Xenon Detector Status - PowerPoint PPT Presentation

About This Presentation
Title:

Xenon Detector Status

Description:

He leak test. 1.8Bar He was filled and found that ... Supporting structure installed to evacuate the inner vessel for the leak test. cover ... Leak test again ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 20
Provided by: satoshi5
Category:

less

Transcript and Presenter's Notes

Title: Xenon Detector Status


1
Xenon Detector Status
  • Liquid Xenon Group

2
Outline
  • Cryostat construction
  • Honeycomb panel test at Pisa
  • Assembly
  • Cryogenic test at SIMIC
  • Leak test at PSI
  • Detector preparation at PSI
  • Alignment at PiE5
  • PMT installation
  • Schedule

3
Cryostat delivery to PSI
  • Delivery to PSI on 5/June
  • 6 weeks delay from the schedule reported in the
    previous review meeting
  • Delay of construction
  • not due to a technical problem
  • Delay of the cryogenic test at SIMIC
  • Difficulty to stop leak

4
Honeycomb panel test completed
  • 3rd panel delivered to Pisa at 1630 on 20/Feb
  • Mounted on the text box and tested on 22, 23/Feb
  • 3 bar
  • Inspection by a Plyform expert
  • 4 bar x4 times
  • Hold for 3 minutes at 4 bar in the last test
  • Panel deformation (max)
  • 0.3 mm at 1 bar
  • 3.4 mm at 4 bar

Holes for evacuation
5
Inspection of the panel
6
Low temperature test
  • Wrapped with insulators and cooled with LN2
  • Pressurized with compressed air
  • 2 bar
  • No damage on the panel found

7
And mounted on the cryostat
  • 400 micron carbon-fiber plate between the panel
    and window to fill the gap

As of 13/Mar
8
Cold and Warm Vessel Assembly
As of 19/April
9
Cryogenic Test at SIMIC
  • -18/May
  • All nuts on the covers of the cold vessel were
    fastened tightly and the warm vessel was
    evacuated whole weekend.
  • 21/May
  • He leak test. 1.8Bar He was filled and found that
    the leak rate was larger than 10-4 mbarl/sec.
    Keep evacuation during the night.
  • 22/May
  • cooling using cold gas from the LN2 tank. Cold
    gas in the cold vessel Most parts were cooled
    down to -5-10 degree C.
  • 23/May
  • liquid N2 through the cooling pipe. All parts
    cooled below -110 degreeC around 1200.
  • Then N2 gas at 1.0Bar and He gas filled step by
    step with measuring leak rate.
  • N2 1.0 bar He 0.2 bar ? 5x10-7 mbarl/sec
  • N2 1.0 bar He 0.4 bar ? 1.6x10-6mbarl/sec
  • N2 1.0 bar He 0.6 bar ? 7.8x10-6mbarl/sec
  • N2 1.0 bar He 0.8 bar ? 2.2x10-5mbarl/sec
  • The leak was not fixed at SIMIC by any means.
  • We decided to bring the cryostat to PSI and
    perform a leak test

10
Cryostat arrived at PSI
  • Delivery at 700 am on 5/June
  • Works to be done
  • Cleaning
  • Leak/pressure test
  • Alignment
  • PMT installation

11
Leak and Pressure Test at PSI
  • The metal gasket was not compressed correctly due
    to deformed shape of the flange
  • Re-machining the flanges by hand
  • Supporting structure installed to evacuate the
    inner vessel for the leak test

cover
flange
gasket
12
Leak Test at PSI
  • Finally we found a hole on the welding line of
    the thin window!

13
Leak test again
  • After closing the hole, we performed a leak test
    again (with recycling the metal gaskets and with
    viton O-rings)
  • Cracks found at corners
  • Eddy-current measurement
  • US-bottom d1.3mm L7mm, -top OK
  • DS-bottom d0.8mm L13mm, -top d0.8mm L5mm
  • It was confirmed that these did not cause leak.
  • In the end we confirmed the tightness of the
    cryostat by using viton O-rings.
  • Leak rate lt 3x10-9 mbarl/sec

14
Alignment at PiE5
  • Decide the cryostat position on the platform.
  • Check how we can install the cryostat in the
    electronics hut

15
Alignment at PiE5
  • Alignment of the cryostat
  • PMT support is aligned relative to the beam line
    within an accuracy of 1mm
  • Cryostat leg positions determined on the platform
  • Screw holes to fix the legs
  • G10 insulator between the platform and legs

16
Piping and cabling
  • Working in a clean hut
  • Cabling from patchpanels to feedthru almost
    finished
  • LN2, GXe, LXe piping is ongoing in parallel to
    PMT installation

17
PMT installation
  • Patchpanel Feedthru cabring completed
  • PMT installation started on 8/July
  • Outer and Top PMT installation completed on
    9/July
  • Now working on the inner (as of 12/July)

18
Schedule
  • PMT installation, -19/July
  • PMT test at room temperature, 20-23/July
  • He leak test, 25-28/July
  • Ready to move to PiE5 on 30/July
  • Evacuation and liquefaction in August
  • 950 liter xenon is already liquefied
  • Alpha/cosmic runs at the end of August
  • In parallel to purification
  • Monitor xenon purity

19
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com