Title: Risk Assessment and Allocation Management
1Risk Assessment and Allocation Management
2Risk Assessment
- What can go wrong?
- Risk identification
- What is the likelihood?
- What are the consequences?
3Risk Management
- What can be done and what options are available
- What are the tradeoffs in terms of all costs,
benefits, and risks among the available options - What are the impacts of current decisions on
future options.
4Chapter 1. Introduction
- Procedures for PSE (plans, specifications, and
estimates) are standard - Across DOTs
- Treatment of Risks are not standard
- Or uniform
5Risk Management
- Identification
- Assessment
- Analysis
- Mitigation
- Allocation
- Monitoring
- Updating
6(No Transcript)
7(No Transcript)
8Typical Risk Issue
Project Phase
Status
9Expected Outcomes
Objectives for Risk Assessment
10Terms
- Technical Risk
- Performance
- Programmatic Risk
- Cost
- Schedule
- Contingency
- Amount of money or time needed above the estimate
to reduce the risk of overruns ..to a level
acceptable to the organization
11Neat contingency
Neat Estimate
12Qualifications of RM Team
- Early
- Environmental planning, funding, operations
- Later
- Scheduling, cost estimating
13(No Transcript)
14(No Transcript)
15But
- Output needs to be clear (and simple)
- Easily understood by decision-makers
- And partners, public, team
16Chapter 2. Risk Identification
- Objectives of Risk Identification
- Identify Risks
- Categorize Risks
- Identify minor risks
- Brainstorming
- Later will analyze these and determine if minor
- Simple project, red flag list may be sufficient
17Cute
- Knows
- Know-unknowns
- Unknown-unknowns
- Also, Triggers
18Risks
- Events that team members determine would
adversely affect the project - Examine
- Project Description
- WBS
- Cost Estimate
- Schedule
- Procurement plan
- Checklists
19Organize
- Classify, groups of like risks
- Right of Way issues
- Levels
- Right of Way
- South Park
- East Park
- Businesses
- Parkland reserve
- Golf course
20http//creatingminds.org/tools/crawford.htm
http//creatingminds.org/tools/ngt.htm
http//creatingminds.org/tools/delphi.htm
http//en.wikipedia.org/wiki/Scenario_planning
21Chapter 3, Risk Assessment
- (Chapter 3, qualitative 4, quantitative)
- Qualitatively evaluate risks from Risk
Identification. - Systematic consideration of risk events, their
likelihood of occurrence, and their consequences.
22Nature of Effects
- Direct, Organization
- Increase cost or schedule
- Direct, public
- Affect the public, public perception,
environmental, health - Indirect
- Increased oversight
- Planning
- Reviews
23Managers v. Annalists
- Managers tend toward qualitative evaluation
- Worst case and likelihood
- Avoid risks
- Reduce negative impacts
- Annalists tend toward quantitative
- Range of results
- Probabilities
- Tend to combine
24From Pennock and Haimes
- Four barriers to transfer of risk knowledge
- Horizontal
- Between subdivisions or specialties, stovepipes
- Vertical
- Between layers of management, upper, middle and
operational - External
- Between organizations
- Geographic
- Distance
- Principles and Guidelines for Project Risk
Management, M.J. Pennock and Y.Y.Haimes, Systems
Engineering, Vol.5, No. 2, 2002
25- Qualitative best for
- Screening and prioritizing risks
- Developing appropriate risk mitigation and
allocation strategies - Quantitative best for
- Estimating the numerical and statistically nature
of the risk exposure
26Risk to whom?
- Often several project participants share the
risk. - Might maintain the risk or shift it to another
party via contract - But owner needs to understand the risks
- Consider change order risk
27Definitions
- Internal risks
- Can be referenced to a project documents
- Cost estimate, schedule
- External risk
- Imposed on projects from outside
- Citizens groups
- Funding restrictions
28- Incremental Risk
- Small, over the life of project
- Most internal risks are incremental
- Costs will occur and be different from the
estimate - Discrete
- Often External
- Will occur or not
29Model Risks and Data Risks
- Aleatory (Data) Risks
- Uncertainty associated with the data
- Future cost of a material
- Epistemic (Model) Risk
- Inability to calculate risk
- Number of passes required to compact
- Despite knowing soils data.
30Organize Data and Decide
- Ordinal Risk Matrix
- Decision tool
31Ordinal Risk Matrix
32Chapter 4 Risk Analysis
- Take qualitative risks
- Surely high
- Probably moderate
- Do a quantitative analysis
- Often, cost and schedule
33Many methods
- Should include explicit knowledge of team
- Allow quick response to changing markets and
conditions - Determine project cost and schedule contingency
- Help foster clear communications among team and
higher about uncertainties - Should be easy to understand
34(No Transcript)
35Technical Risk s
- Reliability
- FMEA
- Failure modes and effects analysis
- Fault tree analysis
- (Here we will spend most time on cost and
schedule)
36Input Parameters
- Probability distributions
- Continuous
- Discrete
- Point
37Output
- Depends on use
- Simple mean (w or w/o SD)
- Of many projects in next years budget
- Distribution
- Useful for assigning contingency
-
38Sensitivity Analysis
- Test how sensitive result is to change in
variables
39Estimate Factors
- Increase estimate for certain items
- Low percent for items that do not vary much in
cost - High percent for items that usually vary
- Problems
- Not project specific
- Dont think
- Does not identify risk drivers
- Mitigation
40 41Analytical Methods
- Last week
- Beta distribution
42Monte Carlo
- With Crystal Ball is easy
- Needs definite input parameters
- Better mousetrap
43Others
- Decision Trees
- Useful
- Model conditional probabilities among project
variables - Examples
44Schedule
- CPM
- Critical path can change
- Can work in MS Project with Beta
- Or set up in Excel/Crystal Ball
45Chapter 5, Risk Mitigation and Planning
- Follows qualitative and quantitative risk
analysis - Identifies and assigns parties to take
responsibility - For each risk response
- Ensures each risk requiring a response has an
owner
46Risk Response Options
- Unrecognized, unmanaged, or ignored
- Recognized but no action
- Absorbed as a matter of policy
- Avoided by taking appropriate steps
- Reduced with alternative approach
- Transfer via contract or insurance
- Retained and absorbed by prudent allowances
- Combination of above
47Risk Planning
- Appropriate risk response strategies
- Iterative through the job
- Large projects with high degree of uncertainty
need formal risk management plan.
48- Assign responsibilities for specific areas
- Identify additional technical expertise needed
- Describe assessment process and areas to consider
- Delineate procedures for consideration of
mitigation and allocation options - Dictate reporting and documentation needs
- Establish report requirements and monitoring
metrics
49- But will vary with size, complexity, and
uncertainty of project. - See CalTrans Excel files.
50Red Flag List
- See several, Caltrans for example
- Identify items
- Focus attention on critical items that can affect
cost and schedule - Need to update
51Risk Charter
- Gives managers list of risks and possible cost
and schedule impacts - It is a management tool to identify, communicate,
monitor, and control risks - Helps set contingencies
52List for each risk
- Description
- Status
- Project phase
- Functional assignment
- Risk Trigger
- Probability
- Impact ( or time)
- Response actions
- Responsibility (task manager)
53Formal Risk Management Plan
- Large, complex, uncertain projects
- Often with management contractor
54(No Transcript)
55Chapter 6 Risk Allocation
- Goals
- Allocate risks to party best able to manage them
- Allocate risks in alignment with project goals
- Share risk when appropriate
- Allocate risks to promote team alignment with
customer-orientated performance goals
561. Party best able to manage
- Contractor
- Labor force, equipment breakdown, construction
technique - Owner
- Project funding, site availability
- Differing Site Conditions
- Owner
- Inappropriate risk shifting can result in
misaligned incentive, mistrust, and increased
disputes.
57Alignment with Project Objectives
- Public needs project completed on short schedule
- Increase LD?
- Understand objectives early and refer to them at
all important project decisions. - Examples of objectives
58(No Transcript)
59Risk Sharing
- Risk is not really shared
- It is split among the parties
- Adverse weather
- Excusable not compensable delay
- Delay by owner
- Cost by contractor
60Example
- Claims on drilling of shafts for bridge piers due
to small boulders. But sufficient equipment
could handle - Owner could
- Specify equipment
- Which has its risks too
- Pass risk to contactor
- No DSC for small boulders
- Non-traditional risk sharing should be explained
to contractors
61Alignment with Customer-Orientated Performance
Goals
- Customer goals
- Satisfaction with product
- Satisfaction with service
- Predictability of time
- Predictability of cost, safety
- Other goals
- Mine
- Agencies'
62Innovations
- AB procurement
- Lane Rental
- Warranties
- Examples
63(No Transcript)
64Novel Shared Contingency
- Set 500,000 aside for boulders
- Contractor can use up at his unit rates
- Owner and contractor spilt remaining 50-50
- This is more profitable than the profit in his
unit rates - ??
65- Contractor and supply chain are more likely to
contribute to the effective and efficient
management of risks if they have fair and
reasonable incentives - Risk of fuel price escalation
66Chapter 7 Risk Monitoring and Updating
- Objectives
- Systematically track the identified risks
- Identify any new risks
- Manage the contingency reserve
- Capture lessons-learned
67- Tasks
- Develop consistent and comprehensive reporting
procedures - Monitor risk and contingency resolution
- Provide feedback of analysis and mitigation for
future risk assessment and allocation.
68Reporting
- Formal?
- Tends to ensure more comprehensive assessments
- Distinguish from Project Control
- Cost
- Schedule
- Production
- These focus on what has happened relative to plan
69- Part of other reports monthly
- See Fig 22, page 39
70(No Transcript)
71(No Transcript)
72(No Transcript)
73Contingency Funds
- Track and Manage
- Contingency should be matched to underlying risks
- Which changes over time
- La La Land?
- Manager will try to hold on to contingency
- May not be able to transfer between projects
74Estimates, Risk, Public Trust
- Public perception
- Projects grossly over budget
- Waste or incompetence?
- Dishonesty
- Low-ball estimates?
- Explain project risks?
- http//www.tfhrc.gov/pubrds/04jul/03.htm