An introduction to DIAMOND Personnel Safety System - PowerPoint PPT Presentation

About This Presentation
Title:

An introduction to DIAMOND Personnel Safety System

Description:

Annunciator indicating vault status. Blue lights in vault when access is not allowed. Signs in vault indicating danger. 10/12/09. Martin Wilson. DIAMOND LIGHT ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 23
Provided by: martin556
Learn more at: https://epics.anl.gov
Category:

less

Transcript and Presenter's Notes

Title: An introduction to DIAMOND Personnel Safety System


1
An introduction to DIAMOND Personnel Safety System
  • By Martin Wilson
  • Principle Personnel Safety Engineer

2
Contents
  • The Requirements
  • Hazard Management
  • Access Zones
  • Personnel Safety Hardware
  • Test strategy
  • EPICS

3
The Requirements
  • Why do we need PSS?
  • 1. We cant separate the hazard from the product
  • 2. Required by LAW
  • Legal Requirement under Health and Safety at
    Work act 1974 / IRR99
  • Senior management are liable to prosecution and
    punishment
  • Persons ignoring or interfering with processes or
    equipment may also be liable to prosecution

4
The Requirements
  • Personnel Safety, the Legal and Site Requirements
  • Designation of controlled and supervised areas
  • Prior examination of plans
  • Risk assessments and hazard management
  • Conduct of investigations
  • Regular calibration of equipment
  • Periodic examination and testing

5
Hazard Management
  1. Identify and Log Hazards
  2. Assess and control Risk
  3. Operate
  4. Monitor and Log events
  5. Review
  6. Decommission

6
Hazard Management
  • Risk Matrix
  • Reduce severity
  • Reduce likelihood

7
Hazard Management
  • Mitigation for a Radiation Hazard
  • Shielded enclosure with access via locked
    labyrinths
  • 2.   Captive Permit key allowing access or beam
    operation
  • 3.   A personnel safety system with the following
    features
  • Micro-switches on doors as interlocks
  • Search required prior to operation
  • Audible Warnings
  • Annunciator indicating vault status
  • Blue lights in vault when access is not allowed
  • Signs in vault indicating danger

8
Access Zones
9
Daresbury
  • Hardware

ESRF
DIAMOND
10
Hardware
  • PLC verses Hardware
  • Simple failure modes
  • Established system based on DL SRS system
  • User confidence in system
  • Easier to maintain over a 30 year life
  • Many of the advantages of a PLC are not
    requirements of high integrity system
  • Configurability
  • Upgradeability
  • Ease of change

11
Hardware
  • Dual guard rail interlock system
  • Based on Relays
  • Redundant
  • Diverse
  • Interfaced to VME/EPICS via a G64 adaptor
  • PPC VME processor to readout module status

12
Hardware Dual Guard Rail System
13
Hardware SRS Safety Module
14
Hardware SRS Backplane
15
Hardware VME to G64 adaptor (prototype)
16
Test strategy
Markov model of dual guard rail System
17
Test Strategy
  • Modules Test
  • Crate test
  • System test
  • On line test

18
EPICS
  • 1. Each PSS rack is an IOC
  • 2. Develop device driver for VME/G64 and PSS
    modules This gives access to the PSS status and
    allows the modules to be RESET

19
EPICS
  • 3. VxWorks applications to check guard line
    operations and test routines - detect faults as
    they develop and help to prevent double faults
  • 4. Scripts to sequence resets as part of the
    search
  • 5. EDM extension to show logic process
    graphically and to allow resets

20
(No Transcript)
21
EPICS Typical Reset Window
22
Additional safety measures
  • Local Rules
  • Formal Analysis (Fault Tree analysis)
  • Change control
  • Safety committee
Write a Comment