Receive and assemble Grid
Receive Calorimeter, TEM/TEM PS Flight Units B
Receive Tracker Flight Unit B
Install in Metrology Bay for Shimming Assembly
Integrate Grid onto Rotation Stand
Install in Metrology Bay for Shimming Assembly
Install tower in Test Bay
Test CAL A TEM/TEM PS A
Grid Optical Survey
Install tower in Test Bay
Test CAL B TEM/TEM PS B
Test Single Bay Tower
Test Single Bay Tower
De-Install Tower from test bay
De-Install Tower from test bay
Integrate Tracker A into Grid
Integrate CAL/TEM/TPS A into Grid
Single Tower Test in Grid
Integrate Tracker B into Grid
Integrate Cal/TEM/TEM-PS B into Grid
Single Tower Test in Grid
Two Tower IT
Optical Survey
5Assembly and Inspection Data Sheet
6Assembly and Inspection Data Sheet
7Assembly and Inspection Data Sheet
8Mapping of AIDS to schedule / PMCS
- Strategy
- AIDS line items tracked in MS Project
- Line items are groups of work which take gt1hr
- Status
- AIDS drafts delivered to scheduler data input in
process ECD Dec. 18
9AIDS and Time Estimates Overview
10Grid Installation and Survey
- Notes
- Mechanical Systems (Martin Nordby) is working
with SLAC metrology to define the Grid survey
requirements. - Risk Mitigation
- Plan for completing a Grid to Grid Perimeter Ring
fit check in work ECD 12/1.
11Calorimeter Receiving and Post-Ship Test
- Notes
- Calorimeter post-ship test performed by
Calorimeter Subsystem using subsystem GSE and
staff. - Calorimeter TEM/TPS safe-to-mate performed by IT
for TEM-GASU and TPS-PDU connectors only - Calorimeter IT receiving test performed by IT
- Risk Mitigation
- ELX will complete acceptance testing on EGSE Test
Stand
12TEM/TPS Receiving
- Notes
- TEM/TPS manufacturing is completed in Room 103
- Safe-to-mate is performed on all TEM/TPS
connectors (14)
13Tracker Receiving and Post-Ship Test
- Notes
- Tracker receiving inspection yet to be defined
- Tracker post-ship test performed by tracker
subsystem - Risk Mitigation
- IT working closely with TKR subsystem to develop
processes. - Plan is to use the TKR Mock Up with Flight-like
Cables delivered in December to dry run receiving
procedures. - ELX will complete acceptance testing on EGSE Test
Stand
14Calorimeter and TEM/TPS IT
- Notes
- IT is considering requirements for relocating
this process from room 104 (current baseline) to
room 103 to relieve floor space usage in room 104 - Risk Mitigation
- ELX will complete acceptance testing on EGSE Test
Stand
15Test Bay IT
- Notes
- Tracker installation procedures not finalized at
this time - Tower survey is managed by Martin Nordby and
staffed from SLAC Metrology - Tower trigger test procedures and software not
finalized at this time - E2E test software not finalized at this time
- SVAC test software not finalized at this time
- Risk Mitigation
- Plan is to use the TKR Mock Up with Flight-like
Cables delivered in December to dry run receiving
procedures - ELX will complete acceptance testing on EGSE Test
Stand
16Tracker Installation
- Basic Procedure complete
- New inputs from Tracker Group to be incorporated
- Cone assembly process (done)
- Cable bonding process (still in work)
- Some Project decisions pending
- Adjustment of Tower lean
- Measurement of Tower location
- Procedures and documentation for Lifting need
approval after procedure release
17IT Test Definitions
- Single Bay Test (in EM single bay) 54 hrs total
(40 hrs w/o E2E/SVAC/VDG) - Aliveness Test (15 min)
- Calorimeter CPT (2 hrs)
- Tracker Pass/fail tests (2hrs)
- Trigger Module internal timing, GEM timing
alignment, subsystem TACK delays (36 hours) - End-to-end Test, 6 hrs
- SVAC Data Collection (Bay 9 only, includes VDG) 8
hrs - Single Bay Test (in flight grid) 44 hrs total (4
hrs w/o SVAC) - Aliveness Test (15 min)
- Calorimeter CPT (2 hrs)
- Tracker Pass/fail tests (2hrs)
- SVAC Data Collection (Bay 9 only, no VDG) Day
116 hrs, Day 2 24 hrs - Two Bay Test (in flight grid) 104 hrs total
- Aliveness Test (15 min)
- Calorimeter CPT (4 hours)
- Tracker Pass/fail tests (4hrs)
- End-to-end Test, 40 hrs
- SVAC Data Collection (includes VDG) Day 116 hrs,
Day 2 24 hrs, VDG16 hrs
18Grid Bay IT
- Notes
- Same as for test bay IT, except no trigger nor
E2E tests - Risk Mitigation
- Plan is to use the TKR Mock Up with Flight-like
Cables delivered in December to dry run receiving
procedures - ELX will complete acceptance testing on EGSE Test
Stand
19Bays 89 IT
- Notes
- Flight mates are performed on DAQ cables to bays
8 9 - Subsystem tests are executed module by module
- E2E test software not finalized at this time
- SVAC test software not finalized at this time
- Risk Mitigation
- ELX will complete acceptance testing on EGSE Test
Stand - Test definition in process with Systems
Engineering
20IFCT Part II. EGSE Preparation
- Acceptance and validation process
- COTS
- BOBs
- Connector savers
- PDU
- GASU
- TEM/TPS
- BPU
- Test Stands
- Test Procedures
21EGSE Process Design to Use
Integration and Test (IT) Subsystem Electrical
Ground Support Equipment (EGSE) Plan
LAT-MD-01533 Just released for review.
22Break Out Boxes are Ready
- Breakout boxes facilitate interface verification
without significant risk to flight hardware.
Note that the LAT electronics design does not
easily permit measurements of LVDS signaling
characteristics at data rate. Four boxes are
required - 26 pin interface
- 44 pin interface
- 78 pin interface
- 104 pin interface
- Adapter cables adapt between different pin outs,
connector styles and sizes. Examples of breakout
boxes are shown in the following picture
23Configuration Block Diagram, Tracker Test
EGSE
TKR
24Equipment List, Tracker Test
Type Manufacturer/Model/ID Number
VME Crate Dawn VME Products, 11-1011777-2119
VME, TST-STP Trans card LAT-DS-00999
VME SBC MVME2304 card Motorola PN MVME2304-0123
VME LCB Mezzanine card LAT-TD-00860
LCB Transition board cable LAT-DS-03247
DC Power supply BK Precision MN1786A
Uninterruptible Power Supply Tripp-Lite SU1000 or equivalent
28 Volt supply cable LAT-DS-03246
PS Control cable LAT-DS-02095-20
TEM to GASU cable LAT-DS-02106
CAT5 Ethernet cable TRD855PL-50
CAT5 Ethernet cable.RS-232 TDC003-7 (RECO98M connectors)
Local PC DELL, Model
Golden TEM/TPS
25Configuration Block Diagram, Two Tower Test
26Equipment List, Two Tower Test
27EGSE IN SINGLE TOWER ASSY FLOW
28EGSE IN TWO TOWER ASSY
29EGSE TEST REQUIREMENTS MD-00408
- Configuration of EGSE shall be controlled via
released documentation - EGSE shall be acceptance tested
- EGSE shall be validated before use if it has been
moved, reconfigured, or repaired - Validation shows that equipment is both ready for
use and safe to use - High degree of confidence that equipment in that
configuration has full operating capabilities - NASA guidance
- Perform an EICIT and an SVT to ensure electrical
safety - Trip points on circuit breakers, current limits
in power supplies, shall be verified - While everything is validated, the scope of
validation is tailored for each piece equipment
type
30STATUS OF EGSE COTS
- Digital Multimeters (IT responsible for these)
- Calibrated Instrument
- Validation Tests
- Embedded within test procedure that calls them
- STATUS Meter purchased exceed maximum voltage
for parts in some equipment, so we are
re-procuring - Borrowing Safe DMMs in the meantime
- Hand Tools
- Procured, cleaned, and placed in toolbox within
cleanroom - Automated Test Equipment for Safe to Mate
- All parts received - calibrated
- Interconnection harness designed in assembly
- Rack trays sent out for machining affected by
safety stand down at SLAC
31SCOPE OF EGSE TESTS BOBs ETC.
- Cables and break out boxes (IT is responsible
for these) - Design documentation complete and released
- Acceptance Tests include
- Configuration inspection to assembly drawing
- Interface integrity and cleanliness, inspection
- Electrical continuity isolation tests per
LAT-TD-04325 - Labeling with test due date, operator, QA
- Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical continuity tests, manual
- Connector Savers
- Tests Interface integrity and cleanliness,
inspection
32STATUS OF BOBs ETC
- All BOBs designed, built, and tested
- Inspection remains to be completed
- Associated cables designed, built to shortage,
and tested - The backshells for the 100 pin cables were back
ordered and just arrived. Estimate assembly
complete 12/1 - Inspection remains to be completed
- Long versions of the Two Tower test cables for
EGSE interconnections are awaiting the floor
layout to determine lengths. Design, build, and
test complete 12/31. - Acceptance and Validation Test Procedures in sign
off cycle
33STATUS OF CONNECTOR SAVERS
- Determining connector saver needs
- Coordinating with subsystems
- All ELX boxes arrive with connector savers on
each connector - CAL delivers mated to an EM TEM, so they are not
needed - TKR towers arrive with connector savers that will
be turned over to IT - Determining who buys connector savers for the
flight cables submitted lien to program office
to fund procurement - Complete determination by 11/24
34SCOPE OF EGSE TESTS - PDU
- EM PDU
- Acceptance Tests include
- Configuration inspection to LAT-DS-01696
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-02544-01 - Labeling with test due date, operator, QA
- Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Further validation tests performed within the
test stand using load box
35SCOPE OF EGSE TESTS PDU LOAD
- EM PDU LOAD BOX
- Acceptance Tests include
- Configuration inspection to LAT-DS-03400
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-04095-01 - Labeling with test due date, operator, QA
- Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Further validation tests performed within the
test stand
36STATUS OF PDU LOAD BOX
- Documentation
- PDU Assy, LAT-DS-01696, released
- PDU Test Procedure, LAT-TD-02544-01, released
- PDU Load Box Assy, LAT-DS-03400, released
- PDU Load Test Procedure, LAT-TD-04095-01,
released - EICIT Procedure, PDU, LAT-TD-04332, released
- SVT Procedure, PDU, LAT-TD-04332, in work (12/1)
- Delivered to IT
- Inspection, acceptance test, validation pending
development of flight documentation
37SCOPE OF EGSE TESTS - GASU
- EM GASU
- Acceptance Tests include
- Configuration inspection to LAT-DS-01611-09
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-04267-02 - Labeling with test due date, operator, QA
- Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Further validation tests performed within the
test stand
38STATUS OF GASU
- Documentation
- GASU Assy, LAT-DS-01611-09, released
- GASU/Test Stand Test Procedure, LAT-TD-04267-02,
released - EICIT Procedure, GASU, LAT-TD-04260, released
- SVT Procedure, GASU, LAT-TD-04382, in work (12/1)
- Delivered to IT
- Inspection, acceptance test, validation pending
development of flight documentation
39SCOPE OF EGSE TESTS TEM/TPS
- EM TEM/TPS
- Acceptance Tests include
- Configuration inspection to LAT-DS-01643
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-4085-01 - Labeling with test due date, operator, QA
- Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Further validation tests performed within the
test stand
40STATUS OF TEM/TPS
- Documentation
- TEM/TPS Assy, LAT-DS-01643, released
- TEM/TPS Test Procedure, LAT-TD-4085-01, released
- EICIT Procedure, TEM, LAT-TD-03875-02, released
- SVT Procedure, TEM, LAT-TD-04097-02, released
- EICIT Procedure, TPS, LAT-TD-03875-02, released
- SVT Procedure, TPS, LAT-TD-04098-01, released
- Two delivered to IT
- Inspection, acceptance test, validation pending
development of flight documentation
41SCOPE OF EGSE TESTS BUS PROTECTOR
- Acceptance Tests include
- Configuration inspection to LAT-DS-
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with LAT-TD-
- Labeling with test due date, operator, QA
- Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Validation tests performed in accordance with
LAT-TD-
42STATUS OF BUS PROTECTOR
- Requirements identified in EGSE Plan
- Design assigned within ELX
- Documentation needs be created
- Developing schedule with ELX to support Two Tower
Test
43TEM TEST STAND - CAL AND TKR TESTS
- Acceptance Tests include
- Configuration inspection
- LAT-DS-02861 CAL
- LAT-DS-03605 TKR
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-4085-01 - Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Perform tests described in LAT-TD-4085-01, Para.
5.5.4, Basic Test
44STATUS OF TEM TEST STAND
- Documentation
- CAL Test Stand set up procedure, LAT-DS-02861,
released - TKR Test Stand set up procedure, LAT-DS-03605,
released - TEM/TPS Test Procedure, LAT-TD-4085-01, released
- EICIT Procedure, TEM, LAT-TD-03875-02, released
- SVT Procedure, TEM, LAT-TD-04097-02, released
- EICIT Procedure, TPS, LAT-TD-03875-02, released
- SVT Procedure, TPS, LAT-TD-04098-01, released
- Two Test Stands delivered to IT
- Inspection, acceptance test, validation pending
development of flight documentation
45GASU TEST STAND TESTS IN 1X1
- Acceptance Tests include
- Configuration inspection LAT-TD-04267-02
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-04267-02 - Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Perform tests described in LAT-TD-4085-01, Para.
5.5.4, Basic Test
46STATUS OF GASU TEST STAND
- Documentation
- Assembly and test procedure, LAT-TD-04267-02,
released - Validation test, run LAT-TD-4085-01, released
- EICIT Procedure, GASU, LAT-TD-04260, released
- SVT Procedure, GASU, LAT-TD-04382, in work (12/1)
- Delivered to IT
- Inspection, acceptance test, validation pending
development of flight documentation
47GASU/PDU TEST STAND TWO TOWER
- Acceptance Tests include
- Configuration inspection LAT-TD-04267-02
- Interface integrity and cleanliness, inspection
- EICIT and SVT tests
- Functional Tests in accordance with
LAT-TD-04267-02 - Validation Tests include
- Verify Acceptance Testing has been performed and
is not due for re-test - Configuration inspection
- Interface integrity and cleanliness, inspection
- Electrical STM tests
- Perform tests described in
- LAT-TD-02544-01, Para. 5.3.6, PDU-GASU Interface
and electrical load tests - LAT-TD-4085-01, Para. 5.5.4, Basic Test
48STATUS OF GASU/PDU TEST STAND
- Documentation
- Assembly and test procedure, LAT-TD-04267-02,
released - PDU Validation LAT-TD-02544, released
- Validation test, run LAT-TD-4085-01, released
- EICIT Procedure, PDU, LAT-TD-04332, released
- SVT Procedure, PDU, LAT-TD-04332, in work (12/1)
- EICIT Procedure, GASU, LAT-TD-04260, released
- SVT Procedure, GASU, LAT-TD-04382, in work (12/1)
- Delivered to IT
- Inspection, acceptance test, validation pending
development of flight documentation
49TEST PROCEDURE STATUS
- IT Test procedures are being written prior to
completion of test plan. - CAL Test Procedure
- Draft complete and in review
- Draft must be updated with new input from CAL
subsystem (received after procedure completed) - Complete one week after CAL final update
- TKR Test Procedure
- Draft was complete and in review three weeks ago
- Draft was updated with new input from TKR
subsystem (received after procedure completed) - Complete one week after TKR final update
50TEST PROCEDURE STATUS (cont)
- Single Tower Test
- Draft in review in IT
- Affected by change to subordinate documents
- References to be updated and test descriptions
re-written - Complete 12/15
- Two Tower Test
- Draft begun
- Complete 12/31
- VG and CR Data Runs for LAT Integration
51IFCT Part III. Integration Facility
- Cleanroom
- Computing
52Cleanroom
- Building 33 Clean Rooms functional and occupied
- Monitoring system fully operational.
- Clean Rooms fully certified.
- All computers and oxygen sensors have battery
back ups. - Upgrades
- Grounding system for ESD and Multi-point ground
to be installed. ECD 1/3/05 - 15 ton crane to get two speed option, after
initial Grid handling. ECD 3/1/05 (TBR) - Stand alone hot water boiler. ECD 3/1/05 (TBR)
- Upgrade environmental controls on clean room air
handler. ECD 3/1/05 (TBR) - Substation upgrade. ECD 3/31/05
- Extend back up generator lease thru Jun 05. ECD
12/31/04
53Computing
- Hardware and networking
- Online network / firewall fully operational
- SLAC centrally administered accounts (active
directory) working - Upgrades
- RAID5 servers in hand (3 unitsspare) and
migration is in progress ECD Dec.18 - Environmental test computing infrastructure
design in progress