Title: NOAA POES PROGRAM Future Satellite Status
1NOAA POES PROGRAMFuture Satellite Status
- Presented to
- ARGOS OPERATIONS COMMITTEE CONFERENCE
- June 11-13, 2003
- les Saintes-Maries de la Mer, France
-
- Michael Mickey Fitzmaurice, NOAA/NESDIS/OSD
-
-
2Topics
- HIGHLIGHTS
- PROGRAM STATUS
- POES Launch Schedule
- FUTURE SATELLITE STATUS
- NOAA N and N
- MetOp
- NPOESS Program
2
3Highlights
- NOAA-N is scheduled to be launched June 30, 2004.
- NOAA-N is scheduled to be launched March 2008.
- 1st MetOp is scheduled for a mid/late 2005
launch. - 2nd MetOp is scheduled for a mid/late 2010
launch. - NPOESS is scheduled to be launched in April 2009.
3
4POES Launch Scheduleas of May 2003
SATELLITE LIKELY AVAILABLE NEED
PLANNING
ORBIT
LAUNCH NOAA-N
PM JUN 041 JUN 02
JUN 2004 1st METOP AM MAR 05
-------- JUL - DEC
2005 (Metop-2) NOAA-N PM JUN 05
JUN 04 MAR 2008 2nd
METOP AM MAR 04
--------- JAN - JUN 2010 (Metop-1)
(no flight IASI) 1Thruster
leak problem prevented spacecraft from going into
Storage as planned. Repair dependant on
refurbishment of thrusters by Valve-Tech and
return of instruments being repaired in Europe.
5May 2003 Polar Satellite Status
7
6Future Polar Satellite Status
- NOAA-N Status
- Spacecraft having Reaction Control System
partially refurbished due to leaking thrusters. - First End-to-End test with NOAA SOCC scheduled
for Fall 2003. - DCS instrument had spacecraft fuse blow during
spacecraft Integration Test (IT). - Extensive research effort conducted by
CNES/Thales/CMAC found intermittent spurious
oscillation during instrument turn on/warm up
period. - Modified oscillator circuit with suppression
capacitor - Instrument returned to LMSS in Jan 2003 and
integrated onto spacecraft without incident - SARP instrument slated for NOAA N uses same
oscillator. Instrument was refurbished and
returned to LMSS in June 2003.
7
7Future Polar Satellite Status
- NOAA-N Status (Cont.)
- Battery production difficulties by Saft (France)
has delayed delivery of flight batteries - Current battery delivery schedule has flight
batteries delivered to LMSS in Feb 2004. - Use of DMSP S-17 batteries may be necessary.
Retrofit of SARP oscillator planned after S/C
goes to storage. - An extensive investigation into on-orbit
anomalies with the S-band transmitters may
require transmitter re-design and cause launch
delay.
8
8Future Polar Satellite Status
- NOAA-N Status
- Spacecraft is completing Thermal Vacuum testing
in June 2003. - Some issues have arisen with regards to message
processing at low signal levels. - Special testing at end of TV testing with CNES
support. - CNES already at LMSS to support NOAA N SARP/2
delivery and bench acceptance testing. - A-DCS and SARP/3 were tested successfully during
integration with minor processing errors being
evaluated. - LMSS IT ground system (ATNAGE) required
extensive modification for A-DCS and SARP/3
telemetry and command processing. - Late delivery did not allow time to flush out
all errors previously. - CNES/Thales evaluation of pre-TV data agreed
instrument performance was nominal.
9
9Future Polar Satellite Status
- NOAA-N Status (cont.)
- Issue with A-DCS transmitter found (box level
qualification testing) during instrument start-up
at temperatures outside specification exists. - Some concern that signature could shift over
time to a temperature within the performance
specification. - CNES requires instrument return to evaluate root
cause and repair. - Spacecraft Electro-Magnetic Interference (EMI)
testing will be delayed until after the launch of
NOAA N (June 2004). - Current LMSS contract expires in April 2004.
Extension of contract being negotiated to include
yearly testing of spacecraft.
9
10Future Polar Satellite Status
- MetOp
- First satellite scheduled for launch in 2005
- Will fly US-provided instruments and the A-DCS
SARP/3 provided by CNES. - Joint Technical Agreement (JTA) slated to be
signed in summer 2003 stating that spare US
instruments will be provided to Eumetsat to fly
on MetOp3 in 2014.
11Future Polar Satellite Status
- NPOESS Status
- Integrated Program Office (IPO) manages NPOESS
program. - Spacecraft contractor selected (TRW Inc.) in
August 2002. - Interface Control Document (ICD) for A-DCS has
been defined using modified POES ICD.
10
12Satellite Transition Schedule(November 2002)