http://www.ge.infn.it/ATLAS/SQTF/StaveProduction/SummaryAll.xls. Ranked ... 2 downgraded to System Test. SQTF @ RPDSG. C. Darbo INFN / Genova. RPDSG, 21/03/2006 ...
SQTF: Stave Still to Load. G. Darbo- INFN / Genova. SQTF, 22/06/2006. o. Staves ... EB (22/6) for leak test, sand blasting and measuring Cleaning at CERN (3/7) ...
Genova Site - Report at SQTF. G. Darbo ... Status of Loaded Staves in Genova. Stave 4004 - 18/08/2004 ... The encoder parts will be in genova by mid February. ...
We are able to load 1 per week and we keep 1 week more for safety and Easter slow down. Survey takes 1/2 day. LOAD test Thermal cycles STAVE test takes 1 week. ...
... August 2005, after ~43 staves, when aluminium pipe corrosion appeared in all its ... In August we had a first workshop to understand the corrosion problem and to ...
Loading after few weeks of stop resumed last week: CPPM: 2 loaded as L1 and in test; Genova: not resumed yet (Visa problem), will probably restart next week; ...