Title: Dr. George Jergeas PEng
1Managing Fast Track Projects A Guide and
Checklists
- Dr. George Jergeas PEng
- University of Calgary
- Project Management Specialization
2Reference
This presentation is based on the European
Construction Institute (ECI) - UK ECI
Manual The Fast Track Manual A guide to Schedule
Reduction for Client and Contractors on
Engineering and Construction Projects
3Agenda
- Introduction
- Different Project Stages
- Concept Stage
- Development Stage
- Definition Stage
- Design Stage
- Procurement Stage
- Construction Stage
- Commissioning
- Operation Stage
- Key Issues
4Introduction
- Takes place more quickly than normal
- A difficult and often stressful route to follow
- There is no boundary between a normal project and
a fast track project - Projects ranged from 4 - 36 months
- Schedule reduction 10 - 29
- Cost increase 10 - 20
5Reasons for Fast Track
- Urgent requirements by client
- To maximize profit or limit loss
- Imposed deadline
- Start of academic year
- End of current lease
- New legislation
- Minimize disruption of services
6Objectives
- To assist who are considering a fast track to
make the right decisions - To help implement fast track strategy successfully
7Key Success factors
- The calibre of individuals and their working
relationships - The adequacy of the definition of the project
- Strategy adopted and systems for implementation
- The passion to succeed on the part of key
participants
8Definitions
- A managerial approach to the achievement of
early project delivery, involving the application
of innovations in the management of construction
procurement and recent advances in the process
that, bringing into play - The integration of construction and design phases
- The involvement of the contractor in both the
design and construction phases - Overlapping of work packages to enable
construction of sections of the project to
proceed while the design for other sections is
being progressed - The employment of the expertise of suppliers in
design and construction - Kwakye, 1991
9Definitions
- Design and construction are overlapped and
different sections of the plant are designed and
built in parallel with significant additional
risk due to the links between the design of
different parts of the plant - Turner, 1996
- The reduction of the the schedule to the minimum
practicable is the principal driving force for
one or more stages of the project
10Project Stages
Normal Project
Fast Track Project
11General Principles
- Work Package Overlap
- Work packages are progressed in parallel
- Overlap the stages for each work package
- Early Decisions
- Experienced judgement and empowerment
- Commence design before scope has been defined
- Must accept wrong decisions
12General Principles
- Integrated Project Team
- Main parties are combined into a single
organization and participate to the limit of
their capability in achieving the project
objectives - Partnering
- Benefits
- Availability of additional expertise
- Avoiding learning curve errors
- Reduction in the overall workload
- Commitment to the project definition and schedule
- Design and construction developed together
13General Principles
- Additional Staff
- More labour will be needed at peak period as a
consequence of scheduling activities in parallel - More management resource will be needed to deal
with interface and progress issues arising from
inter-dependencies between disciplines and
between design, procurement and construction - Schedule Reduction Techniques
- Project must be managed in an efficient manner
making full use of project management and
schedule reduction techniques
14General Principles
- Additional Risks
- Decisions based on limited information, cannot
always be right first time - A structured and thorough risk management process
needed
15Advantages vs. Disadvantages
- Advantages
- Time to market
- Commercial benefits
- Short schedule (at least 10)
- Reduce time period for risk exposure
- Disadvantages
- Additional risk factors, very limited
alternatives - Increased amount of PM, control, etc.
- Cost increase (at least 10 20)
16Characteristics that Support Strategy
- Ownership
- Client support
- Project sponsor or champion
- Stakeholder support and commitment
- Organization
- Project team needs to be simple, clear and devoid
of rigid hierarchy - If parent organization has a functional matrix
structure, the functional line must be
subordinate to the project management (task) line
for the duration of the project team
17Characteristics that Support Strategy
- Desirable Team Characteristics
- Honesty - Openness - Trust
- Anticipation and avoidance of issues rather than
waiting for them to turn into problems - Mutual support - issue resolution, coaching
- No blame culture
- Access to all parties, no communication barriers
- Lean organization, which aids communications and
speeds decision taking - Full time members
- Authorized and empowered team members
- Decision making on the spot without referring
18Characteristics that Support Strategy
- People and Relationships
- Technical competence
- Decisiveness - self starter - can do -
flexibility - Ability to forecast outcome and act accordingly
- See the big picture
- Willing to collaborate
- Enthusiasm
- Strong leadership
- Managerial competence
- Openness
19Characteristics that Support Strategy
- Motivation
- Create a team culture that avoid de-motivation of
individuals who are keen to succeed, but are
prevented by the organization, procedures,.. - Working part of a team, working equally hard and
supporting each other - Appoint key positions to individuals known to be
good motivators - Early identification and removal of
under-performing individuals - Team building and partnering sessions
- Incentive/penalty clauses
20Characteristics that Support Strategy
- Contractual arrangements
- Achieve win-win situation
- Pre-selected, preferred contractor
- Reimbursable basis, with incentives
- Lump-sum can also be used
- Partnering
- Up front agreement for payment for changes and
extras
21Characteristics that Support Strategy
- Communications
- More informal communication - face-to-face
- Barriers should be removed - information flows
directly between the parties regardless of parent
organization and level of hierarchy - Responsibility for communication lies with the
individual who has made a decision - Frequency and progress meetings
- Frequent and concise reporting
22Concept Stage
- Introduction
- Time to establish the concept is NOT recoverable
- The opportunity to influence the outcome falls
off rapidly - People
- Stakeholders (ALL Should be identified)
- Integrated Team (Sponsor, Project Manager
Senior Managers from different key players) - Qualified personnel and motivated
23Concept Stage
- Scope
- Identify the real Goal and Objectives of the
client - Identify Critical Success Factors (CSFs)
- Strategy
- Fast tracking should be avoided unless the client
business benefits from early completion
significantly and outweigh risks - Contract strategy addressed and outlined
24Concept Stage
- Business and PM Systems
- Business Planning
- process for weeding out poor projects
- A smooth transition from business process to PM
process - Stage gates process
- Communications
- Rapid transmission of information
- IT systems
- Publicity needs to be controlled
- Risk Management
- Cost and Risk
- Determination of cost is difficult
- Limited industry information on fast track
projects - As accurate as possible estimate to help in the
decision to adopt a fast track strategy
25Concept Stage
- Logistics
- Consideration to location of new asset in
relation to - Location of customers
- Source and availability of feedstocks, component
parts - Supply routes
- Transport security and cost of supply and
products - Existing assets
- Workforce skills and availability
- Also should consider
- Locations of parties involved
- Client site - design office - contractor -
contractors and sub-contractor - suppliers - Sources of construction equipment - material -
supply routes and methods - Site access and
controls
26Definition Stage
- Introduction
- Lack of adequate definition has arguably been
responsible for more project failures - Expenditure of 25 of the total design effort
- Design will need to be progressed on those
elements of the definition that are sufficiently
secure in order to feed information to
construction at the earliest practicable time - Quality of project definition is very often a
casualty, with the potential for overruns of cost
time
27Definition Stage
- People
- Clarity of objectives
- A clear focus on the objectives as agreed with
stakeholders at the concept stage must be
maintained in order to aid in the decision making
process - Stakeholders
- The significant stakeholders early identified
should continue to be involved, consulted and
advised - Any other identified stakeholders should be
involved ASAP - Integrated Team
- If the project has not so far been led by the
project manager who will be responsible for
seeing it through to beneficial use, that
individual should be appointed at the beginning
of the definition stage
28Definition Stage
- People
- Suitably qualified and experienced personnel
- The team should not be selected only on their
technical and managerial competencies but also
on their ability to - Overcome the obstacles and succeed in achieving
the project CSFs - Work with high level of uncertainty
- Work flexibly outside the normal work boundaries
- Co-operate with others for the benefit of the
project - Project Scope
- It is essential that the project team have a
clear understanding of what has been agreed by
stakeholders to be in the scope and what is
outside the scope
29Definition Stage
- Scope
- For technical definition consider
- Fit for purpose (which may not be ideal
sometimes) - Fastest to manufacture/construct rather than
cheaper - Reuse of design from existing assets
- Modular design
- Pre-fabrication of components
- Minimization of project scope lean construction
approach - Reduction in the number of processing steps in a
manufacturing plant
30Definition Stage (Cont.)
- Scope
- Reduction in the size of the asset
- Elimination of non-essential elements of the
design - Standardization of layout or repeated units
- Standard / off-the-shelf components
- Simplification of design dependencies
- Simplification of the build/construct/assemble
process - Avoidance of innovation/new/untried elements in
general - Early identification and ordering of long
delivery items - Constructability / Operability
- This stage should also include
- Arrangements for handover and commissioning
- Proving and warranty test to be carried out
- Definition of beneficial operation / use as the
end point of the project
31Definition Stage (Cont.)
- For the Overall Scope also consider
- Achievement of the overall project objectives,
both what is to be done and how it is to be
achieved - Whether phased completion would be acceptable
- Arrangements for handover and commissioning
- Proving and warranty test to be carried out
- Definition of beneficial operation / use as the
end point of the project - Project specific critical success factors
32Definition Stage
- Project Strategy
- It should take into account the same aspects
which were considered in the concept and
development stages that include - Work Breakdown Structure and the ability to spilt
the project into relatively independent parts - Willingness to take early decisions and accept
competent solutions - Ability to keep options open until the last
responsible moment - Elimination of hold points for the approval of
design - Agreement that the project will accept the best
decision in light of the information available at
the time - Acceptance of risk taking, and the impact of each
risk - Delegation and empowerment of the team to promote
decisions - Early applications of authorization and approvals
- Availability of benefits / incentives for all
project parties - Opportunities to allocate risk and share rewards
33Definition Stage
- Project Management Procedures
- Planning
- It is essential that, as the definition evolves,
work is scheduled on the basis of achieving the
earliest beneficial use of the finished asset - It is also essential that interactive planning
process advocated as a team building activity - Project Process
- Based on the project organization, the project
procedures may be those of the client, the
contractor or one of the other parties - Standard processes need to be modified to
accommodate the degree of overlap between various
stages - Authority to approve modifications should be
assigned ASAP - A project risk management system must be set up
as part of the project procedures - A good system for project documentation is
essential
34Definition Stage
- Project Management Procedures
- Project control
- Care is needed to ensure that previously rejected
ideas are not reintroduced at the definition
stage - The use of Value Engineering / Constructability
is essential to enhance the decision making
process - Project Communications
- A good communications system need to be
established and maintained - This could include intranet, Extranet, Internet,
Chat rooms, Bulletin Boards, Event Calendars,
Data Base, etc. - The greater the level of integration in the
sharing and re-use of information the more that
the communication system will support the project
and enhance success
35Definition Stage
- Project Management Procedures
- Cost and risk
- Cost
- Approval of cost will have to be given on a lower
level of definition and with a wider tolerance on
the estimate if the project is to proceed
unhindered by the supply of funds - A cost estimate to within plus or minus 10 will
not be obtained until the end of the design stage - It is recommended that a control estimate should
be produced once all the necessary details are
known - During this stage it will be necessary to address
the potential cause of increased cost which may
rise
36Workshop 1 Risks
List risks associated with the increased level
of overlap between definition and design stages
of a project.
37Solution Workshop 1
- Design and construction rework arising from lack
of firm definition - Additional management effort at peak to control
the project - Use of additional resources arising from repeat
work and parallel working requiring more than
optimal number of people - Essential additional items to achieve the CSFs
which creep into the scope through lack of firm
definition - Procurement against best/guaranteed delivery
rather than lowest price - Additions to equipment orders as details evolve
- Additional expediting
38Solution Workshop 1
- Air freighting to speed delivery
- Incorrect initial material quantities which may
give rise to surpluses, or shortages which will
need to be topped up at premium costs - Additional contingencies being included in
quotations to cover unknown elements where there
is no scope - High allowances in tender prices to cover
penalties for defaults - Overtime and shift working resulting in higher
cost and loss of productivity - Over design vs. waiting for detailed information
39Design Stage
- Introduction
- The main purpose of this stage is to finalize the
design requirements for the project - This stage requires a good understanding of the
options for compressing the schedule - It requires the use of the most up-to-date proven
computer aided design - People
- Clarity of objectives
- The most elegant design is useless unless it is
capable of being built safely and to time and
budget, this has to be fully understood by the
project team and senior management
40Design Stage
- People
- Stakeholders
- The interests of all stakeholders should be kept
under review as the design progress so that
interested parties can be kept up to date and
involved at the earliest appropriate stage - Alliances
- Establishment of a long-term relationship between
the companies and team involved helps to ensure a
rapid start-up of the team involved on the
project at each stage - Integrated Team
- This stage requires the use of single design team
incorporating the expertise of all discipline and
involving those responsible for subsequent stages
of the project - The design should be able to be right first
time to minimize the number and duration of
design reviews
41Design Stage
- Integrated Team
- The team need to be supported with appropriate
collaboration and communication systems - Team members should have clearly identified roles
and objectives to eliminate duplication and
inefficiencies - The team members need proper empowerment to
promote rapid and effective decision making - Team members should be very competent and
experienced in order to enhance the efficiency of
the design - Project Scope
- Clarity of definition
- The problem with some fast track projects is that
detailed design has to proceed without total
clarity of definition - It is a a matter of judgment as to which areas
are sufficiently well defined to proceed without
incurring too great risk
42Design Stage
- Project Scope
- Extent of design
- The extent of design details need to be defined
from the beginning. Some elements of design has
always been left to contractors on site to
complete - There will be no benefit if the easy 95 of the
project is fully detailed and the contractor is
left to struggle with the difficult 5 - Design can only be based on the best option at
the time given information available - Early involvement of contractors and suppliers is
essential
43Design Stage
- Over-design
- In the absence of hard information it is
necessary to make more generous allowances than
would normally be the case - The level of the over-design will depend on the
extent of the un-known, the significance and
perhaps the cost of the time - The design can be based on the maximum expected
values e.g., weight of structure, pressure in
system together with an appropriate safety factor
rather than waiting until precise values can be
calculated. - Example There maybe little cost difference for
the project as a whole if piling is 30
over-designed or 50 over-designed, but may allow
site work to proceed well ahead before the
accurate details of the superstructure can be
determined.
44Design Stage
- Design process
- The design sequence must be planned to ensure
that the schedule needs of construction drive the
design process for the production at the right
time of - Design information
- Drawings
- Documents
- Materials
- Equipment
- Long lead item data sheets and specifications
will need to be produced out of sequence with the
rest of the design.
45Design Stage
- Design process
- Visual appearance and structural design may need
to be compromised to achieve the fastest
completion - Design option selection may be based on fastest
to manufacture or build rather than lowest cost - Design will overlap with procurement and
construction - Design of work packages will be in parallel
- By-pass design areas with insufficient
information and work to assumptions put
experienced team members to work resolving the
issues within the black box area - Incorporate constructability to ensure the
optimum construction productivity - Design holds must be minimized as possible
- Design reviews must be carried out very
thoroughly
46Design Stage
- Design process
- Design freeze
- The overlap between definition, design and
construction means that the number of unknowns
remains higher than in a normal project while
work is proceeding on the following stage - Only freeze part of the design which then have to
be accepted as constraints on the rest of the
design
47Design Stage
- Strategy
- Simplicity and repetition
- Reduction in the number of processing steps in a
manufacturing plant - Reduction in the size of the asset
- Elimination of non-essential elements of the
design (de-scoping) - Standardization of layout or repeated units
- Simplification of the build / construct /
assemble process - Standard / Reusable / Off-the-shelf-design
- Consideration should be given to re-use design of
an existing asset - An existing asset can be used to train both the
constructors and users of the new asset - Base the design of the long delivery items on
those that already exist so that material
procurement and fabrication can be started at the
earliest possible time.
48Design Stage
- Strategy
- Modularization
- If the overall design can be structured as a
series of units or modules then there is the
potential to introduce a number of schedule
reduction approaches - Progress separate modules in parallel using
separate design teams, suppliers, construction
contractors - Care to identify all the interdependencies
between the separate modules and to ensure that
these are taken into account as the design
progresses. - If a number of the modules can be of similar
design then should be possible to utilize the
experience gained on early modules to improve the
efficiency and time - In a process plant design as a number of parallel
streams, rather than a single large stream
Smaller and off-the-shelf items - Consider the concept of sub-modules mounted
within plant p may be interchangeable
49Design Stage
- Strategy
- Prefabrication / Pre-assembly
- Manufacture modules off the site and under
factory controlled conditions - Cladding panels complete with windows, external
fittings, internal finishes - Fully finished air handling units
- Skid mounted plant
- Fully finished bathrooms
- Standardized internal partitioning
- Completed, tested, validated pilot/ process plant
- Design tools
- The low technology approach will often be found
(on many projects) to be the quickest to produce
results - Consideration to the use of the latest, proven,
design (CAD) and communication systems (IT)
50Design Stage
- Project Management Systems and Procedures
- Planning
- Planning of the design must be driven by the
requirements of later stages, mostly the
construction stage. - Interactive planning which involves all members
of the project team in problem solving and plan
optimization. - Critical Chain project planning methodology has
been credited with a significant reduction in
project duration. The methodology results in the
schedule contingency, which is normally hidden in
the planned duration of each activity, being
removed from the critical chain of activities and
being replaced by a number of buffers of project
contingencies that are provided to protect blocks
of activities and are visible to the project team
51Design Stage
- Project Management Procedures
- Project Control
- Effective project control is one of the keys to a
successful fast track - It must be a dynamic process with a very short
cycle time so that deviations are recognized and
corrected - Design progress measurements should be at the
simplest level - Frequent up-dates of measurements / information
- Progress information / reports are simple,
concise and easily available to relevant people - Monitoring of key trends flogging adverse
trends and forecast out-turns that are not in
accordance with the schedule including schedule
float. - Exception reporting of items not completed to
schedule - Progress against deliverables, milestones, CSFs
and forecast out-turns - Earned Value measurement
52Design Stage
- Project Management Procedures
- Design Approval
- To ensure that the client fully understands the
detail of the assets being created and does not
come up with additional or alternative
requirements during procurement, construction or
commissioning phases, it is necessary to have
good design approval system which includes
sign-off by the client. - Approval of the design sub-units that are the
responsibilities of specialist vendors may need
to take place on their premises to avoid delays - Design verification
- Verification should commence as soon as possible
to limit the amount of re-work
53Design Stage
- Project Management Procedures
- Change Control
- Effective change control system is essential, but
is difficult to enforce due to the increased risk
of rework arising from the overlap of design and
construction. - Rapid rejection and approval will help to limit
rework and minimize the impact of change - Communications
- Good verbal communications need to be established
between the parties so decisions are known
quickly and design can progress rapidly. - Meetings should be kept to a minimum and focused
on decision taking rather than communication of
matters purely for interest. - Communications within the team should take place
as needed and not be restricted to a meetings
timetable - Communications with other parties outside the
design team need to be kept up to speed with
design details as they evolve - Full use of IT systems for storage and
communication of information
54Design Stage
- Project Management Procedures
- Constructability Reviews
- The integrated team is best placed to address the
issues which arise from Constructability
considerations as the structure and detailed
design are evolving.
55Design Stage
- Cost and Risk Considerations
- The main risks in this stage are of increased
cost and delay due to sub-optimum design or
incorrect design resulting in rework - The root cause can be either commencing detailed
design before a comprehensive and firm definition
has been agreed or from the early decision
approach where there are interdependencies
between the elements on which parallel working is
taking place.
56Workshop 2 Risks at the Design Stage
- List the risks associated with increased overlap
between design and construction stages - List the risks associated with increased overlap
between design and procurement stages
57Workshop 2 Solution
- List the risks associated with increased overlap
between design and construction stages - Product which is to be manufactured on the plant
fails its trials - Failure of innovative designs as a result of
putting them into practice without sufficient
development - Failures of innovative methodologies as a result
of hasty and insufficiently considered
application - Increased level of rework as a result of
- Lack of firm definition
- Omissions as a consequence of out-of-sequence
design - Changes to design of fabricated items after
delivery to site - Increased whole of life cost due to sub-optimum
design - Conflict
58Workshop 2 Solution
- List the risks associated with increased overlap
between design and construction stages - Increased capital cost arising from
- Modularization e.g., extra structural steel,
extra joint/connections, greater precision - Over-design due to judgments based on limited
information - Sub-optimum design through the use of standard
designs or reuse of existing design - Problem at design and construction discipline
interfaces
59Workshop 2 Solution
- List the risks associated with increased overlap
between design and procurement stages - Lack of understanding of scope
- Design changes requiring revised contract and
purchase orders leading to delays or cost
increases - Errors or omissions in purchase of materials or
equipment - Reduced certainty of outcome for all project
parameters cost, time, quality, safety - Interdisciplinary design conflicts arising from
out of sequence working - Problems with systems integration
- Inappropriate form of contract for those
contracts which are let on the basis of
inadequate or incorrect design information - Selection of inappropriate contractors
- Inappropriate allocation of risk
60Design Stage
- Logistics
- Design team location
- The design team is the center of the project team
activities - If the whole project team cannot be located
together, consideration should be given to locate
them all together through the design stage - Access
- Arrangements should be made for design team to
gain access to project site as early as possible
61Construction Stage
- Introduction
- Manage the additional risks
- Achieve high productivity from construction work
force - Good understanding of options for compressing the
schedule - Good risk management and communication system
- Coordination among all contractors and suppliers
- People
- Clarity of objectives
- The CSFs and what is expected of site staff in
achieving these CSFs should be communicated to
all construction staff - The key performance indicator against which
construction performance is to be measured should
be explained - The interests of the site workforce should be
identified (working arrangements, working
periods, flexibility and critical path activities)
62Construction Stage
- People
- Integrated team
- Single integrated team with one culture should be
carried through to the construction site (it may
be difficult with many suppliers) - Contracts between the parties involved need to be
set up to promote integration and co-operation
and to enable all parties to be available as and
when demanded by the schedule. - The following elements have been noted as being
helpful - Effective management of the overall team effort
- Contractual obligations for all parties to work
co-operatively regardless of direct contractual
relationship - Design staff to be based on the construction site
- Rapid response from engineering staff not site
based
63Construction Stage
- Integrated team
- Vendors available to assist in the erection, site
testing and pre-commissioning - Dedicated staff to co-ordinate and expedite
permits, clearness, etc. - Commissioning staff used as construction
inspectors - Client and commissioning staff involved in punch
listing of defects - Project facilitators to deal with hold ups,
interface problems - Joint construction and commissioning punch
listing team - Punch list rectification squad which is separate
from the normal construction squad to hit
critical items while avoiding disruption to
construction progress - Testing as part of the installation process, not
subsequent activity
64Construction Stage
- People
- Delegation and empowerment
- Authorize and empower members of the project
team to promote rapid and effective decision
taking at the lowest competent level - Necessary numbers and skills must be made
available to meet the demands of the schedule - Supervision ratios may need to be increased
- Skilled and experienced staff are employed
- Construction team motivation is essential to
enhance success - Remove disincentives and provide incentives
- Schedule is challenging but realistic
- Demonstrate management dedication and commitment
- Remove underperforming staff from team
- Simplify work methods
- Avoid non-essential overtime
- Supply design information, materials, equipment,
support services
65Construction Stage
- Scope
- A clear definition of scope in form of drawings
and specifications, codes, standards and best
practices. - Need to now what is required and how to deliver
he scope - Strategy
- Construction plan
- Satisfy conditions for plant commissioning and
handover - Provision of agreed documentation to following
stages - Pull through of design, materials, equipment,
resources - Inclusion of output from Constructability reviews
- Utilization of latest proven methods and
technical improvements - Detailed planning / control for critical path and
special operations - Modularization and off-site fabrication
- Locations of site facilities, workshops, etc.
- Complete weld preps prior to installation of
steelwork/pipes - Pre-painting of pipes and steel
66Construction Stage
- Site contracts
- Number and arrangement of contractors should be
optimized for speed of construction - Management and resources
- Number and skills supplied to meet demands of
plan - Competence in required project management and
discipline skills - Workforce clocking / accommodation / messing
facilities close to work faces - Materials and equipment
- Materials and consumables supplied to ensure no
delay through shortage - Materials management system to supply materials
and equipment safely and efficiently to the work
face - Generous supply of construction equipment,
personal protective - Construction, commissioning and operational
spares ordered with equipment
67Construction Stage
- Quality assurance
- Build quality in. Do the job right the first time
(inspection does not improve quality) - Systems designed to minimize rework
- Ensure that the latest revision is n use and
previous issues have been withdrawn - Access
- Good, safe site access
- Generous lay-down, storage and work areas for
pre-fabrication, assembly and inspection/testing - Safe and unobstructed access to the work face
e.g. scaffolding - Maximum use of mobile access devices such as
Cherry Pickers and scissor lifts - Safety, Health and Environment
68Construction Stage
- Project Management Procedures
- Planning
- Construction requirements in terms of design,
planning approvals, contracts, materials,
equipment services and documentation should be
built into the project plan from the earliest
practicable time. - Only in this way will it be possible for the
preceding stages (Development, design,
procurement) to organize their work so as to
produce constructable design packages and
constructable procurement packages - Construction plan should be based on the
requirements for pre-commissioning and
commissioning - Keep plan under review throughout the
construction period.
69Construction Stage
- Planning
- Only the minimum number of essential activities
on the critical path - Maximize benefits from prefabricated elements
- Plan construction of repetitive units as a
manufacturing process - Package work to allow multiple work fronts in
parallel - Plan construction sequence so as to meet
pre-commissioning and commissioning needs - Base the schedule on shorter time intervals i.e.
days or hours for critical tasks - Site access arrangement
- Establishment of site infrastructure
- Work permit provision
- Resource demands of the schedule recruitment,
induction, training - Move from area based to process system
- Commence construction based on early design
information - Key long lead and critical activities
- Contingency planning for critical activities
- Constructable work packages
- Deferment of non-essential items until late in
the program
70Construction Stage
- Project Management Procedures
- Project Control
- Control must be a dynamic process with very
short cycle time and include the following - Frequent monitoring of all trends in work
progress - Frequent monitoring of changes
- The use of simple progress indicator graphs
(S-curve) on a daily basis - Simple progress reports and easily available to
relevant people - Exception reporting of items not completed to
scheduled - Progress against deliverables, milestones, etc.
- Earned Value measurement
- Change Control
- Design changes are to be avoided
- If design change is essential, implement through
change control system - Resist verbal request at all costs
71Construction Stage
- Project Management Procedures
- Communications
- Communications should be
- Simple limited to what is necessary
- Pertinent
- Timely
- Using best available mechanism face-to-face
- Use of IT and 3D design tools to have a clear
understanding of the product - Enable all parties to work together with an
improved understanding of the design intent to
avoid delays arising from misunderstandings and
interdisciplinary conflicts
72Construction Stage
- Cost and Risk
- Mechanism for controlling costs through efficient
use of labour and materials and the avoidance of
rework including rectification of defective work - Strategies to achieve high productivity
- Multiple shift or night shift will add to cost
- It may be necessary for the client to provide
advance payment to enable contractors to commit
materials and resources ASAP. - Balance between risk and reward
73Construction Stage
- Logistics
- Design support for construction should be located
on site - If not possible then effective IT system should
be used to improve communications and enable
marked up drawings to be rapidly transmitted - Maintain the momentum of the construction site
and avoid the need to move site labour on to less
urgent work due to hold ups on the critical
activities - Procurement support should be provided and
include - Documentation covering both purchasing
transaction and documentation - Good receipt procedures
- Inspections requirements
- Quarantine of incorrect or defective goods
- Storage and conservation
- Handling and delivery to the work face
- Surpluses
- Returns of incorrect, defective materials and
equipment
74Key Issues
- With Fast Track
- Control is redefined from monitoring results to
making things happen - Performance is maximizing value and minimizing
waste at the project level - Value to the client is defined, created and
delivered throughout the life of the project - Coordinating action through pulling and
continuous flow as opposed to traditional
schedule driven push with its over-reliance on
central authority and project schedule to manage
resources and coordinate work - Decentralizing decision making through
transparency and empowerment (effective
communication)
75Key Issues
- Key organizational features include leadership,
teamwork and trust - The construction requirement is the basis for
planning the supply of design, documentation,
materials, equipment and resources - Providing the wrong goods or service the right
way is waste do the right project before you do
the project right - Project control is controlling the project, not
just retrospective monitoring - Good communication are needed to support decision
making - Eliminate ineffective time on site activities
- Significant attention to project with new
technology
76Managing Fast Track Projects A Guide and
Checklists
Thank You