Title: Belt Air Federal Advisory Committee Briefing
1Belt Air Federal Advisory Committee Briefing
- Ronald Reagan Building
- Washington, DC
- January 9-10, 2007
2Historical Background of Belt Air Rule
- 1985 Ventilation Rule Pre-proposal included use
of belt air - 1988 Proposed Ventilation Rule included use of
belt air Six public hearings - 1989 MSHA Belt Entry Ventilation Review Committee
reports Belt Air can be used safely with
precautions - 1990 Belt- Air Hearing takes place in Reston,
Virginia
3Historical Background of Belt Air Rule (cont.)
- 1991 Secretary of Labor forms Federal Advisory
Committee on Belt Air - 1992 Final ventilation rule excludes Belt Air,
defers to Advisory committee which concludes that
Belt Air can be used to safely ventilate working
faces provided certain conditions are met - Belt-Air Rulemaking is placed on the Regulatory
Agenda in 1992
4Advantages of Belt Air Use
- It allows quicker detection of combustion
- It represents a potential cost savings for new
mines because fewer entries would be needed,
resulting in lower mining and ventilation costs - Increases the efficiency of the ventilation
system - It can allow for greater quantities of air at the
face - When used to increase the total quantity of air,
it dilutes methane and respirable dust
5Belt Air Course Ventilation 75.350
- Belt air course cannot be used as a return air
course. - Retains requirements for separation from intake
and return entries with permanent ventilation
controls. - Allows use of belt air to ventilate sections as
long as certain requirements are met.
6Belt Air Usage Requirements
- Install, operate, examine, and maintain
Atmospheric Monitoring System (AMS) per
requirements in 75.351 - Training requirements
- Establish designated areas for dust monitoring
- Monitor primary escapeway for CO or smoke
- Sections must be developed with three or more
entries
7(No Transcript)
8(No Transcript)
9Point Feeding 75.350(c)
- Permitted with the following precautions
- Monitoring of point feed for CO or smoke
- Monitoring belt air course for CO or smoke
- Means to remotely close point-feed regulator
- Minimum velocity through point feed
- Location approved in mine ventilation plan
- AMS installed, operated, examined, and maintained
10Atmospheric Monitoring System 75.351
- (a) AMS Operation
- Establishes when an AMS must be operated and
when a designated AMS operator is on duty - (b) Designated surface location and AMS operator
- 1. Requires mine operator to designate surface
location - 2. Specifies duties and location of AMS
operator - 3. Requires schematic (map) of sensor locations
- 4. Requires names and method to contact key
personnel
11Atmospheric Monitoring System 75.351
- 75.351 (c) minimum operating requirements
- 1. Requires automatic signals on surface for
malfunctions - 2. Requires automatic alert signal on surface
- 3. Requires automatic alarm signal on surface,
at sections, and at other locations per approved
program of instruction - 4. Requires system to identify operational
status of all AMS sensors
12Atmospheric Monitoring System 75.351
- 75.351 (d) location and installation of AMS
sensors - 1. Addresses specific location within entry
- 75.351 (e) location of sensors belt air course
- 1. Specific location and spacing requirements
(1000 ft) - 2. Permits lower velocities with reduced
spacing (350 ft) - 3. District manager may require additional
sensors
13Atmospheric Monitoring System 75.351
- 75.351 (f) location of sensors primary
escapeway - 1. CO sensors required within 500 ft of section
- 2. CO sensors required within 500 ft of
beginning of panel - 75.351 (g) location of sensors return air
splits - 1. Addresses location of methane sensors
- 75.351 (f) location of sensors electrical
installations - 1. Requires specific locations for CO and smoke
sensors installed to comply with 75.340
14Atmospheric Monitoring System 75.351
- 75.351 (i) establishing alert and alarm levels
- 1. Establishes alert and alarm levels for
methane, CO, and smoke sensors - - for methane 1.0 and 1.5 percent
- - for CO 5 and 10 ppm
- - for smoke optical density of 0.022 per meter
- 75.351 (j) establishing CO ambient levels
- 1. Method and level approved in ventilation plan
15Atmospheric Monitoring System 75.351
- 75.351 (k) installation and maintenance
- 1. Requires system to be installed and
maintained by trained personnel and maintained in
proper operating condition - 75.351 (l) sensors
- 1. NRTL or Secretary Approval
- 75.351 (m) time delays
- 1. Permits time delays to be used up to three
minutes if a demonstrated need exists - 2. Approved in ventilation plan
16Atmospheric Monitoring System 75.351
- 75.351 (n) examination, testing, and calibration
- 1. Visual exam of system required each shift
- 2. Functional test of alarms required every
seven days - 3. Calibration of sensors required every 31
days - - In accordance with manufacturer specs
- - Concentration sufficient to activate alarms
- - Cal gas certified traceable to NIST standard
17Atmospheric Monitoring System 75.351
- 75.351 (o) recordkeeping
- 1. Records required for
- - Alerts and alarms, malfunctions, seven-day
test, calibrations, maintenance performed - 2. Person entering record must include
- - Name, title, date, and signature
- 3. Establishes AMS Log
- - Can be book or computer file
- 75.351 (p) retention period
- 1. One year available to miners and MSHA
18Atmospheric Monitoring System 75.351
- 75.351 (q) training
- 1. AMS operators must be trained annually
- 2. Record must be maintained for one year
including - - Content of training
- - Person conducting training
- - date of training
- 75.351 (r) communications
- 1. A voice communication system and the AMS
system must be installed in separate entries
19Required Responses 75.352 (a)
- 75.352 (a) (1) alerts
- 1. Notification of appropriate personnel by AMS
operator - 75.352 (a) (2) alarms
- 1. Notification of appropriate personnel
including miners working on working sections and
other locations
20Required Responses 75.352 (b)
- 75.352 (b) (1) alerts
- 1. Identify sensor and initiate investigation
- 75.352 (b) (2) alarms
- 1. Identify sensor and initiate investigation
initiate fire fighting and evacuation procedures
21Required Responses 75.352 (c) and (d)
- 75.352 (c) methane sensors
- 1. identify sensor
- 2. examination
- 3. actions required under 75.323
- 75.352 (d)
- 1. Immediate actions to return system to proper
function - 2. Establishes procedures to manually monitor
belt air course while continuing belt operation
22Ventilation Plan Requirements 75.371
- Add six requirements subject to ventilation plan
approval - Designated area (DA)
- Location of point-feed regulators
- Additional CO sensors in belt air course if
required - Time delays
- Reduced alert and alarm settings
- Alternate instrument alert and alarm levels for
monitoring under 75.352
23Mine Ventilation Map 75.372
- Location and type of all required AMS sensors
24Escapeways 75.380
- Addresses the use of point feeding
25Costs
- The belt air rule is an alternative means of
compliance as such, it is almost of necessity a
cost savings to the mining industry - Cost savings primarily from
- Reduced air horsepower requirements
- Delaying some shaft sinking costs
- Eliminating costs of filing and litigating
petitions for modification of the existing
standard
26Safety Benefit
- This rule requires the use of technologically
superior AMS - These systems provide early-warning fire
detection - This capability will save lives and mine property
- Using belt air with AMS fire detection technology
can provide mine operators with ultimate cost
savings the detection of fires before
significant damage occurs possibly avoiding
costs of sealing and mine recovery or permanent
mine closure due to a serious fire.
27Overview of Compliance Guide
28Introduction
- The rule allows all mine operators the option of
using belt air as intake air - As of June 1, 2004, all granted petitions for
modification (except in mines using two entries)
to use belt air were superceded by this rule
29Who can be an AMS operator?
- The AMS operator must be properly trained and be
knowledgeable about the operation of the AMS
according to 75.351 (q) - The AMS operators performance is critical in
safely using belt air to ventilate working
sections and setup and removal areas
30Who are appropriate personnel?
- Appropriate personnel will be different
individuals depending on the type of signal and
the location where the signal originates
31What is a belt air course?
- The entry in which a belt is located and any
adjacent entry not separated from the belt entry
by permanent ventilation controls, including any
entrees in series with the belt entry,
terminating at a return regulator, a section
loading point, or the surface
32What is the carbon monoxide ambient level?
- The average concentration of carbon monoxide
detected in an air course - This average is representative of the composition
of the mine atmosphere over a period of mining
activity during non-fire conditions - Separate ambient levels may be established for
different areas
33What is point feeding?
- The process of providing additional intake air to
the belt air course from another intake air
course through a regulator - A minimum air velocity of 300 fpm must be
maintained through the point-feed regulator - The use and location of all point feeds must be
approved in the ventilation plan
34Point Feed Example
35How are the detection systems and fire
suppression systems treated in this rule?
- 30 CFR 75.350 (a)(2) requires that air velocities
must be compatible with all fire detection
systems and fire suppression systems used in the
belt entry
36Sensor Spacing
37Alert and Alarm Levels and Ambient Levels
- All alert and alarm levels are set at 5 and 10
ppm above the ambient level - The MSHA District Manager may require lower
levels depending upon local mine conditions - Use of diesel-discriminating sensors will reduce
alerts and alarms caused by diesel equipment
38Time Delays
- Time delays are permitted when a demonstrated
need exists and the delay is approved in the mine
ventilation plan - Determination of the length of time delays is
dependent upon conditions at the mine - In any case, the maximum time delay allowed is
three minutes
39AMS Sensors, Examination, Testing, and Calibration
- Visual examinations once each shift
- Records of hazardous conditions found must be
kept - All alarms functionally tested once every seven
days - Functional test requires calibration gas be
applied to activate alarms - Any other method used must be equally effective
- The AMS operator must be notified prior to
testing, calibration, or alarm activation
40AMS Sensors, Examination, Testing, and Calibration
- The AMS operator must notify miners on the
affected sections - Calibration intervals not to exceed 31 days
- Calibration gas must be traceable to NIST
standards - Calibration gas must be within () or (-) 2.0
percent of the indicated gas concentration - Calibration and testing must be performed by
properly trained persons
41Recordkeeping Requirements
- Computer printouts
- Hand-written notations
- Pre-printed forms
- Electronic records
- Record must not be susceptible to alteration
- Record must be kept separately from other records
and identified as the AMS Log - Retain records for at least one year at a surface
location at the mine and made available for
inspection by miners and authorized
representatives of the Secretary
42Actions in Response to AMS Signals
- AMS operator must immediately respond to AMS
signals and notify appropriate personnel - In addition, in the event of an alarm from a
single sensor or an alert from two consecutive
sensors, the AMS operator must immediately notify
appropriate personnel which may include the
responsible person - Affected underground personnel must be withdrawn
to a safe location as identified in the program
of instruction required under 75.1502 - Actions must be appropriate for the type of
signal received
43Thank you
- Michael G Kalich
- Senior Mining Engineer
- MSHA