Project Management - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Project Management

Description:

Establish Performance Standards at the BEGINNING ... Meghan. Pete. Mike. Avoid This. Parallel Preferred. 18. ME340. Recommendations ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 25
Provided by: noisecon
Category:

less

Transcript and Presenter's Notes

Title: Project Management


1
Project Management
  • Reference Chapter 16, Ulrich Eppinger

2
One enemy of good project management is Feature
Creep
3
Project Management balancing and planning
  • Balancing
  • Deliverables
  • Cost
  • Quality
  • Planning
  • Technical issues
  • Time
  • Resources
  • Personnel
  • Equipment/facilites
  • Budget

4
Fundamentals of planning
  • Establish Performance Standards at the BEGINNING
  • Assure Performance Standards as Project
    Progresses
  • Verify Final Performance Against Standards
  • NO SURPRISES!

5
Benefits of planning
  • Framework for communication
  • Clients and coworkers
  • Allocate resources
  • Personnel, equipment and facilities, budget
  • Benchmark to measure progress

6
Time planning
  • Identify TASKS
  • Estimate DURATION of Tasks
  • Establish PRECEDENCE of Tasks
  • Record MILESTONES (Performance and Dated)
  • Plan Start and Finish DATES for Tasks

7
Three Fundamental Activity Relationships
Example Kodak Cheetah Microfilm Cartridge
RECEIVE AND ACCEPT SPECIFICATION
CONCEPT GENERATION/ SELECTION
DESIGN BETA CARTRIDGES
Sequential
Parallel
Coupled/Iterative
8
Program Evaluation and Review Technique (PERT)
Critical Path Method (CPM)
  • A network or flow diagram
  • Two basic varieties - Activity in Box (AIB),
    Activity on Arrow (AOA)
  • Shows how activities (tasks) are related
    (dependencies)
  • Helps identify critical path the longest chain
    of dependent events
  • Useful for allocation of resources and personnel
  • Promotes parallel activities

PARALLEL TASKS
COUPLED TASKS
9
Program Evaluation and Review Technique (PERT,
AIB form)
8
4
C
2
4
8
2
2
10
2
5
14
6
Task or Activity
Critical Path
2
Duration (weeks)
10
PERT/CPM how to
  • Tabulate Project Tasks
  • Title and ID Number for Each Task
  • Estimate Duration for Each Task D(O4MP)/6
  • O Optimistic, M Most Likely, P Pessimistic
  • Estimate Resource Requirements for Each Task (May
    Need Dummy Tasks for Critical Resources)
  • Identify Prerequisite Tasks for Each Task
  • Layout Flowchart of Tasks Based on Dependencies
    NOT Time
  • Indicate Performance Milestones on Flowchart

11
PERT/CPM how to (continued)
  • Calculate Earliest Completion Time and Latest
    Completion Time
  • Beginning at start of project, ECT for task ECT
    for preceding node duration
  • Beginning at end of project, LCT for task LCT
    for following node - duration
  • Calculate Slack Time for Each Task
  • Slack for Task ECT - LCT
  • Determine Critical Path
  • Longest Time Path
  • Zero Slack

12
PERT/CPM pros and cons
  • Strengths
  • Shows Task Dependencies
  • Predicts Critical Path
  • Identifies Slack Time for Resources
  • Weaknesses
  • Assumes Subsequent Task Starts Immediately After
    Prerequisite Concludes
  • Difficult to Visualize Timing

13
Gantt Chart
  • A timeline diagram, bar chart
  • Shows timing of milestones and tasks
  • Does not show task dependencies

14
Gantt how to
  • Tabulate Project Tasks
  • Title and ID Number for Each Task
  • Estimate Duration of Each Task
  • Estimate Resource Requirements for Each Task (May
    Need Dummy Tasks for Critical Resources)
  • Identify Prerequisite Tasks for Each Task
  • Layout Bar Chart with One Bar per Task based on
    Time
  • Add Dated Milestones

15
Gantt pros and cons
  • Strengths
  • See Status of Each Task at Any Point in Time
  • See Overlapping and Parallel Tasks
  • Weaknesses
  • Unable to Tell if the Entire Project is on Time
    for Highly Dependent Projects
  • Difficult to Show Critical Path

16
MS-Project
  • Tool for project planning and tracking
  • Can switch between PERT and Gantt views

17
How to build a Gantt Chart
  • Identify all necessary tasks the task list
  • List all milestones and deliverables
  • Assign responsibility and duration to each task
  • Identify task dependencies
  • Use MS Project

Parallel Preferred
Avoid This
18
Recommendations
  • Organize tasks in parallel as much as possible,
    avoid serial tasks
  • No task longer than 1 week
  • One person is assigned to each task
  • Build in contingency (safety) time
  • (minimum 10-20)
  • Do not believe suppliers promises of delivery
  • Order an assortment of materials and components,
    not just what you think you will need

19
The Baseline Project Plan
  • Contract Book
  • documents the project plan
  • Project Task List, with time estimates
  • Team Staffing and Organization
  • Project Schedule
  • PERT, Gantt or both
  • Budget
  • How you plan to spend your money
  • Risk Plan
  • What if things dont go as planned, how will you
    recover?

20
Contract Book
21
Risk Plan
22
Critical success factors for team staffing and
organization
  • 10 or fewer members on team
  • Members volunteer to serve on team
  • Members serve from concept development until
    product launch
  • Members are assigned to the team full time
  • Members report directly to team leader
  • Key functions are on the team (including at least
    marketing, design and manufacturing)
  • Members located within conversational distance

23
Management of your final project
  • Prepare a time schedule (Gantt Chart) for your
    project
  • Task List with time estimates
  • Identify task dependencies
  • Identify person responsible for each task
  • List milestones
  • Rough draft on paper (today), then use MS
    Project, Excel

24
For next class
  • Gantt chart in MS-Excel or MS-Project
  • 2) Journals will be collected on F 11/2
Write a Comment
User Comments (0)
About PowerShow.com