Title: PROJECT MANAGEMENT
1PROJECT MANAGEMENT
- PROJECT METHOD OVERVIEW
- Version 1.0
- Issued 31.05.2006
2Training Objectives
- A High Level Overview of NWCEs Project
Management Methodology
3What is a Project?
- a management environment that is created for
the purpose of delivering one or more business
products according to a specified Business Case
(PRINCE2) - Characteristics
- Finite
- Business Case Must Exist
- Deliver Something Products
- Not Business as Usual
- Created Management Environment
No Two Projects Are Exactly The Same
4What is a Programme?
- A collection of projects that together achieve a
beneficial change for an organisation.
5Typical Differences between Programmes and
Projects
6Why Project Management?
75 of Projects Fail
- Research conducted on behalf of the ODPM
suggests that authorities suffer from - lack of skills in project management
- no single defined method for project management
- initiative overload due to poor project
management - lack of capacity in project management
- lack of sponsorship at a senior level
- Capacity Building in Local Government
Research on Capacity Building Needs
7PRINCE2
8PRINCE2
9PRINCE2 Processes
10PRINCE2 Start Up Process
11(No Transcript)
12A Simplified Approach to Project Management
- Prince2 A Simplified Model
- Flexible
- Process Oriented
- Focus on Key Deliverables
- Provide Templates
- Practical Guidance
- Worked Examples
13A Simple Model
14How Does it Work?
15The Full Process Model
End Project Report
Full Business Case PID
Outline Business Case
Exception Report
Highlight Report
Issues Log
Risk Log
16The Project Management Toolkit
- 4.3 Risk Log (Stage 6)
-
- Risk is a major factor to be considered during
the management of any project. Project management
must control and contain risks if a project is to
stand a chance of being successful. -
- The risk log provides a repository of information
about the project risks, their status, impact,
evaluation and countermeasures. It will be a
living document that will be revisited throughout
the life of the project. -
- Inputs
- Outline Business Case
- Project Profile Risk Analysis Model
-
- Process
- Complete the Risk Log Template by filling in any
risks identified so far. A template including
full instructions can be found on the TheLoop. A
good place to start is to add in the high scoring
risks identified in the initial risk analysis. -
- Responsibility
- Project Manager
-
- Outputs
- Risk Log
17The Toolkit and Templates
- To access the toolkit and project management
templates please visit the NWCE website. They
can be found by visiting the following link - www.nwce.gov.uk/projectmanagement
18Project Categories
19Starting a Project
20High Level Project Organisation
21Do We Have a Project?
- Is there a Business Case?
- How much will it cost?
- How long will it take?
- What risks are involved?
- Are the benefits worth the effort?
Go to next stage? ?
22Initiating a Project
23Full Business Case
- Business Case Drives The Project
- The Business Case Can Change Over Time
- Project With An Invalid Business Case Should Be
Stopped - Responsibility Board
24Whats Involved Exactly?
- WHAT? WHO? HOW? WHERE? WHEN?
- Objectives Scope
- Deliverables
- Approach
- Quality Controls
- Communications
- Project Plan
Run the Project? ?
25Coffee Break
26Directing a Project
27Various Project Interests
Project Board
Project Board is NOT a democracy! The
Executive/Owner is the decision maker, with
advice and commitments from the others.
28Project/Programme Board
- Making CRITICAL Decisions
- Authorising Project Stages
- Committing Resources
- Monitoring Progress
- Communication Support
RESPONSIBLE for SUCCESS!
MANAGEMENT BY EXCEPTION - MBE
29Management by Exception
30Management by Exception
- Authorising Project Stages
- Tolerances Time, Cost
- Change Control
- Highlight Reports
- Exception Reports
- End of Project Assessment
31Tolerances
- TIME
- COST
- QUALITY
- SCOPE
- BENEFITS
- RISK
32Managing a Project
- Planning
- WHTBD
- Managing
- Risks
- Issues
- Reporting
- Delivery
- Work
- Products
33Planning
- Design a Plan
- Define the Products
- Identify Activities
- Estimating
- Scheduling
- Analysing Risks
- Completing the Plan
34Product Based Planning
- Product Breakdown Structure
- Identify the products
- Group the products logically
- Product Descriptions
- Quality Attributes
- Product Flow Diagram
- Sequence
35Product Breakdown Structure
36Managing Risks, Issues and Changes
- RISK possible future impact
- ISSUE its already happened
- Basic Process
- Log
- Assess Impact Analysis
- Assign Ownership Action
- Monitor Report
- CHANGES raised as issues
37Risk Analysis / Management
- EVALUATION
- Likelihood
- Impact
- RESPONSES
- Prevention
- Reduction
- Transference
- Contingency
- Acceptance
38Change Control
39Project Reporting
40Highlight Reports
- RED/AMBER/GREEN
- Overall Project Status
- Budget Status
- Schedule Status
- Products Completed
- Actual Problems (Issues)
- Potential Problems (Risks)
- Forward Plan
41Managing Delivery
Authorise a Work Package
Assess Progress
Accept a Work Package
PROJECT MANAGER
MBE
Accept a Work Package
Execute a Work Package
Deliver a Work Package
TEAM MANAGER
42Work Packages
- Mini-Projects
- Focus on Deliverables / Products
- Approach
- Resources Required
- Time, Cost, Effort
- Quality Controls
- Authorisation Approval
43Product Descriptions
- Purpose
- Composition
- Derivation
- Format
- Who will produce it?
- Quality criteria and checks
44Closing a Project
45Closing a Project
- Has everything been delivered?
- Is there anything left to do?
- How well did the project perform?
- What could we have done better?
- When will benefits accrue?
46The End!