Title: Earned Value Management and Past Performance
1Earned Value Management and Past Performance
- NCMA Suncoast Chapter
- November 30, 2006
David Muzio DLM Consulting
2Why Earned Value Management?
- Fluid Project Baselines
- Continuing problem
- Poor budget discipline
- FASA, Title V
- Establish Cost, Schedule and Performance Goals
for Major Acquisitions and achieve, at least, 90
of the goals. - If project not within 90 of goals, Agency Head
shall (1) determine if there is a continuing
need for the project, and (2) identify suitable
actions to be taken, including termination. - Clinger-Cohen Act of 1996
- OMB - Establish the processes for executive
agencies to analyze, track, and evaluate the
risks and results of major investments in IT - Report on the net program performance benefits
achieved by agencies - Agency Requirements
- Implement OMB policies through effective capital
planning and performance and results based
management
3Why Past Performance?
- Improves contract administration and the ability
to select the best contractors for future work. - Provides a formal mechanism for, at least, an
annual discussion between the customer and
supplier on contract performance and provides a
record of that discussion. - Provides the Government customer a standard way
to annually rate a suppliers performance on a
contract. - Allows the Government to input contract
performance information into a central database
for use by all other government contracting
officers in making source selection decisions for
new contracts. - Encourages outstanding performance throughout the
life of a contract.
4Earned Value Management
- A project management tool that integrates the
project scope of work with schedule and cost
elements. - ANSI/EIA Standard 748-1998-A, Earned Value
Management Systems. Reaffirmed Aug 28, 2003 - Copies from Global Engineering Documents
- (1-800-854-7179)
- EVM information at
- www.pmi-cpm.org
- http//acc.dau.mil/evm
- http//www.ndia.org
5History of EVM (CSCSC)
- DOD developed CSCSC early 60s
- Air Force initially developed system for the
Minuteman Missile program. Lt. Gen. Driessnack - Reason Major Contract Overruns, and lack of
government visibility into contract status. - Contractors reluctant acceptance
- concerns Government imposed, complicated and
cumbersome 35 Criteria - Boeing used modified CSCSC in Commercial Airplane
Division on development of 747 - Raytheon 1974 First Multi-Plant/System
Certification
6History of EVM (CSCSC)
- April 1976 First OMB Circular on program
management A-109 - 1969 Commission on Government Procurement deep
concerns over management effectiveness of major
systems - Requirement to assess acquisition cost, schedule
and performance experience against predictions,
and provide such assessments to the agency head
at key decision points. - DOD adopted A-109 policies, continued to require
CSCSC, other agencies did not.
7History of EVM (CSCSC)
- OMB Response to FASA and CCA in 1996 - complete
rewrite of Circular A-109 - Team of 82 people from 14 Major Agencies and GAO
- DOD working with NDIA to convert Government CSCSC
to Industry EVM. - DOD using draft EVM until ANSI/EIA Standard 748
issued in 1998. - Programs reviewed quarterly at DOD
- Programs held to 1 to 2 overruns during late
1990s - GAO reviewed use of EVM in State and local
government and private industry. - Motorola used EVM on 4.6 Billion Iridium Program
- Model for good project management with EVM used
on fixed price subcontracts, including with
Russia and China. - Virginia used on construction
8OMB Policy Developed 1995-1997
- Included in Circular A-11 - Preparation,
Submission, and Execution of the Budget 1996 - Eight (8) Parts Issued annually
- Part 7 Planning, Budgeting, Acquisition and
Management of Capital Assets - Instructions on budget justification and
reporting requirements - requirement for a business case
- Supplement to Part 7 Capital Programming Guide
version 1, May1997, Version 2, June 2006 - Specific program and contract management
guidance, which is flexible policy, unless
deviation is granted by OMB. - Original guidance EVMS or Similar
- 2002 EVMS only to manage program and report
status to management and OMB.
9(No Transcript)
10Good Policy - No Real Management By OMB No Real
Progress
- Executive Branch Management Scorecard Started
2002 on Presidential Management Agenda. (See
www.results.gov or www.whitehouse.gov/omb - Good intentions and good beginnings are not the
measure of success. What matters in the end is
completion performance and results. - To ensure accountability, a traffic light
grading system is used to track how well agencies
are executing the management initiatives and
where they stand at any point in time.
11(No Transcript)
12(No Transcript)
13Success Factors
- Justify projects with complete business cases
adequately addressing, expected life-cycle costs,
acquisition strategy, performance standards tied
to agency strategic goals, alternatives analysis,
risk management, cost and schedule analysis
(EVMS) and - Demonstrate management of projects using EVMS
achieving, on average, 90 of cost, schedule and
performance goals and for IT - Secure at least 90 of operational systems and
- Have an effective Enterprise Architecture and
- Avoid redundant or agency unique systems
14EIA 748 is a Guideline
- High level and goal oriented
- States qualities and operational considerations
of an integrated management system using EV
analysis methods - Does not mandate detail system characteristics
- Process must fit firms management style and
business environment. - One size does not fit all contracts
15EVMS Principles
- Plan all work scope for the program to completion
- Break down the program work scope into finite
pieces that can be assigned to a responsible
person or organization for control of technical,
schedule and cost objectives. - Integrate program work scope, schedule and cost
objectives into a performance measurement
baseline plan against which accomplishments may
be measured. - Control changes to the baseline.
16EVMS Principles (Cont)
- Use actual costs incurred and recorded in
accomplishing the work performed - Objectively assess accomplishments at the work
performance level - Analyze significant variances from the plan,
forecast impacts, and prepare an estimate at
completion based on performance to date and work
to be performed - Use EVMS in the Companys Management processes.
17EVMS Is A Central Key to Project Management
- EVMS required on all contracts with development
effort - Application of EVM principles (use WBS) begins
during the program definition to ensure that
technical requirements and schedule and cost
estimates are properly integrated to support
program authorization. - Program baselines are finalized and risks
identified by ensuring the contractor or in-house
project is using an ANSI-748 System and through
the completion of an Integrated Baseline Review - Project management is accomplished through
implementation of EVMS and the resulting
reporting of achievement or variations from cost,
schedule and performance goals. - Variations from plan are expected, it is how they
are handled that is important. - Do not use incentives to achieve 1.0 CPI and SPI
18CONTRACT WBS (CWBS)
LEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4 LEVEL 5
COST ACCOUNTS
19WHY HAVE A WORK BREAKDOWN STRUCTURE (WBS)?
- Provides a product framework for organization and
management of the project - provides a common framework for planning and
controlling cost, schedule, and work scope - allows work to be broken down into cost accounts
--- the lowest level of visibility
20Responsibility Assignment Matrix
The control account level is determined by the
responsibility assignment matrix (RAM). The RAM
is defined by combining the contract WBS with the
organizational structure.
21A COST ACCCOUNT IS MADEUP OF WORK PACKAGES
In-Progress Work Package
50
65
80
Planned Work Package
50
Completed Work Package
25
70
30
J F M A M J J A
S O N D
22ESTABLISH THE BASELINE
2. SCHEDULE THE WORK
3. ALLOCATE BUDGETS
100
TIME
60
80
20
40
15
40
23The Time-Phased Spend Plan
Years
24 Earned Value Measurement
PLANNED
ACTUAL COST
PERFORMED
2
2
2
2
15
10
10
5
5
5
5
5
5
5
5
25
3
3
3
3
BUDGET 50
EARNED VALUE 35
COST 40
STATUS Schedule Variance Earned - Budget -
15 Unfavorable Cost Variance
Earned - Actual - 5 Unfavorable
255 PERFORMANCE INDICATORS
26COST PERFORMANCE REPORTINGKEY DATA ELEMENTS
27What Capital Investments Require a Business Case
(Exhibit 300) ?
- All major capital investments
- Land, structures, equipment, intellectual
property (e.g., software), information technology
(including IT service contracts), environmental
restorationSee appendix 1 of the CPG) - All major IT investment business cases must be
submitted to OMB with the Budget - For all other types of capital assets OMB shall
request a sample of the business cases (Section
II.9.2. CPG) - Important note All information necessary to
complete an Exhibit 300 already exists as part of
project specific documentation. Materials used
to populate the Exhibit 300 should be readily
available to OMB upon request.
28Section C Acquisition/Contract Strategy
- 1. Complete the table
- Contract of Task Order Number
- Type of contract/task order
- Has the contract been awarded (Y/N)
- Date of award, if not awarded, planned date
- Start and end date of contract/task order
- Total Value of Contract/T.O. (includes all
options) - Is this an interagency acquisition?
- Is it performance-based?
- Competitively awarded? (Y/N) (many T.O.s will
not be). - Alternative financing? (ESPC, UESC, EUL, N/A)
- Is EVM in the contract? (Y/N)
- Does the contract include the required security
and privacy clauses? (Y/N)
29Section C Acquisition/Contract Strategy
- Name of Contracting Officer
- CO contact information (phone/email)
- CO Certification Level. ( 1, 2, 3, N/A)
- If N/A, does the CO have the competencies and
skills necessary - 2. If EVM is not required or will not be a
contract requirement for any of the
contracts/T.O.s, explain why - Do the contracts ensure Section 508 compliance?
- Is there an acquisition plan which has been
approved in accordance with agency requirements - If yes, what date?
- If no, will an acquisition plan be developed?If
no, explain why
30Acquisition Plan
- Actual plan developed must meet the requirements
in - FAR Part 7, Acquisition Plans
- FAR Part 34, Major System Acquisition
- OMBs Capital Programming Guide
- Phase 1 Planning and Budgeting
- Phase II Acquisition
31FAR 7.105(b)(10) Management Information
Requirements.
- If an EVMS is to be used, discuss the methodology
the Government will employ to analyze and use the
EV data to assess and monitor contract
performance. - Discuss how the Offerors/Contractors EVMS will
be verified for compliance with ANSI/EIA 748 and
- The timing and conduct of IBRs (whether prior to
or post award).
327.105(b)(3) Source Selection Procedures
- When EVM is required (see FAR 34.202(a)) and a
pre-award IBR is contemplated, the acquisition
plan must discuss - How the pre-award IBR will be considered in the
source selection decision - How it will be conducted in the source selection
process (see FAR 15.306) and - Whether offerors will be directly compensated
for the costs of participating in a pre-award
IBR.
33CPG Contracting
- 1.5.5.5 Integrating EV into Acquisition Strategy.
- All contracts with EVM are required to have an
IBR pre- or post-award to finalize the agreement
on the baseline and ensure the risks are
identified and understood. - Depending on the risk to establishing an
achievable performance measurement baseline at
time of contract award, the use of an IBR before
or after award must be determined. - Nevertheless, agencies are expected to achieve at
the completion of the contract at least 90
percent of the cost, schedule and performance
goals established at the time of contract award.
34Part 34, Major System Acquisition
- 34.2, Earned Value Management Systems,
- (a) An EVMS is required for major acquisitions
for development, IAW OMB A-11, The Government may
also require an EVMS for other acquisitions, IAW
agency procedures. - (b) Offerors that propose to use a system not in
compliance with 748 must submit a comprehensive
plan for compliance - (e) COs will determine the adequacy of the
proposed EVMS plan prior to contract award - (c) At a minimum require monthly EVM reports
- (d) EVMS requirement will be applied to
subcontractors using the same rules as applied to
the prime contractor.
35Two Provisions, One Clause for EVM
- 52.234-2 Notice of EVMS Pre-Award IBR
- 52.234-3 Notice of EVMS- Post-Award IBR
- The above are the same, except the Pre-Award IBR
provision has a paragraph (d) The Government
will conduct an IBR, as designated by the agency,
prior to contract Award. - 52.234-4 Earned Value Management System
- (a) The contractor shall use an EVMS that has
been determined by the Cognizant Federal Agency
(CFA) to be compliant with the guidelines in
ANSI/EIA 748 (current version at time of award)
to mange the contract. (See NDIA EVM Systems
Acceptance Guide) - (d) The CO may require an IBR at
- Exercise of significant options, or
- Incorporation of major modifications.
- CPG I.5.5.5 - An IBR must be accomplished
whenever there are major changes to the baseline.
36CPG Contracting
- TM contracts should only be used in the planning
phase and only when there is insufficient
knowledge about the requirement to be able to use
a cost reimbursement contract. - Agencies should only require in the contract
sufficient goods or services to result in the
agency receiving complete useful assets. Do not
incentive contractors to provide more than needed
to meet strategic goals. - EVM is normally used on Fixed-price incentive
contracts and cost reimbursement contracts. EVM
shall also be used on firm-fixed price and any
other type of contract that meets the major
acquisition threshold if that contract contains a
significant amount of development work.
37Part II-Section B Risk Management
- Expected to have performed a risk assessment
during the early planning and initial concept
phase, developed a risk adjusted life-cycle cost
estimate and a plan to eliminate, mitigate or
manage risk, and be actively managing risk
throughout investments life-cycle - 1. Does the investment have a Risk Management
Plan? - If yes, date
- Has the plan been significantly changed since
last years submission to OMB? - If yes, describe significant changes.
- 2. If no plan When?
- 3. Briefly, describe how investment risks are
reflected in the life-cycle cost estimate and
investment schedule - Use appendix 5, Risk Management, as the basis for
your risk management process - Use appendix 9, Cost Estimating, as the basis for
your cost estimating process - Agencies are expected to award contracts that
have a high probability of achieving at least 90
of the cost, schedule and performance goals
established in the planning phase.
38CPG Risk Principles
- Risk management leads to the development of a
Risk-Adjusted Program Budget and Risk-Adjusted
Schedule (See NDIA EVM Application Guide) - The IPT must ensure that the proposals and
in-house estimates clearly recognize the amount
and impact of risk on cost, schedule and
technical effort. - New technology should be subject to Technical
Readiness Level (TRL) and Degree of Difficulty
(RD3) reviews to help determine the risk and
necessary reserves. - High risk should be accepted only if it can be
justified by high expected returns, and only if
program failure can be absorbed by the agency
with loss of service capability or significant
effect on the budget. - Decision thresholds should be set for cost,
schedule and performance expectations of
development projects beyond which the ROI becomes
so low that the project should be cancelled.
39Part II-Section C Cost and Schedule Performance
- EVM is required only on DME (development)
portions of investments - For mixed life-cycle, OM milestones should still
be included in the table (Comparison of Initial
Baseline and Current Approved Baseline.) - Does the EVMS meet the criteria in 748? Y/N
- What is
- PV, EV, AC
- What costs are included, Govt. Only/Contractor
Only/Both? - SPI
- SV
- CPI
- CV
- Is the CV or SV greater than /- 10
- Explain variance
- Use the EVM system to identify the specific work
packages where problems are occurring. - Corrective Actions, with risk included
- Current EAC
- Any significant changes to baseline in past year?
- If yes, when approved by OMB?
40(No Transcript)
41EVMS Data Indicated EVM Not Being Implemented
Properly
- In 2005 many agencies submitted EVM data showing
SPI and CPI close to 1 - Agencies at same time asking for budget increase.
- For the 2006 Budget, OMB requested agencies to
first self-evaluate their business cases, and - Before beginning development, ensure cost,
schedule and performance goals are independently
validated for reasonableness. - Inspector Generals, current IVV reviewers, or
any other source internal or external to the
agency, including another agency. - Pre-Award Integrated Baseline Reviews may be
substituted for a independent validation.
42Requirements for Fully Implementing EVMS
- 1. Comprehensive agency policies by December 31,
2005 New or Verified - --Use NDIA EVMS Application Guide and those
listed below - 2. EVMS requirements in contracts or agency
in-house project charters - 3. Compliance Reviews of agency and contractor
EVM systems - - Use NDIA Intent Guide and Systems Acceptance
Guide
43Requirements for Fully Implementing EVMS for IT
Projects
- 4. Periodic system surveillance reviews to ensure
the EVMS continues to meet the guidelines in
ANSI-748 - -- Use NDIA Surveillance Guide
- 5. Integrated Baseline Reviews
- --Use NDIA Program Managers Guide to the
Integrated Baseline Review.
44Benefits of EVMS
- Reduces propensity of customers/boss to add work
without adding budget - Ties budget directly to work
- Requires all work transfers to include associated
budget - Requires all budget transfers to include
associated work - Fosters management decisions within a framework
of reality, rather than latent unease.
45Questions ?
- Agencies have flexibility in how they implement
the key principles and concepts in the CPG. - However, the key principles and importance of
thorough planning, risk management, full funding,
portfolio analysis, performance-based acquisition
management, accountability for achieving the
established goals will not change - In General, OMB will only consider recommending
for funding in the Presidents Budget priority
capital asset investments that comply with good
capital programming principles.
46Past Performance
- The Federal Acquisition Streamlining Act of 1994,
mandated the collection and use of contractor
performance information. - FAR Subpart 42.15 Contractor Performance
Information - FAR 42.1501
- Past performance information is relevant
information, for future source selection
purposes, regarding contractor actions under
previously awarded contracts.
47FAR 42.1501
- Past performance information includes
- Contractors record of conforming to contract
requirements and standards of good workmanship - Record of forecasting and controlling costs
- Adherence to contract schedules, including the
administrative aspects of performance - History of reasonable and cooperative behavior
and commitment to customer satisfaction - Generally, the business-like concern for the
interest of the customer
48FAR 42.1502 Policy
- Evaluations are required for each contract in
excess of 100,000. - At time of contract completion
- Contracts exceeding one year in duration,
including options require interim evaluations - Evaluation is generally for the entity, division,
or unit that performed the contract - Each agency establishes procedures
- Generally use scale of 1 to 5 with narrative
49FAR 42.1503
- Technical office, contracting office and end
users input to the evaluations - Evaluations are provided to the contractors
- Contractors have 30 days to respond
- Disagreements reviewed at a level above the
Contracting Officer - Marked Source Selection Information
- Evaluations revealed to other Government COs and
the Contractor. - Evaluations retained for three (3) years
50Past Performance Information Retrieval
System(PPIRS)
- Web-enabled Government-wide application which
currently collects information from - Past Performance Data Base NASA
- Past Information Management System ARMY and
DISA - Contractor Performance Assessment Rating System
- Navy, USMC, Air Force, DLA and other Defense
Agencies - Construction Contractor Appraisal support System
- Contractor Performance System - NIH
- HHS, Agriculture, Treasury, Commerce, Justice,
Energy, Interior, Labor, VA, SSA, USAID, EPA,
FEMA GSA, Transportation, Education, State,
Export-Import Bank and the Architect of the
Capital - All of the above subsystems will be turned off
next year?
51New Guide and FAR Rule
- Contractor Performance in the Acquisition Process
- Draft open for comment at http//www.acquisition.
gov - Comments due January 16, 2007
- FAR rule currently being processed and will be
issued for comment at a later date
52Chapter 1- Pre-Solicitation Use of Performance
Information
- Designing Factors and Subfactors
- Should be designed to evaluate the key
performance requirements of the solicitation. - Whether done as a stand-alone evaluation factor,
or integrated with other factors, the
solicitations should request the offerors record
for - On-time delivery
- Technical quality and accomplishments
- Cost control
- Business relations
- Performance on subcontracting plans/programs.
53Exhibit 3-1
54Contractor Performance Information Report Summary
Exhibit 3-11
55Contract Management at its Simplest
- What is the Government getting for the money it
is spending? - If it was your money would you spend it?
- Questions