NOAA POES PROGRAM Future Satellite Status - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

NOAA POES PROGRAM Future Satellite Status

Description:

Repair dependant on refurbishment of thrusters by Valve-Tech and ... Spacecraft having Reaction Control System partially refurbished due to 'leaking' thrusters. ... – PowerPoint PPT presentation

Number of Views:20
Avg rating:3.0/5.0
Slides: 13
Provided by: POES9
Category:

less

Transcript and Presenter's Notes

Title: NOAA POES PROGRAM Future Satellite Status


1
NOAA POES PROGRAMFuture Satellite Status
  • Presented to
  • ARGOS OPERATIONS COMMITTEE CONFERENCE
  • June 11-13, 2003
  • les Saintes-Maries de la Mer, France
  • Michael Mickey Fitzmaurice, NOAA/NESDIS/OSD

2
Topics
  • HIGHLIGHTS
  • PROGRAM STATUS
  • POES Launch Schedule
  • FUTURE SATELLITE STATUS
  • NOAA N and N
  • MetOp
  • NPOESS Program

2
3
Highlights
  • NOAA-N is scheduled to be launched June 30, 2004.
  • NOAA-N is scheduled to be launched March 2008.
  • 1st MetOp is scheduled for a mid/late 2005
    launch.
  • 2nd MetOp is scheduled for a mid/late 2010
    launch.
  • NPOESS is scheduled to be launched in April 2009.

3
4
POES Launch Scheduleas of May 2003
SATELLITE LIKELY AVAILABLE NEED
PLANNING
ORBIT
LAUNCH NOAA-N
PM JUN 041 JUN 02
JUN 2004 1st METOP AM MAR 05
-------- JUL - DEC
2005 (Metop-2) NOAA-N PM JUN 05
JUN 04 MAR 2008 2nd
METOP AM MAR 04
--------- JAN - JUN 2010 (Metop-1)
(no flight IASI) 1Thruster
leak problem prevented spacecraft from going into
Storage as planned. Repair dependant on
refurbishment of thrusters by Valve-Tech and
return of instruments being repaired in Europe.
5
May 2003 Polar Satellite Status
7
6
Future Polar Satellite Status
  • NOAA-N Status
  • Spacecraft having Reaction Control System
    partially refurbished due to leaking thrusters.
  • First End-to-End test with NOAA SOCC scheduled
    for Fall 2003.
  • DCS instrument had spacecraft fuse blow during
    spacecraft Integration Test (IT).
  • Extensive research effort conducted by
    CNES/Thales/CMAC found intermittent spurious
    oscillation during instrument turn on/warm up
    period.
  • Modified oscillator circuit with suppression
    capacitor
  • Instrument returned to LMSS in Jan 2003 and
    integrated onto spacecraft without incident
  • SARP instrument slated for NOAA N uses same
    oscillator. Instrument was refurbished and
    returned to LMSS in June 2003.

7
7
Future Polar Satellite Status
  • NOAA-N Status (Cont.)
  • Battery production difficulties by Saft (France)
    has delayed delivery of flight batteries
  • Current battery delivery schedule has flight
    batteries delivered to LMSS in Feb 2004.
  • Use of DMSP S-17 batteries may be necessary.
    Retrofit of SARP oscillator planned after S/C
    goes to storage.
  • An extensive investigation into on-orbit
    anomalies with the S-band transmitters may
    require transmitter re-design and cause launch
    delay.

8
8
Future Polar Satellite Status
  • NOAA-N Status
  • Spacecraft is completing Thermal Vacuum testing
    in June 2003.
  • Some issues have arisen with regards to message
    processing at low signal levels.
  • Special testing at end of TV testing with CNES
    support.
  • CNES already at LMSS to support NOAA N SARP/2
    delivery and bench acceptance testing.
  • A-DCS and SARP/3 were tested successfully during
    integration with minor processing errors being
    evaluated.
  • LMSS IT ground system (ATNAGE) required
    extensive modification for A-DCS and SARP/3
    telemetry and command processing.
  • Late delivery did not allow time to flush out
    all errors previously.
  • CNES/Thales evaluation of pre-TV data agreed
    instrument performance was nominal.

9
9
Future Polar Satellite Status
  • NOAA-N Status (cont.)
  • Issue with A-DCS transmitter found (box level
    qualification testing) during instrument start-up
    at temperatures outside specification exists.
  • Some concern that signature could shift over
    time to a temperature within the performance
    specification.
  • CNES requires instrument return to evaluate root
    cause and repair.
  • Spacecraft Electro-Magnetic Interference (EMI)
    testing will be delayed until after the launch of
    NOAA N (June 2004).
  • Current LMSS contract expires in April 2004.
    Extension of contract being negotiated to include
    yearly testing of spacecraft.

9
10
Future Polar Satellite Status
  • MetOp
  • First satellite scheduled for launch in 2005
  • Will fly US-provided instruments and the A-DCS
    SARP/3 provided by CNES.
  • Joint Technical Agreement (JTA) slated to be
    signed in summer 2003 stating that spare US
    instruments will be provided to Eumetsat to fly
    on MetOp3 in 2014.

11
Future Polar Satellite Status
  • NPOESS Status
  • Integrated Program Office (IPO) manages NPOESS
    program.
  • Spacecraft contractor selected (TRW Inc.) in
    August 2002.
  • Interface Control Document (ICD) for A-DCS has
    been defined using modified POES ICD.

10
12
Satellite Transition Schedule(November 2002)
Write a Comment
User Comments (0)
About PowerShow.com