Chapter 10 Project Management - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Chapter 10 Project Management

Description:

A hierarchical breakdown of the tasks and deliverables that need to ... Predecessors. Resources. People. Duration (Days) Deliverables / Checkpoints. Description ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 13
Provided by: odessalgoe
Category:

less

Transcript and Presenter's Notes

Title: Chapter 10 Project Management


1
Chapter 10Project Management
  • If you fail to plan, then you plan to fail.
  • --Anonymous

2
Work Breakdown Schedule
  • A hierarchical breakdown of the tasks and
    deliverables that need to be completed in order
    to accomplish the project objectives
  • Typically created as the first step in project
    planning

3
Work Breakdown Schedule
  • An ordered set of activities required to complete
    the project
  • Activity a combination of a task and its
    associated deliverables
  • Task actions that accomplish a job
  • Deliverables entities that are delivered to the
    project based upon completion of tasks

4
Work Breakdown Schedule
5
Network Diagrams
  • A directed graph representation of the activities
    and dependencies between them for a project.

6
Network Diagram
  • The duration of each path is determined by
    summing the duration of all activities on that
    path
  • Critical path the path with the longest
    duration, i.e. the minimum time required to
    complete the project
  • Slippage falling behind schedule
  • Float the amount of time an activity can slip
    without extending the overall completion time of
    the project

7
Gantt Charts
  • A bar graph representation of activities on a
    timeline.
  • Effectively shows the WBS and the timeline for
    completion.

8
Gantt Charts
9
Break-Even Analysis
  • Aims to determine the number of units that must
    be sold for costs and revenues to be equal
  • Fixed costs constant, regardless of number of
    units produced and cannot be directly charged to
    a process or activity
  • Variable costs vary depending upon the process
    or items being produced, and fluctuate directly
    with the number of units being produced.

10
Project Manager
  • Responsible for planning and organizing the
    project in addition to completing project
    deliverables
  • Not necessarily a Boss, more like a member of
    the team

11
Guidance
  • Build the plan after the design architecture is
    complete
  • Take the initial time estimates for activities
    and double them
  • Assign a lot of time for testing and integration
  • Factor in lead times for part ordering

12
Guidance
  • Assign a project manager
  • Do not assign all team members to all tasks
  • Track the progress versus the plan
  • Dont become a slave to the plan
  • Experience counts
Write a Comment
User Comments (0)
About PowerShow.com