Title: HEALTH PRIVATE FINANCE INITIATIVES PUBLIC PRIVATE PARTNERSHIP
1HEALTH PRIVATE FINANCE INITIATIVESPUBLIC PRIVATE
PARTNERSHIP
- Consultancy Support
- Ian Stewart Healthcare Projects Director
2INTRODUCTION
- The PFI process / Consultancy Support
- Structure of Teams involved in PFI
- Atkins Experience
- Learning from PFI
- Quality Assessment Protocols
- Key Criteria for Success
3THE STRUCTURE OF TEAMS INVOLVED IN PFI PROCESS
- Public Sector
- Project Director
- Project Team
- Technical Advisers
- Legal Advisers
- Financial Advisers
- Independent Certifiers
- Private Sector - Consortium
- Special Purpose Vehicle
- Design Construct Contractor
- Design Team
- Facilities Management Operator
- Debt providers
- Insurance Advisers
- Equipment Specialists
- Legal Advisers
- Finance Advisers
- Due diligence teams
4THE PFI PROCUREMENT PROCESS
- Public Sector Bid Consortium
- Strategic Outline Case Public Sector -
- OJEU Technical Advisors Public Sector -
- Outline Business Case / PSC Public
Sector/Advisers - - OJEU - Procurement Public Sector -
- Preliminary Invitation to Negotiate Advisers/Publi
c Sector Designers - Bidders invited to respond to PITN Public
Sector/Advisers Designers / Due Diligence - Assessment of PITN responses Advisers/Public
Sector - - Shortlist invited to respond to FITN
Advisers/Public Sector Designers / Due Diligence - Assessment of FITN responses Advisers/Public
Sector - - Identification of Preferred Bidder Public
Sector - - Financial Close All Designers / Due Diligence
- Construction Advisors / Independent Certifiers
Designers / Due Diligence - Commissioning Advisors / Independent Certifiers
Designers / Due Diligence
2 years
5THE STRUCTURE OF TEAMS INVOLVED IN PFI PROCESS
6CLIENT ADVISOR ROLE, TECHNICAL ADVISOR OBC
- Development Control Plan
- Operational Policies
- Functional Content
- Departmental Relationships
- Design Philosophy
- PSC Design development
- Risk Assessment
7CLIENT ADVISOR ROLE, TECHNICAL ADVISOR PFI
- Interface with bidders
- Co-ordination of Approval Processes
- Review, comment and contribute to the drafting of
the ITN documentation - Preparation of the Health Safety Pre-Tender
Plan - Develop and agree bid evaluation criteria (based
on AEDET and NEAT)
8CLIENT ADVISOR ROLE, TECHNICAL ADVISOR PFI
- Clarify Bidders queries
- Attend Bidders presentations
- Seek clarification of any items arising from the
Bidders submissions - Review Bidders responses at the end of each
stage and evaluate - Assist during negotiations and participate in
selection of preferred bidder.
9DUE DILIGENCE
- Undertaking a review of the bidders proposals
and comparing against the ITN documents - Joint appointment between the SPV and funding
institutions - Undertaken by health planners, architects,
engineers and cost advisors - In the region of 0.1 of capital value of the
project - Highlighting where derogations identified by the
bidder - Protecting the funders investment
10INDEPENDENT CERTIFIER (I. C.)
- Joint appointment of technical expertise awarded
by procuring body and SPC - Independent Certifier will provide a range of
expertise including health planning,
architecture, engineering and costs - Role is to ensure that the facility delivered by
the DB contractor meets the Employers
Requirements - The I. C. is responsible for certifying Hospital
Availability Date (H.A.D.) - It is a very responsible and a high risk role as
all the payment mechanism kicks-in once H.A.D. is
certified.
11TECHNICAL ADVISORS
Glasgow ACADs- Technical Advisory Services
including Medical Planning, Architecture,
Building Services Engineering, Civil / Structural
Engineering and Cost Consultancy. Project Value
180m. Royal Edinburgh Hospital- Full
Technical Advisory services for 70m provision of
Mental Health facilities for East
Scotland. Dumfries and Galloway NHS Trust
Maternity and Day Surgery Unit- Medical Planning
and Technical Advisory service for 72m extension
to DGRI. South Manchester NHS Trust- Technical
Advisers for proposed Cardiac Care Unit at
Wythenshawe Hospital Hairmyres Hospital-
Medical Planner for replacement DGH
12DUE DILIGENCE
Barts and Royal London 850M (
1200M) University Hospital Coventry
Warwickshire 300M ( 420M) Derby Royal
Infirmary 250M ( 1200M) Manchester Royal
Infirmary 450M ( 350M) Bishop Auckland
Hospital 60M ( 85M) Sedgefield Community
Hospital 20M ( 30M)
13LEARNING FROM PFIFORM OF CONTRACT
- Early PFI deals delayed by bespoke contracts
- Standardisation of PFI Contracts. Revised and
updated in July 2002 August 2003. - Reduction in time and costs of negotiation
- Clarity of understanding of risks
- Consistency of approach in market
- Early PFI schemes were criticised
- Poor design quality
- Lowest cost solutions
- Inappropriate responses to urban context
- Lack of delight for users
- Since 2002 much greater emphasis on design
quality - Commission for Architecture and The Built
Environment. - Promotion of higher standards of design for
public buildings - Use of The Design Development Protocol for PFI
Schemes August 2004
14QUALITY ASSESSMENT PROTOCOLS Achieving
Excellence Design Evaluation Toolkit (AEDET
Evolution)
- AEDET Achieving Excellence Design Evaluation
Toolkit - A tool for evaluating the design of healthcare
buildings from initial proposals through to
post-project evaluation - Assists clients in developing design
specifications for their schemes - Provides a methodology for evaluating and
assessing the design of healthcare proposals - Assists in approval role
- Basis for a national benchmarking system of
design quality for healthcare buildings - Assessment of
- Functionality
- Impact
- Building Standard
15QUALITY ASSESSMENT PROTOCOLS Achieving
Excellence Design Evaluation Toolkit (AEDET
Evolution)
- Functionality
- Use
- Access
- Spaces
- Impact
- Character and Innovation
- Citizen satisfaction
- Internal environment
- Urban and social integration
- Build Standard
- Performance
- Efficiency
- Construction
- Assists in auditability of decision process
16QUALITY ASSESSMENT PROTOCOLSNEAT (NEAT)
- NEAT NHS Estates Environmental Assessment
Toolkit - A self-assessment environmental review tool
covering environmental and social issues - Used for specifying, estimating and monitoring
environmental performance - Issues covered
- Management
- Energy
- Transport
- Water
- Materials
- Landuse and ecology
- Pollution
- Internal environment
- Social operational waste
17Key Criteria for Success
- Avoidance of ambiguities in Employers
Requirements with clarity of specification
requirements - Clear Communication Routes with single points of
contact - Realistic timetable
- Robustness of affordability before going to the
market-place - Application of the Design Development Protocol
- Appointed consultants and bidders must genuinely
understand, and have significant experience of,
the design and operation of healthcare projects.