Title: SQTF Stave Loading Status


1
SQTF - Stave Loading Status
  • G. Darbo - INFN / Genova

2
Loaded Staves
  • Inserted Staves - Completed the production for L2
    half shell (26), a few more can be available if
    needed after some repair.
  • New Pipe Staves (production before August)
  • 71 Loaded, all qualified but two (WU_20/S1114009
    and WU_26/S4136)
  • Loading after few weeks of stop resumed last
    week
  • CPPM 2 loaded as L1 and in test
  • Genova not resumed yet (Visa problem), will
    probably restart next week
  • Wuppertal 1 stave loaded (?) under qualification
  • We still need at least 15 staves to add to the 71
    ready (total 86).
  • There are 27 L1 quality and 18 BL quality (module
    quality before loading). We need 38 and 22.
  • Some of BL will go to L1, but would be better to
    have the complete production finished before L1
    integration to select the best staves for BL!

3
Bare Staves
  • Repaired Staves
  • Last set of repaired staves sent to the 3 Sites
    (5 CPPM, 3 Genova, 4 Wuppertal).
  • Torsion of two staves higher for normal
    acceptance for L1.
  • 4 BL quality and 1 almost BL.
  • New Pipe staves
  • 12 Staves back from Comelec the 17/8 and now in
    Genova for Joule Test and Survey.
  • Distribution to Sites will be discussed at next
    SQTF on Thursday
  • Shipment will happen as soon as decided the
    distribution (CPPM may need to get faster to
    avoid stopping)

4
Modules
  • Genova ad CPPM have a Loading throughput of 2
    staves/week, Wuppertal 1 stave/week.
  • If we want to conclude the loading and
    qualification by end of September we should
    redistribute some modules from sites
  • One possibility would be to ship 25 modules from
    Wuppertal to CPPM.
  • The number of modules that we still have is
    enough for 4 staves more than needed, but we
    want to keep a few modules spares for repair.
    This could be of the order of 1 stave in number
    of modules.