Title: Xenon Detector Status
1Xenon Detector Status
2Outline
- Detector Setup
- Operation
- Performance
- Problems and solutions
3Detector Setup
4PMT installation completed
- All PMT successfully installed in Aug 2007
together with - LEDs
- Alpha sources (plates and wires)
- PT100 temperature sensors
- Laser fibers
- Surface level meter
- lt 200300um gap btw inner slab and wall
xenon
g
5Sensors, LEDs, and alpha sources
Capacitor-type surface level meter
Pt100 Temp sensor 22 sensors in LXe 21 sensors on
the wall
- Two type of a sources
- Plate 20 pieces
- Wire 5x5 wires
LED 3 different attenuation x 10
6Cabling and Al filler installation
7.5l
4.5l
- Filler volume
- Lateral 7.5lx6x2 4.5lx2x2 108l (design) 108
7.5(US) 4.5(DS) 96l (reality) - Bottom 49l (design) 49 10 39l (reality)
7We were ready to close but
- The shape of the newly delivered sealing (metal
gasket) was wrong ! - Does not fit the groove?!
- Radii were correct but they made a mistake in
bending - Sent back to Garlok and repaired
- While waiting repair work, old gaskets were
recycled with indium foil around the corner - Vacuum test OK
- But leak of the order of 10-4 mbarl/sec with 1
bar xenon in the cold vessel
1 bar xenon
outgas
vacuum
Warm vessel vacuum
Xe leak
Mass spectrometer
8RGA of leaking xenon
- Doubly charged 132Xe (Xe) is used to evaluate
amount of xenon in the warm vessel - Production cross section with 110keV electron is
40 of Xe production - Used as reference data for later use
10-4 mbarl/sec leak
9Closing the covers
- Gaskets replaced with newly delivered ones on
5/Sep - Super-insulator on the cold vessel
- 240 Nmm torque
10Pressure/leak test
- Xenon gas (liquid) in the cold vessel
- Mass spectrometer on the warm vessel
- RGA data with recycled gasket used as a reference
- Doubly charged 132Xe (Xe) is used to evaluate
amount of xenon in the warm vessel - Production cross section with 110keV electron is
40 of Xe production
10-4 mbarl/sec leak
11Estimation of xenon leak rate
Recycled gasket 10-4 mbarl/sec leak Room
temperature xenon gas
New gasket Room temperature xenon gas
Better at low temperature
12Operation
13Gas/liquid system
Gas-phase purifier
Gas line
Liquid line
High pressure Storage
Detector
1000L dewar
Liquid-phase purifier
14Evacuation and liquefaction
- Evacuation started on 5/Sep
- Thanks to cryo pump (AISIN)
- 6.9x10-3 Pa in 3 days
- Cooling started on 10/Sep
- Liquefaction started on 15/Sep
- Surface level was monitored with
- Temperature sensors
- Level meter (long and short)
Cryo pump
Xenon gas
0.11 MPa
0.133 MPa
15Liquid transfer
- Liquid transfer by pressure difference between
two cryostats through a vacuum insulated pipe - Started on 17/Sep and completed on 20/Sep
- 10 liter/hour transfer speed
- Xenon filling was done in 15 days after starting
evacuation
3m
16End of xenon filling
temperature
Level meter
- Additional 10 liter was transferred for assurance
17How many liters of liquid xenon?
- Cryostat volume 1200 liter
- PMT and support 142 43 185 liter
- Filler 135 liter
- Lateral 96 liter
- Bottom 39 liter
- Cable 2030 liter
- Additionally transferred amount of xenon 10
liter - 1200 185 135 25 10 865 liter
- Consistent with remaining amount of xenon in the
dewar
18Slow Control
Labview
megon00
PC in barrack
MEG Central DAQ System (SCFE)
For shift crew use
Labview
XEC PC 2
XEC dedicated SCFE Node cooperation Alarm to
experts
XEC PC 1
For expert use
Important controls are implemented in SCS nodes
Detector, storage, dewar, purifiers
19Liquid circulation
Purifier Cartridge Molecular sieves, 13X 25g water
Freq. Inverter OMRON
- Circulate xenon in liquid phase
- Circulation pump
- 100liter/h_at_3175rpm, Dp 0.2MPa
- Molecular sieves
- gt24 g water absorption
PT
20Succeeded!
Circulation period
50.63Hz !
- Circulation speed evaluation
- change of the surface level after closing the
inlet valve - 3.6 / 30sec 432 / h
- 1 corresponds to 0.165 liter
- 0.165x 432/h 71 liter /hour
21Liquid-phase purification
- Light yield for 17.6MeV g saturated around 23/Nov
(180h purification time) - Necessary to continue longer than we expected
- 5 hours purification was enough in the LP test
(100L LXe) - Probably due to
- slower circulation speed (100L/h ? 70L/h)
- Worse initial condition compared to the LP
- Needed longer time to prepare monitoring tools
due to PMT HV feedthru problem (reported later) - Noise from the pump (freq. inverter?) affected
other detectors
C-W run 17.6MeV gamma
22Absorption Length
- Ratio Data/MC vs distance fitted with an
exponential curve. - Inner and Outer face PMTs
- Cosine of incidence angle lt -0.2
- Slope compatible with zero (no absorption).
l gt 3 m _at_95 C.L.
After 50 h purification, 4/Nov
Alpha source
PMT
23Performance
2D display, charge/time
2D hist, chargePMT
3D reconstructed position
Waveform
1D histograms
Chargeevent
24PMT Calibration
- PMT calibration
- LED
- PMT gain
- Flushing LEDs at different intensities
- Npe1/s2
- Time offset calibration
- Viewing one LED flushing with many PMTs
simultaneously - Alpha
- QE and absorption length evaluation
- Liquid and cold gas
25Time offset determination
- Possible method only in non-segmented detector
like ours - c is obtained by using all data
Different LEDs viewed by one PMT
Measured
Flashing Time Of i-th LED
Speed of LED light
Offset of j-th PMT
Tj
RD run (ultra low)
ti ti-1
1/c
txe - tTC
li,j-li-1,j
26C-W run
- Li at 14.6, 17.6 MeV
- B at 4.4, 11.7 and 16.1 MeV
- Details in Giovannis presentation
27CEX run - Pi0 calibration
- CEX process
- p-p?p0n
- p0(28MeV/c) ? g g
- 54.9 MeV lt E(g) lt 82.9 MeV
- LH2 target
- NaI tagging counter
- 3x3 crystals, APD readout
- Pb collimator panel in front of the Xe detector
g
28LH2 Target
- Pressure test of cell 4.5 bar (abs)
- Time to liquefy
- 80 min from start of LHe flow
- Liquid stability
- 1.2 bar operating pressure (96 cell full)
- 1.3 RMS, 6 max excursion
- Liquid Helium consumption
- 2.4/h
- 42h auto
29NaI Detector
beam axis/- 21 (/- 0.07) deg.
Up/down/- 60 (/- 0.005) deg.
30CEX run data analysis, preliminary
- Position cut
- Cut shallow events (lt 2cm)
- Select only center events ( u,v lt 5cm)
- Position correction
- Pile-up rejection by light distribution
- Select center event on NaI detector
- Not applied QE correction
- If applied worsen resolution.
- Pedestal has 2 spread
- Needs better baseline evaluation
- Check hardware for 2008 run
55MeV gamma
pedestal
sup 2.4 FWHM 6.5
31Time Measurement
Intrinsic resolution by T-B analsysis
- Using only 12 PMTs around the center
115ps
- T weighted mean of inner PMT timing after
subtracting photon propagation time - Effective velocity 10cm/ns
32Position Measurement
- Using collimator run data,
33Physics run
- RD run gamma energy
- Data Xe self trigger threshold3.5V
- MC RD event generation event overlaps
trigger simulation - Vertical scale is scaled assuming,
- Mu stop 5e6
- Calorimeter acceptance 0.1
- Calorimeter detection efficiency 0.6
34Problems found in 2007andsolutions for 2008 run
35Feedthru
- We could not apply required voltage on all PMTs
at the beginning - We found that this had been caused by spark in
the feedthru - Needed to prepare new ones for 2007 run
- Commercial products or hand made?
36How did we make new ones?
Watarus Design
Air
Metal body
Glass insulator
Xe
- Production procedure
- Fix pins in the holes and fill with silica
- Bake in argon atmosphere
- Cool down
No need to change connector Replacement can be
done quickly Body made of insulator (not metal)
37Installation
- Oct. 10-12 LXe recovery to 1000L Dewar
- Oct. 13-14 GXe recovery
- Oct. 15-16 Mounting new flanges testing
- With flushing dry nitrogen gas in the cryostat
- Oct 17-19 evacuation
- Gas filling 0.13MPa
- Successfully took gas alpha data at 800, 900,
1000V - LED data
- Liquid transfer started at almost same time
- Until the detector is cooled we continued LED and
alpha DAQ - 21, 22, 23/Oct transfer speed 1520 liter/hour
- Completed early morning of 24/Oct
- 2 weeks interruption of DAQ
38PMT status after replacing feedthru
- Stable operation after replacing feedthru
- LED intensity optimization
- Better gain evaluation than before
39As a bonus
- Xenon recovered through purifier
- Practice to transfer the liquid to the dewar
- Water contamination suppressed
- Cryostat was warmed up to 220K
- 1st experience of temperature cycle
- Test of the gasket
- RGA I 3.8x10-13A ? 5.7x10-7 mbarl/sec
132Xe
40Future plan (currently ongoing)
- Replacement during winter shutdown
- 48 pin x 6 x 4
- Need to change connectors
- Used in the small prototype and PMT test chamber
ceramic
Kyocera Ultra High Vacuum Feedthrough
welding
41Heat load
- Pressure is slowly increasing under normal
operating condition. - Refrigerator cooling power 200W
- Expected redundant cooling power 100W
- Calculation based on LP modeling
- PMT37W (Vmean 775V)
- Conduction64W
- Cable (50), Chimney (4.8), SI(3.1), Support(6.3)
- Heat income through Cu cooling pipes was not
taken into account - Cu heat conduction 390 W/m/K
- 10mm diam 1mmt pipe, 20cm
- 390 x 135 (K) x 2.83x10-5/0.2 (m) 7.4W
- 6 pipes ? 44.4W
- Cf. Steel heat conduction 20W/m/K
- There seems to be other heat leak
- Larger than 50W
- Super-insulator?
42LN2 cooling pipe
- Cu pipe feedthru ? SUS pipe feedthru
43Cooling Power
44Blow up of low temperature valve
- Low temperature valves blew up
- A few liters of liquid xenon was lost
- Purifier cryostat was opened
- Misleading valve design
- No documentation on the manual
- Piping was modified and no valve is in use now
Wilson Seal
Air
Wilson Seal
xenon
Plug or shaft
Cup nut
collar
bellows
O-ring
Liquid xenon
45PMT Signal Splitter
- Spark in feedthrus destroyed protection zener
diodes on PMT splitter boards - base-line shift at splitter output
- Signal was out of range of WFD
- Fixed by replacing all zener diodes
DRS
splitter
PMT
Trigger
46Light YieldDiscrepancy between a and g data
- Energy scale discrepancy btw alpha and gamma
- Too small light yield from g events (1/2)
- Not due to magnetic field
- Confirmed by taking C-W data w/o COBRA field
- Purity seems good
- Improvement and plateau of light yield of both
gammas and alphas - Have a look on WF
a
47Waveforms
- ?triplet 22 ns
- ?recomb 45 ns
ta 21 ns
tg 34 ns
! Careful treatment of electronics time constant
is necessary
Before purification
Q/A
was 1.93/-0.02 in LP test
A
Q
Electronegative impurity? Oxygen??
48Electronegative Impurity Removal
- O2 getter cartridge
- Developed for LAr use at CERN
- be mounted at the exit MEG liquid-phase purifier
with by-pass valves - Preparing an oxygen purity monitor also
- will be ready at an early stage of 2008 run
49Current Status and Schedule
- Xenon recovered to the 1000 liter dewar
- Gas analysis will be done on site
- Cryostat is opened now
- All PMTs and cables are checked
- Replacing feedthru is in progress
- LN2 cooling pipe modification
- Cryostat will be moved back to PiE5 at the end of
March - Evacuation, liquid transfer, purification
- Ready on 19/April
- Schedule at http//meg.web.psi.ch/subprojects/inst
all/xenon.html