Title: Paolo Guglielmini TS / CV / DC08th April 2005


1
BIDDERS CONFERENCE Invitation to Tender
3307 Supply and Installation of water cooling
equipment for the LHCb detector Technical
Specification
Paolo Guglielmini TS / CV / DC 08th April
2005
2
Main scopes of the work
  • construction of a cooling unit at demineralised
    water for the Outer Tracker sub-detector
  • 2. installation of
  • - supply/return transfer lines and distribution
    manifolds for the OT
  • - supports for pipelines on the RB84 side of
    the cavern
  • supply and installation of pipelines and
    equipments for primary water networks and
    compressed air line
  • control and electricity works for the OT
  • tests on hydraulic performances and control
    functionalities
  • commissioning, training and validation of both
    the OT and primary systems
  • supply of all required technical documents

Paolo Guglielmini TS / CV / DC 08th April
2005
3
Underground areas Point 8
Paolo Guglielmini TS / CV / DC 08th April
2005
4
Experimental cavern UX 85 Layout
5
LHCb detector Overview
6
Positioning of the platform
7
Passage around shielding wall
8
Transfer lines Passage through the TX84
9
Installation of supports for the pipelines
10
Outer Tracker distribution manifolds
Outer Tracker manifolds represented in light blue
11
Primary water systems on RB86 side
12
Primary water systems - Details
1. Connections to barracks D1 and D2 2.
Connections to barracks D3/A and D3/B 3.
Connections to cooling systems
1
3
2
13
Compressed air and demineralised water networks
RB84
  • the arrows indicate from where the existing
    pipelines have to be prolonged
  • in light blue on the RB84 side the demineralised
    water network
  • - in white on both sides the compressed air
    network

RB86
14
Outer Tracker Requirements
Pressure drop inside the detector (including all piping located after the manifolds) 1.5 bars
Flow rate 10 m3/h (flow to the detector) 1 m3/h (flow in the demineralization loop)
Inlet temperature 19 1 C
Temperature increasing inside the detector 2 C
Volume of coolant in the detector (including all piping located after the manifolds) 50 litres
Demineralised water conductivity 0.1 to 1 mS/cm
Cooling capacity 23 kW
CERN Mixed water network - Inlet temperature - ?T available - Inlet pressure - ?P available 13 C 5 C (!) 10 bar (a) 2 bar
Ambient conditions inside the cavern - Dry temperature - Dew point 17 to 27 C 12 C
Paolo Guglielmini TS / CV / DC 08th April
2005
15
Outer Tracker Principle Schema
Paolo Guglielmini TS / CV / DC 08th April
2005
16
Pipe works in the UX85 experimental cavern
  • Activities related to WORK LOT 1
  • fixation of the supports for 16 transfer lines
    (OT included) along the RB84 side and on top of
    the vault TX84
  • installation of the OT transfer lines in
    stainless steel (multilayer pipes use to be
    quoted as an option)
  • installation of the supply/return OT
    distribution manifolds
  • Activities related to WORK LOT 4
  • - installation of pipelines for chilled and mixed
    water (RB86), demineralised water (RB84),
    compressed air (both sides) networks, including
    supports and required equipments

Due to INTEGRATION matters the detailed
activities shall be scheduled and performed
during JUNE JULY 2005
Paolo Guglielmini TS / CV / DC 08th April
2005
17
Integration in the SCADA local supervision
IT 3307 Paragraph 4.2.2.1 Communication Four
additional cooling systems will also be locally
supervised and operated from the SCADA local
supervision platform. These cooling systems are
controlled by 3 PLCs, which are also built on
Schneider Premium TSX equipment. These PLCs are
not included in the scope of the supply of this
Technical Specification. 1 PLC Inner Tracker
- Tracker Trigger 1 PLC RICH 1 2 1
PLC VELO The Contractor shall integrate in the
SCADA local supervision platform database the
process data from these 3 external PLCs. The
Contractor shall develop, test, install and
validate on-site the local supervision means
corresponding to these external cooling
stations...
Provided commissioning of the cooling systems
whose PLCs shall be integrated end of FEBRUARY
2006
Paolo Guglielmini TS / CV / DC 08th April
2005
18
Provided delivery schedule
Contract signature April 2005 Design
Meeting May 2005 Pipe works in the UX85
cavern June July 2005 Complete installation
of the OT cooling station at Contractors
premises September 2005 Performance tests at
Contractors premises October 2005 Installation
of the unit in the cavern, connection to CERN
networks, tests, commissioning End
2005 Integration in the SCADA of the additional
cooling systems February 2006
Paolo Guglielmini TS / CV / DC 08th April
2005