Title: Understanding Killer Contract Language
1Understanding Killer Contract Language
2This PowerPoint presentation is intended to
provide contractors and subcontractors with
practical information regarding problem areas of
contract language and interpretation. It is not
intended to provide legal advice. Individuals
and companies seeking legal advice are advised to
consult legal counsel
3The Dreaded Contract
Unfortunately, none of the parties typically
discuss the nature of the contract and its
provisions until after they have agreed upon the
scope of work and the price.
4Your Call!
- Sometimes bad contract language must be
considered risk should not include the future of
your company
5Buddys Top 7 Deal Breakers
61. Contingency payment clauses
- Pay If Paid Pay When Paid
7Pay If Paid
Red Flag
- Under a "pay-if-paid" provision, the
subcontractor will be paid only if the GC is
first paid by the owner for the specific
subcontractors work. - A pay-if-paid provision creates a condition
precedent to the GCs duty to pay its
subcontractor and the risk of an owners
non-payment is shared by the contractor and the
subcontractor.
8Pay If Paid
Red Flag
Typical Contract Language
- Contractors obligation to pay Sub any sum due
under the contract is subject to the condition
precedent that Contractor has first received from
Owner payment for Subs work. Contractor shall
have no obligation to pay Sub for any particular
work unless and until Owner first pays Contractor
for such work. Sub expressly assumes the risk of
nonpayment by the Owner to Contractor for any
reason.
9Pay If Paid Examples
Red Flag
- Examples of these clauses might read
- "Notwithstanding any provision to the contrary,
payment by Owner to Contractor is a condition
precedent to payment to Subcontractor" - "Receipt of payment from the Owner is a condition
precedent to payment to Subcontractor and payment
to Subcontractor will only be made after the
Contractor is paid by Owner."
10Pay When Paid
- With a pay-when-paid clause, so long as the cause
for non-payment to the general contractor from
the owner is not related to the subcontractors
work, the general contractor should be liable to
the subcontractor immediately following the
expiration of a reasonable time period. - If the general contractor does not receive
payment from the owner, and it is through no
fault of the subcontractor, the general
contractor is still going to be ultimately liable
to the subcontractor.
11Pay When Paid
- These types of clauses deal only with the timing
of payment and are construed merely as timing
mechanisms, rather than as waiver/forfeiture
clauses. - They are referred to as pay-when-paid clauses,
but they do not operate to preclude payment
indefinitely. In other words, the clauses merely
provide a GC with some reasonable period within
which to make payment. - The AIA 401 and the AGC 650 subcontract forms
contain pay-when-paid payment terms.
12Lien Rights
- Subcontractors should always retain their lien
rights in their contracts with general
contractors. This is especially important when
the parties contract contains the pay-if-paid
language.
132. Waiver of Lien or Bond Rights
14Waiver of Lien and Bond Rights
- Subcontractors should vigorously resist giving up
the payment security provided by lien and Bond
Rights. - Most states have lien laws that require a Notice
to Owner when a lien is filed most states have
specific lien notice and filing timelines know
state lien laws. - However, some courts have upheld such "no lien"
provisions against contractors that sign them.
15Pass Down
- If a contractor agrees to a no lien provision,
the contractor must put the same language in any
contracts he enters into with lower tiered
contractors or material suppliers.
16Partial Lien Waiver
- Upon making progress payments, the owner or
general contractor may require the contractor to
waive all lien claims that the contractor may
have for the work invoiced. - Such partial lien waiver requirement must be
contained in the contract. - Only waive liens through the date of the invoice,
not through the date of the payment.
17Final Lien Waiver
- Upon completing the job, the GC asks the Sub
complete a final lien waiver. - The requirement to sign a final waiver of claims
in order to obtain final payment is against
public policy in most states if the contractor
has asserted a claim or request for an adjustment
to the contract price. - Subs should not be caught between waiving a
previously asserted claim, and getting paid for
its work.
18Protecting Lien Rights
- Look for no lien clauses in your contract, and in
the contract with the owner, if that contract is
incorporated by reference. - Such incorporation language is usually enforced.
- If a no lien clause is in the contract, try to
negotiate it out of your contract
193. Waiver of Subrogation Rights
20Typical Waiver Language
- Contractor shall and does hereby waive any
rights of subrogation that it or any of its
insurers may have against the owner, its agents,
employees or its insurers. - "The owner and Contractor waive all rights
against (1) each other and any of the
subcontractors, sub-subcontractors, agent and
employees, each of the other, and (2) the
architect, architect's consultants, . . . for
damage caused by fire or other perils to the
extent covered by property insurance obtained
pursuant to this contract.
21Limitations of Waiver of Subrogation Clauses
- 1. Typically, they apply "only to the extent
covered by property insurance" obtained pursuant
to the contract. Thus, if there is not coverage
under the property insurance for any reason
(exclusions, etc.), the waiver of subrogation
clause does not apply, and the owner is free to
pursue claims against anyone who allegedly caused
or contributed to cause the event. - 2. If the amount of the loss exceeds the amount
of the property insurance limits of coverage,
then the owner is free to pursue claims for all
losses which exceed the amount of property
insurance.
22Waiver of Subrogation
- The "waiver of subrogation" means that by giving
up its right of recovery, the insurer accepts the
fact that the policyholder and the parties with
whom it has contracted have allocated the risk of
the insured event to the insurer - the insurance
would be the sole remedy and that all risk would
be on the insurer.
23Insurance Policies
- If the owner has given up (i.e., waived) the
right to pursue certain claims in the contracts,
the legal effect is that the property insurer is
bound by that waiver. - Many insurance policies state that the insured
may waive subrogation provided it is done as part
of the contract between the insured and its
client and is done at the outset of the job and
not after a claim or loss has arisen.
24Deal Breakers
- Since builders risk policies are written on a
great variety of forms, it is especially critical
for an insured to determine whether the policy
prohibits the insured from waiving recovery
rights against another. - If the policy does prohibit such waivers and the
contractor enters into a typical construction
contract containing a mutual waiver of
subrogation provision, the contractor may have
violated policy conditions and voided the
coverage. This is particularly true in the case
of waivers of recovery against architects and
engineers. - In the case of design professionals, builders
risk insurers are hesitant to allow waivers of
recovery since design errors often cause other
covered losses under the policy.
25Ask Insurer
- Waivers of subrogation should be entered into by
an owner or a contractor only after permission is
obtained from the builders risk insurer. - It is obviously prudent to seek a clarifying
endorsement from the insurer. This, of course, if
especially important where the policy form
strictly prohibits all waiver of recovery against
third parties, whether pre- or post- loss.
26Good Waiver Language
- Waivers of subrogation to prevent the builders
risk insurer from bringing suit against the
contractor and the subcontractor good. - Another method to avoid that result would be to
add the contractor and all of its subcontractors
as named insureds to the policy since insurers
are generally not allowed to pursue subrogation
against their own insureds OCIPs/CCIPs.
27Deal Breaker Language
- Sub gives up right for its insurer to subrogate
but owner and GC can subrogate. - Another frequently disputed issue regarding
waivers of subrogation is the length of time over
which the waiver extends. Typically, as is the
case with the AIA documents, the waiver is
intended to be coextensive with the length of
time during which the builders risk policy is in
place, that is, usually the completion of the
project.
284. Incorporation by Reference
29Incorporation By Reference
- Be alert to prime contract provisions that
contain incorporation by reference clauses. - Particularly inequitable are provisions that
incorporate only the contractors
responsibilities, but not your rights against the
owner.
30Example of Concern
- An owner and contractor used an AIA contract for
a project. The contract incorporated by reference
AIA general conditions requiring the parties to
submit disputes to the project architect for
decision. The contract provided that the
architect's decision was "final and binding on
the parties subject to arbitration." Under the
contract, either party could demand arbitration
of the dispute by filing "notice of demand for
arbitration with the other party to the
Agreement, with the American Arbitration
Association and with the architect." The contract
also provided that failure to demand arbitration
within 30 days would result in "the architect's
decision becoming final and binding."
315. Change Orders in Writing.
32Change Orders
- There is no such thing as a contract that gets
completed without change orders. Just contractors
who end up taking it on the chin because of no
change order procedures in their contracts.
33Change Orders
- Make certain that the key basic elements for
change orders is addressed in the contract - Who you have to notify and receive permission
from for change order work? - When and how do you have to notify them of
potential change order work? - What documents do you have to provide?
- How and when will the change order work get paid?
- Where will the additional funds come from for the
change order work? - What is the reasonable time for approval and what
is the additional cost for your delays while
youre waiting for approval? - How will you and the owner resolve the change
order issue if immediate approval for the work is
not received in the agreed time?
34Change Orders
- Remember, change order work is not extra work.
It disrupts the progress and productivity of the
work as you had originally planned for when you
bid the work. It is neither your fault nor your
responsibility, and you should be justly
compensated for this unanticipated disruption.
35Payment for Change Orders
- The owner has an obligation to build a building
in compliance with adopted codes and standards.
Subs should not pay for the owners obligation. - If it is a code required item the owner should
pay. - The only potentially open issue if it is our
design error is the difference between the cost
to make the change verses the cost if the
original plans addressed the item needing change.
36Design Errors
- There exists a propensity for design team members
to reject change orders to fix errors they have
made. - Be cautious of language in design concept
documents that shift or attempt to shift design
responsibility to contractors. - Successful bidder is responsible to ensure the
system is installed to code.
376. Broad form Indemnification.
38Indemnity Clauses
- Three Different Forms of Indemnity Clauses
- 1. Broad
- 2. Intermediate
- 3. Limited
39Indemnity Clauses
- Broad Sub shall indemnify and hold harmless GC
and Owner from and against any and all claims,
losses, damages, costs and expenses relating to
the performance of the subcontract and involving
personal injury, sickness, disease, death or
property damages, including any resulting loss of
use, REGARDLESS OF WHETHER CAUSED IN WHOLE OR IN
PART BY THE NEGLIGENCE OF GC OR OWNER. SUB
ACKNOWLEDGES AND AGREES THAT IT IS INDEMNIFYING
GC AND OWNER FOR THEIR OWN SOLE AND/OR PARTIAL
NEGLIGENCE.
40Indemnity Clauses
- Intermediate Sub shall indemnify and hold
harmless GC and Owner from and against any and
all claims, losses, damages, and expenses
relating to the performance of the subcontract
and involving personal injury, sickness, disease,
death or property damages, including any loss of
use, REGARDLESS OF WHETHER CAUSED IN PART BY THE
NEGLIGENCE OF THE GC OR OWNER. Subs indemnity
obligation shall not extend to any claims,
losses, damages, or expenses for which the sole
cause is the negligence of GC or Owner.
41Indemnity Clauses
- Limited Sub shall indemnify and hold harmless GC
and Owner from and against any and all claims,
losses, damages, costs and expenses relating to
the performance of the Subcontract and involving
personal injury, sickness, disease, death or
property damages, including any resulting loss of
use, but only to the extent caused by the
negligent acts or omissions of Sub, its
employees, or other persons or entities for whose
acts Sub may be liable.
42Indemnification
- Insurers refusing to cover indemnification
clauses particularly indemnification of sole
negligence. - Refusing to sign indemnification because of no
insurance is good argument. - READ CONTRACTS hold harmless requirements can
be worded many different ways. - Laws to protect us.
43Indemnity Clauses
- 1. Express Negligence Test.
- 2. Conspicuousness Requirement.
44Express Negligence Test
- In Ethyl Corp. v. Daniel Construction, the Texas
Supreme Court adopted the Express Negligence Test
for indemnitee agreements. - . . . parties seeking to indemnify the
indemnitee from the consequences of its own
negligence must express that intent in specific
terms.
45Express Negligence Test
- Furthermore, the court added, Under the doctrine
of express negligence, the intent of the parties
must be specifically stated within the four
corners of the contract.
46Conspicuousness Requirement
- The Conspicuousness Test states that a clause is
conspicuous when a reasonable person against whom
the clause is to operate ought to have noticed
it. - Language in CAPITAL HEADINGS, language in
contrasting type or color, and language in an
extremely short document, such as a telegram, is
conspicuous.
47Indemnity Clause Satisfying theConspicuousness
Test
- Broad Sub shall indemnify and hold harmless GC
and Owner from and against any and all claims,
losses, damages, costs and expenses relating to
the performance of the subcontract and involving
personal injury, sickness, disease, death or
property damages, including any resulting loss of
use, REGARDLESS OF WHETHER CAUSED IN WHOLE OR IN
PART BY THE NEGLIGENCE OF GC OR OWNER. SUB
ACKNOWLEDGES AND AGREES THAT IT IS INDEMNIFYING
GC AND OWNER FOR THEIR OWN SOLE AND/OR PARTIAL
NEGLIGENCE.
487. Additional Insured Endorsements.
49Additional InsuredEndorsements
- Sub shall, at no expense to GC, maintain in full
force at all times Commercial General Liability
Insurance. This insurance shall be written for
not less than (limits specified) or required by
law. The following AIE shall be furnished to GC
prior to the commencement of the work. In
consideration of the premium charged, GC is named
as additional insured with respect to all
liabilities arising out of the performance of the
work.
50Additional InsuredEndorsements
- Sub shall, at no expense to GC, maintain in full
force at all times Commercial General Liability
Insurance. This insurance shall be written for
not less than (limits specified) or required by
law, and this insurance shall be primary to any
other insurance of the GC. The following AIE
shall be furnished to GC prior to the
commencement of the work. In consideration of the
premium charged, GC is named as additional
insured with respect to all liabilities arising
out of the performance of the work.
51Additional InsuredEndorsements
- . . . . insurance shall be written for not less
than (limits specified), and this insurance shall
be primary to any other insurance of the GC. In
consideration of the premium charged, GC is named
an additional insured with respect to all
liabilities arising out of the performance of the
work. Sub shall waive all rights against GC, its
agents, and employees for all damages covered by
insurance pursuant to this contract.
52Flow Through Provisions
- BROAD Sub is bound to Contractor by all terms of
the Prime Contract and assumes toward Contractor
all of the obligations and responsibilities that
Contractor by those instruments assumes toward
Owner.
53Flow Through Provisions
- The Subcontract consists of this Agreement and
any Exhibits attached hereto, and, to the extent
applicable to the Subs work, the Prime Contract
consisting of the Agreement between Owner and
Contractor . . . . Sub is bound to Contractor by
all terms of the Prime Contract and assumes
toward Contractor all of the obligations and
responsibilities pertaining to the Subs work
that Contractor by those instruments assumes
toward Owner and Sub shall have the same rights
and remedies against the Contractor as the
Contractor has against the Owner.
548. Acceptance of Final Payment as Wavier.
55Final Payment Waiver
- Acceptance of final payment by the contractor
constitutes a waiver of all claims. - Under this contract clause, unresolved
subcontract claims may be inadvertently waived
when final payment is received for the original
contact sum. - Avoid this provisions OR be careful not to
request final payment in full until all claims
are resolved.
569. Dispute Resolution.
57Dispute Resolution
- Many subs favor arbitration over litigation.
- One should resist venue and jurisdiction
provisions that attempt to force a dispute to be
resolved in an inconvenient forum far from the
project. - It is important that a subs claims not be stayed
pending resolution of any contractor/owner
dispute. - Be aware of AIA contract provisions.
58Dispute Resolution
- Insist that a subcontract state that the laws of
the state in which the project exists shall apply
and that any dispute should be arbitrated or
litigated in that state.
5910. No Damage for Delay
60BAD DELAY CLAUSE
- The Contractor agrees to make no claim for
damages for delay in the performance of the
Contract occasioned by any act or omission to act
of the Owner or the Architect and agrees that any
such claim shall be fully compensated by an
extension of time to complete the performance of
the Work.
61Where to we go from here?
62Use Conditional Bids
- One way to avoid the unpleasant experience of
receiving an inequitable subcontract after the
fact is to condition the bid upon acceptable
contract language. - This bid is conditioned upon the use of the AIA
A401 Subcontract (2003 edition). - A GC who accepts a bid is therefore not only
accepting the price but also the level of risk
found in A401. Cant force bad contract.
63Use ASA Addendum
- The ASA has prepared a generic addendum
intended to defuse the typical proprietary bad
contract language. - While the ASA Addendum is not perfect, it will
address most of the offensive contract provisions
typically encountered.
64Educate Your Customer
- GCs want subs not only with low prices but also
that read and strictly follow the details in the
plans and specifications. - Let the GC know your professionalism up front but
also advise what subcontract terms are acceptable
and be prepared to explain why certain language
is one-sided and unfair.
65Walk Away From Unfair Contracts
- It is hard to lose a job but it is worst to lose
your company. Look at past losses and determine
if bad contract language was a factor. - Unfair risk shifting have long-range implications
on your companys future.
66Questions?
67NFSA Regional Operations
- On a Path Towards Excellence