Risk Assessment and Allocation Management - PowerPoint PPT Presentation

1 / 74
About This Presentation
Title:

Risk Assessment and Allocation Management

Description:

What can be done and what options are available. What are the tradeoffs in terms of all costs, benefits, and ... Owner and contractor spilt remaining 50-50 ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 75
Provided by: robertp84
Category:

less

Transcript and Presenter's Notes

Title: Risk Assessment and Allocation Management


1
Risk Assessment and Allocation Management
2
Risk Assessment
  • What can go wrong?
  • Risk identification
  • What is the likelihood?
  • What are the consequences?

3
Risk Management
  • What can be done and what options are available
  • What are the tradeoffs in terms of all costs,
    benefits, and risks among the available options
  • What are the impacts of current decisions on
    future options.

4
Chapter 1. Introduction
  • Procedures for PSE (plans, specifications, and
    estimates) are standard
  • Across DOTs
  • Treatment of Risks are not standard
  • Or uniform

5
Risk Management
  • Identification
  • Assessment
  • Analysis
  • Mitigation
  • Allocation
  • Monitoring
  • Updating

6
(No Transcript)
7
(No Transcript)
8
Typical Risk Issue
Project Phase
Status
9
Expected Outcomes
Objectives for Risk Assessment
10
Terms
  • Technical Risk
  • Performance
  • Programmatic Risk
  • Cost
  • Schedule
  • Contingency
  • Amount of money or time needed above the estimate
    to reduce the risk of overruns ..to a level
    acceptable to the organization

11
Neat contingency
Neat Estimate
12
Qualifications of RM Team
  • Early
  • Environmental planning, funding, operations
  • Later
  • Scheduling, cost estimating

13
(No Transcript)
14
(No Transcript)
15
But
  • Output needs to be clear (and simple)
  • Easily understood by decision-makers
  • And partners, public, team

16
Chapter 2. Risk Identification
  • Objectives of Risk Identification
  • Identify Risks
  • Categorize Risks
  • Identify minor risks
  • Brainstorming
  • Later will analyze these and determine if minor
  • Simple project, red flag list may be sufficient

17
Cute
  • Knows
  • Know-unknowns
  • Unknown-unknowns
  • Also, Triggers

18
Risks
  • Events that team members determine would
    adversely affect the project
  • Examine
  • Project Description
  • WBS
  • Cost Estimate
  • Schedule
  • Procurement plan
  • Checklists

19
Organize
  • Classify, groups of like risks
  • Right of Way issues
  • Levels
  • Right of Way
  • South Park
  • East Park
  • Businesses
  • Parkland reserve
  • Golf course

20
http//creatingminds.org/tools/crawford.htm
http//creatingminds.org/tools/ngt.htm
http//creatingminds.org/tools/delphi.htm
http//en.wikipedia.org/wiki/Scenario_planning
21
Chapter 3, Risk Assessment
  • (Chapter 3, qualitative 4, quantitative)
  • Qualitatively evaluate risks from Risk
    Identification.
  • Systematic consideration of risk events, their
    likelihood of occurrence, and their consequences.

22
Nature of Effects
  • Direct, Organization
  • Increase cost or schedule
  • Direct, public
  • Affect the public, public perception,
    environmental, health
  • Indirect
  • Increased oversight
  • Planning
  • Reviews

23
Managers v. Annalists
  • Managers tend toward qualitative evaluation
  • Worst case and likelihood
  • Avoid risks
  • Reduce negative impacts
  • Annalists tend toward quantitative
  • Range of results
  • Probabilities
  • Tend to combine

24
From Pennock and Haimes
  • Four barriers to transfer of risk knowledge
  • Horizontal
  • Between subdivisions or specialties, stovepipes
  • Vertical
  • Between layers of management, upper, middle and
    operational
  • External
  • Between organizations
  • Geographic
  • Distance
  • Principles and Guidelines for Project Risk
    Management, M.J. Pennock and Y.Y.Haimes, Systems
    Engineering, Vol.5, No. 2, 2002

25
  • Qualitative best for
  • Screening and prioritizing risks
  • Developing appropriate risk mitigation and
    allocation strategies
  • Quantitative best for
  • Estimating the numerical and statistically nature
    of the risk exposure

26
Risk to whom?
  • Often several project participants share the
    risk.
  • Might maintain the risk or shift it to another
    party via contract
  • But owner needs to understand the risks
  • Consider change order risk

27
Definitions
  • Internal risks
  • Can be referenced to a project documents
  • Cost estimate, schedule
  • External risk
  • Imposed on projects from outside
  • Citizens groups
  • Funding restrictions

28
  • Incremental Risk
  • Small, over the life of project
  • Most internal risks are incremental
  • Costs will occur and be different from the
    estimate
  • Discrete
  • Often External
  • Will occur or not

29
Model Risks and Data Risks
  • Aleatory (Data) Risks
  • Uncertainty associated with the data
  • Future cost of a material
  • Epistemic (Model) Risk
  • Inability to calculate risk
  • Number of passes required to compact
  • Despite knowing soils data.

30
Organize Data and Decide
  • Ordinal Risk Matrix
  • Decision tool

31
Ordinal Risk Matrix
32
Chapter 4 Risk Analysis
  • Take qualitative risks
  • Surely high
  • Probably moderate
  • Do a quantitative analysis
  • Often, cost and schedule

33
Many methods
  • Should include explicit knowledge of team
  • Allow quick response to changing markets and
    conditions
  • Determine project cost and schedule contingency
  • Help foster clear communications among team and
    higher about uncertainties
  • Should be easy to understand

34
(No Transcript)
35
Technical Risk s
  • Reliability
  • FMEA
  • Failure modes and effects analysis
  • Fault tree analysis
  • (Here we will spend most time on cost and
    schedule)

36
Input Parameters
  • Probability distributions
  • Continuous
  • Discrete
  • Point

37
Output
  • Depends on use
  • Simple mean (w or w/o SD)
  • Of many projects in next years budget
  • Distribution
  • Useful for assigning contingency

38
Sensitivity Analysis
  • Test how sensitive result is to change in
    variables

39
Estimate Factors
  • Increase estimate for certain items
  • Low percent for items that do not vary much in
    cost
  • High percent for items that usually vary
  • Problems
  • Not project specific
  • Dont think
  • Does not identify risk drivers
  • Mitigation

40

41
Analytical Methods
  • Last week
  • Beta distribution

42
Monte Carlo
  • With Crystal Ball is easy
  • Needs definite input parameters
  • Better mousetrap

43
Others
  • Decision Trees
  • Useful
  • Model conditional probabilities among project
    variables
  • Examples

44
Schedule
  • CPM
  • Critical path can change
  • Can work in MS Project with Beta
  • Or set up in Excel/Crystal Ball

45
Chapter 5, Risk Mitigation and Planning
  • Follows qualitative and quantitative risk
    analysis
  • Identifies and assigns parties to take
    responsibility
  • For each risk response
  • Ensures each risk requiring a response has an
    owner

46
Risk Response Options
  • Unrecognized, unmanaged, or ignored
  • Recognized but no action
  • Absorbed as a matter of policy
  • Avoided by taking appropriate steps
  • Reduced with alternative approach
  • Transfer via contract or insurance
  • Retained and absorbed by prudent allowances
  • Combination of above

47
Risk Planning
  • Appropriate risk response strategies
  • Iterative through the job
  • Large projects with high degree of uncertainty
    need formal risk management plan.

48
  • Assign responsibilities for specific areas
  • Identify additional technical expertise needed
  • Describe assessment process and areas to consider
  • Delineate procedures for consideration of
    mitigation and allocation options
  • Dictate reporting and documentation needs
  • Establish report requirements and monitoring
    metrics

49
  • But will vary with size, complexity, and
    uncertainty of project.
  • See CalTrans Excel files.

50
Red Flag List
  • See several, Caltrans for example
  • Identify items
  • Focus attention on critical items that can affect
    cost and schedule
  • Need to update

51
Risk Charter
  • Gives managers list of risks and possible cost
    and schedule impacts
  • It is a management tool to identify, communicate,
    monitor, and control risks
  • Helps set contingencies

52
List for each risk
  • Description
  • Status
  • Project phase
  • Functional assignment
  • Risk Trigger
  • Probability
  • Impact ( or time)
  • Response actions
  • Responsibility (task manager)

53
Formal Risk Management Plan
  • Large, complex, uncertain projects
  • Often with management contractor

54
(No Transcript)
55
Chapter 6 Risk Allocation
  • Goals
  • Allocate risks to party best able to manage them
  • Allocate risks in alignment with project goals
  • Share risk when appropriate
  • Allocate risks to promote team alignment with
    customer-orientated performance goals

56
1. Party best able to manage
  • Contractor
  • Labor force, equipment breakdown, construction
    technique
  • Owner
  • Project funding, site availability
  • Differing Site Conditions
  • Owner
  • Inappropriate risk shifting can result in
    misaligned incentive, mistrust, and increased
    disputes.

57
Alignment with Project Objectives
  • Public needs project completed on short schedule
  • Increase LD?
  • Understand objectives early and refer to them at
    all important project decisions.
  • Examples of objectives

58
(No Transcript)
59
Risk Sharing
  • Risk is not really shared
  • It is split among the parties
  • Adverse weather
  • Excusable not compensable delay
  • Delay by owner
  • Cost by contractor

60
Example
  • Claims on drilling of shafts for bridge piers due
    to small boulders. But sufficient equipment
    could handle
  • Owner could
  • Specify equipment
  • Which has its risks too
  • Pass risk to contactor
  • No DSC for small boulders
  • Non-traditional risk sharing should be explained
    to contractors

61
Alignment with Customer-Orientated Performance
Goals
  • Customer goals
  • Satisfaction with product
  • Satisfaction with service
  • Predictability of time
  • Predictability of cost, safety
  • Other goals
  • Mine
  • Agencies'

62
Innovations
  • AB procurement
  • Lane Rental
  • Warranties
  • Examples

63
(No Transcript)
64
Novel Shared Contingency
  • Set 500,000 aside for boulders
  • Contractor can use up at his unit rates
  • Owner and contractor spilt remaining 50-50
  • This is more profitable than the profit in his
    unit rates
  • ??

65
  • Contractor and supply chain are more likely to
    contribute to the effective and efficient
    management of risks if they have fair and
    reasonable incentives
  • Risk of fuel price escalation

66
Chapter 7 Risk Monitoring and Updating
  • Objectives
  • Systematically track the identified risks
  • Identify any new risks
  • Manage the contingency reserve
  • Capture lessons-learned

67
  • Tasks
  • Develop consistent and comprehensive reporting
    procedures
  • Monitor risk and contingency resolution
  • Provide feedback of analysis and mitigation for
    future risk assessment and allocation.

68
Reporting
  • Formal?
  • Tends to ensure more comprehensive assessments
  • Distinguish from Project Control
  • Cost
  • Schedule
  • Production
  • These focus on what has happened relative to plan

69
  • Part of other reports monthly
  • See Fig 22, page 39

70
(No Transcript)
71
(No Transcript)
72
(No Transcript)
73
Contingency Funds
  • Track and Manage
  • Contingency should be matched to underlying risks
  • Which changes over time
  • La La Land?
  • Manager will try to hold on to contingency
  • May not be able to transfer between projects

74
Estimates, Risk, Public Trust
  • Public perception
  • Projects grossly over budget
  • Waste or incompetence?
  • Dishonesty
  • Low-ball estimates?
  • Explain project risks?
  • http//www.tfhrc.gov/pubrds/04jul/03.htm
Write a Comment
User Comments (0)
About PowerShow.com