Title: Update on a Proposed Bakeout
1Update on a Proposed Bakeout CXC SOT
FOT, ACIS Instrument Team and MSFC Project
Science
2New Items since Last CUC Briefing (January 2005)
- MIT/ACIS team conducted irradiation tests of
flight spare CCDs at GSFC in May 2005. MIT/ACIS
concluded that the CTI increase from another 30
C Bakeout would most likely be smaller than
previously believed, 5. - MSFC Project Science continued to explore the
sensitivity of the simulation results to the
parameters (ie temperatures of the relevant
surfaces, volatility of the contaminant) - The ACIS contamination working group reviewed
the new results in the summer and decided on July
15, 2005 against recommending a Bakeout. The
team felt that the uncertainties were too large
to be able to predict the outcome of the Bakeout
with any confidence. - The Bakeout is therefore postponed indefinitely.
3Docosane, nominal TOBF Mass column
ODell Swartz (MSFC)
e 0.30
1 ACIS OBF 2 Camera top 3 ACIS snoot 4 ACIS
collimator 5 SIM trans table 6 SIM focus
struc 7 OBA stove pipe 8 Optical bench 9 OBA
vent
4Docosane, de-rated TOBF Mass column
ODell Swartz (MSFC)
e 0.30
1 ACIS OBF 2 Camera top 3 ACIS snoot 4 ACIS
collimator 5 SIM trans table 6 SIM focus
struc 7 OBA stove pipe 8 Optical bench 9 OBA
vent
5Limits on Vaporization Rates
ODell Swartz (MSFC)
Min to vent 0.2 g in 1 orb5?10-3 mg cm-2 s-1 _at_
Tcoldest
Min to clean OBF in 1 orb2?10-3 mg cm-2 s-1 _at_
TOBF-bake
Upper limit at OBF center1?10-7 mg cm-2 s-1 _at_
TOBF-ops
6Monitoring the ContaminantTransmission _at_ 700eV
Grant (MIT)
7Monitoring the Contaminant C-K Optical Depth
Marshall (MIT)
8Summary of Bakeout Effort
- There will not be a Bakeout anytime soon
- We will continue to monitor the contaminant
buildup and improve the characterization of the
absorption of the contaminant - MIT/ACIS will analyze CTI measurements at
temperatures between -90 C and -120 C to
understand the temperature dependence of the CTI
better - Calibration files for the time-dependent and
spatial-dependent absorption of the contaminant
are available in the CALDB CIAO, we will
continue to assess the accuracy of these
corrections and update as necessary
9Bonus Material ACIS FP Temperature Anomaly
- ACIS DEA-A autonomously shutdown on 15 Sep 2005
- Two unintended consequences of the recovery from
this anomaly
- FP temperature setpoint for -120 C was not
loaded into the DEA-A - The A/D converter which reports the DEA
Housekeeping data initialized into a low
resolution mode
- The consequences of this were
- 16 Sep 2005 - 05 Oct 2005 - the FP temperature
was not regulating and was 1.3 degrees colder
than reported in TLM - 06 Oct 2005 - 15 Oct 2005 - the FP temperature
WAS regulating but the reported temperature was
1.3 degrees warmer than the actual temperature
(-118.4 C instead of -119.7 C)
- The FP temperature regulation is back to nominal
as of 15 Oct 2005
10FP Temperature Anomaly
DePasquale (SAO)