Understanding Killer Contract Language - PowerPoint PPT Presentation

1 / 58
About This Presentation
Title:

Understanding Killer Contract Language

Description:

It is not intended to provide legal advice. ... Sub gives up right for its insurer to subrogate but owner and GC can subrogate. ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 59
Provided by: buddy2
Category:

less

Transcript and Presenter's Notes

Title: Understanding Killer Contract Language


1
Understanding Killer Contract Language
2
This PowerPoint presentation is intended to
provide contractors and subcontractors with
practical information regarding problem areas of
contract language and interpretation.  It is not
intended to provide legal advice.  Individuals
and companies seeking legal advice are advised to
consult legal counsel
3
The Dreaded Contract
Unfortunately, none of the parties typically
discuss the nature of the contract and its
provisions until after they have agreed upon the
scope of work and the price.
4
Your Call!
  • Sometimes bad contract language must be
    considered risk should not include the future of
    your company

5
Buddys Top 7 Deal Breakers
6
1. Contingency payment clauses
  • Pay If Paid Pay When Paid

7
Pay If Paid
Red Flag
  • Under a "pay-if-paid" provision, the
    subcontractor will be paid only if the GC is
    first paid by the owner for the specific
    subcontractors work.
  • A pay-if-paid provision creates a condition
    precedent to the GCs duty to pay its
    subcontractor and the risk of an owners
    non-payment is shared by the contractor and the
    subcontractor.

8
Pay If Paid
Red Flag
Typical Contract Language
  • Contractors obligation to pay Sub any sum due
    under the contract is subject to the condition
    precedent that Contractor has first received from
    Owner payment for Subs work. Contractor shall
    have no obligation to pay Sub for any particular
    work unless and until Owner first pays Contractor
    for such work. Sub expressly assumes the risk of
    nonpayment by the Owner to Contractor for any
    reason.

9
Pay If Paid Examples
Red Flag
  • Examples of these clauses might read
  • "Notwithstanding any provision to the contrary,
    payment by Owner to Contractor is a condition
    precedent to payment to Subcontractor"
  • "Receipt of payment from the Owner is a condition
    precedent to payment to Subcontractor and payment
    to Subcontractor will only be made after the
    Contractor is paid by Owner."

10
Pay When Paid
  • With a pay-when-paid clause, so long as the cause
    for non-payment to the general contractor from
    the owner is not related to the subcontractors
    work, the general contractor should be liable to
    the subcontractor immediately following the
    expiration of a reasonable time period.
  • If the general contractor does not receive
    payment from the owner, and it is through no
    fault of the subcontractor, the general
    contractor is still going to be ultimately liable
    to the subcontractor.

11
Pay When Paid
  • These types of clauses deal only with the timing
    of payment and are construed merely as timing
    mechanisms, rather than as waiver/forfeiture
    clauses.
  • They are referred to as pay-when-paid clauses,
    but they do not operate to preclude payment
    indefinitely. In other words, the clauses merely
    provide a GC with some reasonable period within
    which to make payment.
  • The AIA 401 and the AGC 650 subcontract forms
    contain pay-when-paid payment terms.

12
Lien Rights
  • Subcontractors should always retain their lien
    rights in their contracts with general
    contractors. This is especially important when
    the parties contract contains the pay-if-paid
    language.

13
2. Waiver of Lien or Bond Rights
14
Waiver of Lien and Bond Rights
  • Subcontractors should vigorously resist giving up
    the payment security provided by lien and Bond
    Rights.
  • Most states have lien laws that require a Notice
    to Owner when a lien is filed most states have
    specific lien notice and filing timelines know
    state lien laws.
  • However, some courts have upheld such "no lien"
    provisions against contractors that sign them.

15
Pass Down
  • If a contractor agrees to a no lien provision,
    the contractor must put the same language in any
    contracts he enters into with lower tiered
    contractors or material suppliers.

16
Partial Lien Waiver
  • Upon making progress payments, the owner or
    general contractor may require the contractor to
    waive all lien claims that the contractor may
    have for the work invoiced.
  • Such partial lien waiver requirement must be
    contained in the contract.
  • Only waive liens through the date of the invoice,
    not through the date of the payment.

17
Final Lien Waiver
  • Upon completing the job, the GC asks the Sub
    complete a final lien waiver.
  • The requirement to sign a final waiver of claims
    in order to obtain final payment is against
    public policy in most states if the contractor
    has asserted a claim or request for an adjustment
    to the contract price.
  • Subs should not be caught between waiving a
    previously asserted claim, and getting paid for
    its work.

18
Protecting Lien Rights
  • Look for no lien clauses in your contract, and in
    the contract with the owner, if that contract is
    incorporated by reference.
  • Such incorporation language is usually enforced.
  • If a no lien clause is in the contract, try to
    negotiate it out of your contract

19
3. Waiver of Subrogation Rights
20
Typical Waiver Language
  • Contractor shall and does hereby waive any
    rights of subrogation that it or any of its
    insurers may have against the owner, its agents,
    employees or its insurers.
  • "The owner and Contractor waive all rights
    against (1) each other and any of the
    subcontractors, sub-subcontractors, agent and
    employees, each of the other, and (2) the
    architect, architect's consultants, . . . for
    damage caused by fire or other perils to the
    extent covered by property insurance obtained
    pursuant to this contract.

21
Limitations of Waiver of Subrogation Clauses
  • 1. Typically, they apply "only to the extent
    covered by property insurance" obtained pursuant
    to the contract. Thus, if there is not coverage
    under the property insurance for any reason
    (exclusions, etc.), the waiver of subrogation
    clause does not apply, and the owner is free to
    pursue claims against anyone who allegedly caused
    or contributed to cause the event.
  • 2. If the amount of the loss exceeds the amount
    of the property insurance limits of coverage,
    then the owner is free to pursue claims for all
    losses which exceed the amount of property
    insurance.

22
Waiver of Subrogation
  • The "waiver of subrogation" means that by giving
    up its right of recovery, the insurer accepts the
    fact that the policyholder and the parties with
    whom it has contracted have allocated the risk of
    the insured event to the insurer - the insurance
    would be the sole remedy and that all risk would
    be on the insurer.

23
Insurance Policies
  • If the owner has given up (i.e., waived) the
    right to pursue certain claims in the contracts,
    the legal effect is that the property insurer is
    bound by that waiver.
  • Many insurance policies state that the insured
    may waive subrogation provided it is done as part
    of the contract between the insured and its
    client and is done at the outset of the job and
    not after a claim or loss has arisen.

24
Deal Breakers
  • Since builders risk policies are written on a
    great variety of forms, it is especially critical
    for an insured to determine whether the policy
    prohibits the insured from waiving recovery
    rights against another.
  • If the policy does prohibit such waivers and the
    contractor enters into a typical construction
    contract containing a mutual waiver of
    subrogation provision, the contractor may have
    violated policy conditions and voided the
    coverage. This is particularly true in the case
    of waivers of recovery against architects and
    engineers.
  • In the case of design professionals, builders
    risk insurers are hesitant to allow waivers of
    recovery since design errors often cause other
    covered losses under the policy.

25
Ask Insurer
  • Waivers of subrogation should be entered into by
    an owner or a contractor only after permission is
    obtained from the builders risk insurer.
  • It is obviously prudent to seek a clarifying
    endorsement from the insurer. This, of course, if
    especially important where the policy form
    strictly prohibits all waiver of recovery against
    third parties, whether pre- or post- loss.

26
Good Waiver Language
  • Waivers of subrogation to prevent the builders
    risk insurer from bringing suit against the
    contractor and the subcontractor good.
  • Another method to avoid that result would be to
    add the contractor and all of its subcontractors
    as named insureds to the policy since insurers
    are generally not allowed to pursue subrogation
    against their own insureds OCIPs/CCIPs.

27
Deal Breaker Language
  • Sub gives up right for its insurer to subrogate
    but owner and GC can subrogate.
  • Another frequently disputed issue regarding
    waivers of subrogation is the length of time over
    which the waiver extends. Typically, as is the
    case with the AIA documents, the waiver is
    intended to be coextensive with the length of
    time during which the builders risk policy is in
    place, that is, usually the completion of the
    project.

28
4. Incorporation by Reference
29
Incorporation By Reference
  • Be alert to prime contract provisions that
    contain incorporation by reference clauses.
  • Particularly inequitable are provisions that
    incorporate only the contractors
    responsibilities, but not your rights against the
    owner.

30
Example of Concern
  • An owner and contractor used an AIA contract for
    a project. The contract incorporated by reference
    AIA general conditions requiring the parties to
    submit disputes to the project architect for
    decision. The contract provided that the
    architect's decision was "final and binding on
    the parties subject to arbitration." Under the
    contract, either party could demand arbitration
    of the dispute by filing "notice of demand for
    arbitration with the other party to the
    Agreement, with the American Arbitration
    Association and with the architect." The contract
    also provided that failure to demand arbitration
    within 30 days would result in "the architect's
    decision becoming final and binding."

31
5. Change Orders in Writing.
32
Change Orders
  • There is no such thing as a contract that gets
    completed without change orders. Just contractors
    who end up taking it on the chin because of no
    change order procedures in their contracts.

33
Change Orders
  • Make certain that the key basic elements for
    change orders is addressed in the contract
  • Who you have to notify and receive permission
    from for change order work?
  • When and how do you have to notify them of
    potential change order work?
  • What documents do you have to provide?
  • How and when will the change order work get paid?
  • Where will the additional funds come from for the
    change order work?
  • What is the reasonable time for approval and what
    is the additional cost for your delays while
    youre waiting for approval?
  • How will you and the owner resolve the change
    order issue if immediate approval for the work is
    not received in the agreed time?

34
Change Orders
  • Remember, change order work is not extra work.
    It disrupts the progress and productivity of the
    work as you had originally planned for when you
    bid the work. It is neither your fault nor your
    responsibility, and you should be justly
    compensated for this unanticipated disruption.

35
Payment for Change Orders
  • The owner has an obligation to build a building
    in compliance with adopted codes and standards.
    Subs should not pay for the owners obligation.
  • If it is a code required item the owner should
    pay.
  • The only potentially open issue if it is our
    design error is the difference between the cost
    to make the change verses the cost if the
    original plans addressed the item needing change.

36
Design Errors
  • There exists a propensity for design team members
    to reject change orders to fix errors they have
    made.
  • Be cautious of language in design concept
    documents that shift or attempt to shift design
    responsibility to contractors.
  • Successful bidder is responsible to ensure the
    system is installed to code.

37
6. Broad form Indemnification.
38
Indemnity Clauses
  • Three Different Forms of Indemnity Clauses
  • 1. Broad
  • 2. Intermediate
  • 3. Limited

39
Indemnity Clauses
  • Broad Sub shall indemnify and hold harmless GC
    and Owner from and against any and all claims,
    losses, damages, costs and expenses relating to
    the performance of the subcontract and involving
    personal injury, sickness, disease, death or
    property damages, including any resulting loss of
    use, REGARDLESS OF WHETHER CAUSED IN WHOLE OR IN
    PART BY THE NEGLIGENCE OF GC OR OWNER. SUB
    ACKNOWLEDGES AND AGREES THAT IT IS INDEMNIFYING
    GC AND OWNER FOR THEIR OWN SOLE AND/OR PARTIAL
    NEGLIGENCE.

40
Indemnity Clauses
  • Intermediate Sub shall indemnify and hold
    harmless GC and Owner from and against any and
    all claims, losses, damages, and expenses
    relating to the performance of the subcontract
    and involving personal injury, sickness, disease,
    death or property damages, including any loss of
    use, REGARDLESS OF WHETHER CAUSED IN PART BY THE
    NEGLIGENCE OF THE GC OR OWNER. Subs indemnity
    obligation shall not extend to any claims,
    losses, damages, or expenses for which the sole
    cause is the negligence of GC or Owner.

41
Indemnity Clauses
  • Limited Sub shall indemnify and hold harmless GC
    and Owner from and against any and all claims,
    losses, damages, costs and expenses relating to
    the performance of the Subcontract and involving
    personal injury, sickness, disease, death or
    property damages, including any resulting loss of
    use, but only to the extent caused by the
    negligent acts or omissions of Sub, its
    employees, or other persons or entities for whose
    acts Sub may be liable.

42
Indemnification
  • Insurers refusing to cover indemnification
    clauses particularly indemnification of sole
    negligence.
  • Refusing to sign indemnification because of no
    insurance is good argument.
  • READ CONTRACTS hold harmless requirements can
    be worded many different ways.
  • Laws to protect us.

43
Indemnity Clauses
  • 1. Express Negligence Test.
  • 2. Conspicuousness Requirement.

44
Express Negligence Test
  • In Ethyl Corp. v. Daniel Construction, the Texas
    Supreme Court adopted the Express Negligence Test
    for indemnitee agreements.
  • . . . parties seeking to indemnify the
    indemnitee from the consequences of its own
    negligence must express that intent in specific
    terms.

45
Express Negligence Test
  • Furthermore, the court added, Under the doctrine
    of express negligence, the intent of the parties
    must be specifically stated within the four
    corners of the contract.

46
Conspicuousness Requirement
  • The Conspicuousness Test states that a clause is
    conspicuous when a reasonable person against whom
    the clause is to operate ought to have noticed
    it.
  • Language in CAPITAL HEADINGS, language in
    contrasting type or color, and language in an
    extremely short document, such as a telegram, is
    conspicuous.

47
Indemnity Clause Satisfying theConspicuousness
Test
  • Broad Sub shall indemnify and hold harmless GC
    and Owner from and against any and all claims,
    losses, damages, costs and expenses relating to
    the performance of the subcontract and involving
    personal injury, sickness, disease, death or
    property damages, including any resulting loss of
    use, REGARDLESS OF WHETHER CAUSED IN WHOLE OR IN
    PART BY THE NEGLIGENCE OF GC OR OWNER. SUB
    ACKNOWLEDGES AND AGREES THAT IT IS INDEMNIFYING
    GC AND OWNER FOR THEIR OWN SOLE AND/OR PARTIAL
    NEGLIGENCE.

48
7. Additional Insured Endorsements.
49
Additional InsuredEndorsements
  • Sub shall, at no expense to GC, maintain in full
    force at all times Commercial General Liability
    Insurance. This insurance shall be written for
    not less than (limits specified) or required by
    law. The following AIE shall be furnished to GC
    prior to the commencement of the work. In
    consideration of the premium charged, GC is named
    as additional insured with respect to all
    liabilities arising out of the performance of the
    work.

50
Additional InsuredEndorsements
  • Sub shall, at no expense to GC, maintain in full
    force at all times Commercial General Liability
    Insurance. This insurance shall be written for
    not less than (limits specified) or required by
    law, and this insurance shall be primary to any
    other insurance of the GC. The following AIE
    shall be furnished to GC prior to the
    commencement of the work. In consideration of the
    premium charged, GC is named as additional
    insured with respect to all liabilities arising
    out of the performance of the work.

51
Additional InsuredEndorsements
  • . . . . insurance shall be written for not less
    than (limits specified), and this insurance shall
    be primary to any other insurance of the GC. In
    consideration of the premium charged, GC is named
    an additional insured with respect to all
    liabilities arising out of the performance of the
    work. Sub shall waive all rights against GC, its
    agents, and employees for all damages covered by
    insurance pursuant to this contract.

52
Flow Through Provisions
  • BROAD Sub is bound to Contractor by all terms of
    the Prime Contract and assumes toward Contractor
    all of the obligations and responsibilities that
    Contractor by those instruments assumes toward
    Owner.

53
Flow Through Provisions
  • The Subcontract consists of this Agreement and
    any Exhibits attached hereto, and, to the extent
    applicable to the Subs work, the Prime Contract
    consisting of the Agreement between Owner and
    Contractor . . . . Sub is bound to Contractor by
    all terms of the Prime Contract and assumes
    toward Contractor all of the obligations and
    responsibilities pertaining to the Subs work
    that Contractor by those instruments assumes
    toward Owner and Sub shall have the same rights
    and remedies against the Contractor as the
    Contractor has against the Owner.

54
8. Acceptance of Final Payment as Wavier.
55
Final Payment Waiver
  • Acceptance of final payment by the contractor
    constitutes a waiver of all claims.
  • Under this contract clause, unresolved
    subcontract claims may be inadvertently waived
    when final payment is received for the original
    contact sum.
  • Avoid this provisions OR be careful not to
    request final payment in full until all claims
    are resolved.

56
9. Dispute Resolution.
57
Dispute Resolution
  • Many subs favor arbitration over litigation.
  • One should resist venue and jurisdiction
    provisions that attempt to force a dispute to be
    resolved in an inconvenient forum far from the
    project.
  • It is important that a subs claims not be stayed
    pending resolution of any contractor/owner
    dispute.
  • Be aware of AIA contract provisions.

58
Dispute Resolution
  • Insist that a subcontract state that the laws of
    the state in which the project exists shall apply
    and that any dispute should be arbitrated or
    litigated in that state.

59
10. No Damage for Delay
60
BAD DELAY CLAUSE
  • The Contractor agrees to make no claim for
    damages for delay in the performance of the
    Contract occasioned by any act or omission to act
    of the Owner or the Architect and agrees that any
    such claim shall be fully compensated by an
    extension of time to complete the performance of
    the Work.

61
Where to we go from here?
  • Buddys Recommendations

62
Use Conditional Bids
  • One way to avoid the unpleasant experience of
    receiving an inequitable subcontract after the
    fact is to condition the bid upon acceptable
    contract language.
  • This bid is conditioned upon the use of the AIA
    A401 Subcontract (2003 edition).
  • A GC who accepts a bid is therefore not only
    accepting the price but also the level of risk
    found in A401. Cant force bad contract.

63
Use ASA Addendum
  • The ASA has prepared a generic addendum
    intended to defuse the typical proprietary bad
    contract language.
  • While the ASA Addendum is not perfect, it will
    address most of the offensive contract provisions
    typically encountered.

64
Educate Your Customer
  • GCs want subs not only with low prices but also
    that read and strictly follow the details in the
    plans and specifications.
  • Let the GC know your professionalism up front but
    also advise what subcontract terms are acceptable
    and be prepared to explain why certain language
    is one-sided and unfair.

65
Walk Away From Unfair Contracts
  • It is hard to lose a job but it is worst to lose
    your company. Look at past losses and determine
    if bad contract language was a factor.
  • Unfair risk shifting have long-range implications
    on your companys future.

66
Questions?
67
NFSA Regional Operations
  • On a Path Towards Excellence
Write a Comment
User Comments (0)
About PowerShow.com