Title: H
1HP 206 / Bullwinkle 5/9/06 Hydrocarbon Release
- Investigation Team
- Sponsor Joe Leimkuhler
- Team Leader. Martin Baltus
- MembersMarc Gatlin Eddie Hattier
2crane
Tote initially here
ESD
Broken Nipple
Tote going here
Area of Spray
3Sequence of Events and Casual Factors/Conditions
215 (20 spray) While lowering tote it
strikes valve on heat exchanger resulting in
broken nipple release of HCs
Rigged up and began moving tote tank using two
riggers to make room for toolbox
Lead roustabout (crane operator) assigned to move
Halliburton toolbox
Lead roustabout surveys area and prepares JSA
- Toolbox needed to prep Halliburton unit for next
job - Tote blocking fire extinguisher
- - Valve was not in view of crane operator and
riggers did not see it - Crane operator felt the load hit moved it up
out of way - Both taglines were not positioned diagonally on
load possibly due to crowded conditions - Wind conditions 15 knots w/ 22 knot gusts,
non-issue - - Riggers evacuated area of HC spray
- Deck crew was one person short for about a week
- Crew decided not to use DSP (reoccurring
problem) - Experience levels
- Crane operator 10 mos
- Riggers 3/9 mos
- Tote sitting in area where toolbox needed to be
set - Generic JSA did not require DSP and was not
updated to include hazard of appendages on
production equipment - Lead roustabout decided on where to move tote
after consultation with construction personnel
but not production personnel
4Sequence of Events and Casual Factors/Conditions,
continued
216 219 (20 spray) Shell subsea operator
responds to site and notices GIS deck foreman in
process of closing outlet valve to heater treater
thus he closes inlet
215 (20 spray) Rigger notifies construction
hand who in turn reports incident to Production
via Giatronics
219 (firewater on release) Subsea operator
calls for assistance and speaks to Process Staff
Associate, PSA
GIS employees attempt to ESD platform
- Construction were preparing hooch in area
- PSA notifies Shell Drilling Foreman by phone and
OIM when passing in hallway
- Construction HSE Tech instructs not to ESD until
PIC is on scene - Construction HSE Tech did not receive typical
contract construction HSE Tech orientation
- Subsea operator heard report of release on radio
- No gas detector at scene throughout incident
- Mechanic directs fire hose on to HC spray
- Drilling in cased hole
5Sequence of Events and Casual Factors/Conditions,
continued
247 (no flow) As flow diminishes and finally
stops a ladder is used to remove bushing
222 225(firewater on release) PSA arrives on
location and closes inlet and outlet hot water
valves
227 230 (firewater on release) PSA calls OIM
and he arrives on scene
Operator closes FWKO per instruction of PSA
- Subsea operator brakes off valve assembly
- Reliability engineer attempts to bleed oil from
bulk tank but turned wrong valve (gas outlet) - Flow starts again within seconds of removing
bushing
- Reliability engineer arrives on scene
- OIM discusses ESDing and verifies that Drilling
Foreman had been contacted - Production personnel realized gas was breaking
out of oil but did not manage as a gas release
(no visible cloud present) - OIM returned to LQ to retrieve PIds and then
returns to area.
6Sequence of Events and Casual Factors/Conditions,
continued
255 (no flow) Stab replacement valve assembly
and shut off
247 ( 20 for lt60 sec) Second flow begins and
stops in 1 2 minutes
300 Return to normal production flow
- Reliability engineer gets sprayed with HC
- Fire hoses onto spray
- OIM discusses ESDing
- All oil was captured in skid pans below
- Washed down area
7What Should Have Happened?
- Contractors
- move out area of immediate danger
- notify Production Operations Personnel
- pull ESD
- Production Operator arrives on scene
- pull ESD and initiate ICS
- PSA/PIC arrives on scene
- pull ESD and Blowdown?
- Why ESD and Blowdown
- Uncertainty existed
- Ignition source
- Was it properly isolated
- Risk of spill identified
- Reduce the inventory
8Managing Incident Escalation ByMinimizing
Hydrocarbon Inventories
Scenario 1
- Likely Consequence Limited asset
- damage and no major injuries
9Managing Incident Escalation ByMinimizing
Hydrocarbon Inventories
Scenario 2
- Response wo/ ESD Blowdown
- Potential Consequence Severe
- asset damage and possible
- loss of life
Hydrocarbons from wells
Hydrocarbon from pipelines
10Root Causes (RC) / Conclusion (C)
- RC Elimination of EEP boat and loss of use of
Boxer created tote tank storage problems - RC Hazards created by the storage area were not
identified and mitigated or were identified and
not mitigated. - C Some of the other appendages in this area
would result in a larger release if damaged,
i.e., release of the majority of the contents of
the bulk oil tank. - RC High demand on personnel coupled with the
shortage on HP crane crew made it easier to run
crane without a DSP. - RC Construction HSE Technician prevented
activation of ESD. - C Although the production personnel understood
gas vapors were present as the oil was released
the response was not aligned with the Shells
expectations. - C Expectations for Responding to a Gas Release
or Leak does not address oil releases or leaks. - C The sequence of events do not suggest that the
incident was managed as an ICS event. - RC There is no established requirements for a
structured ICS plan for non-TLP locations.
11Recommendations
12Recommendations