Title: The role of I
1The role of IC systems in power uprating
projects
2Why to uprate?
- Market changes induce the claim to operate the
plants in an ever increasing efficiency. - Efficiency can be increased either by a better
utilization of existing capacities or by
increasing the capacities. - The utilities are aiming for additional
production through the better utilization of
available assets. - Gaining public acceptance to increasing existing
nuclear power plant capacity is significantly
easier than that to constructing a new NPP.
3Conditions enabling power uprating
- The average age of the nuclear units operating
for the time being is above 20 years. - The units were designed in the mid-seventies.
- Today, there is a more accurate knowledge on the
behavior of structural materials and integrated
effects of external and internal factors exerted
on the components. - Today demands affecting components during
transients can be defined more exactly,
uncertainties of calculations can be reduced,
and, as a result, the conservatism applied in the
original design can be reduced. - Today more accurate and reliable control and
assessment methods are available (accuracy of
measurements, reduction of detection thresholds,
etc) - Knowledge related to nuclear fuel and core
thermal hydraulics also had a considerable
development. Fuel utilization arose to one and a
half times of that in the eighties.
4Definition of power uprate
- The process of increasing the maximum licensed
power level at which a commercial nuclear power
plant may operate is called a power uprate.
(Definition from the U.S. NRC) - Types of power uprates
- measurement uncertainty recapture power uprates
- stretch power uprates
- extended power uprates
5Basic ways of power uprating
- Reducing uncertainty
- Improving efficiency
- Increasing thermal power
6Measurement uncertainty recapture uprates
- The reactor thermal power is validated by the
nuclear steam supply system energy balance
calculation. - The reliability of this calculation depends
primarily on the accuracy of feedwater flow,
temperature, and pressure measurements. - Because the measuring instruments have
measurement uncertainties, margins are included
to ensure the reactor core thermal power does not
exceed safe operating levels. - 10 CFR, Part 50, Appendix K (1973), required
licensees to assume a 2.0 percent measurement
uncertainty for the reactor thermal power. - The current rule (2000) allows licensees to
justify a smaller margin for power measurement
uncertainty when more accurate instrumentation is
used to calculate the reactor thermal power.
7Measurement uncertainty recapture uprates 2.
- Measurement uncertainty recapture (MUR) power
uprates are achieved by implementing enhanced
techniques, such as the improved performance of
plant equipment both on the primary and secondary
side, protection and monitoring system, operator
performance, etc. These uprates are less than 2
measured in electrical output power. - The use of state-of-the-art feedwater flow
measurement devices that reduce the degree of
uncertainty associated with feedwater flow
measurement can be an example.
8Measurement uncertainty recapture example
9Stretch power uprates
- Uprates are typically up to 7-percent and are
within the design capacity of the plant. The
actual value for percentage increase in power a
plant can achieve and stay within the stretch
power uprate category is plant-specific and
depends on the operating margins included in the
design of a particular plant. - Stretch power uprates usually involve changes to
instrumentation setpoints, but do not involve
major plant modifications. This is especially
true for boiling-water reactor (BWR) plants. - In some limited cases where plant equipment was
operated near capacity prior to the power uprate,
more substantial changes may be required.
10Extended power uprates
- Extended power uprates are greater than stretch
power uprates and are usually limited by critical
reactor components such as the reactor vessel,
pressurizer, primary heat transport systems,
piping etc., or secondary components such as the
turbine or main generator. To cope with these
limitations, extended uprates usually require
significant modifications to major
balance-of-plant equipment such as the
high-pressure turbines, condensate pumps and
motors, main generators, and/or transformers.
Extended power uprates have been approved for
increases as high as 20 percent.
11Power uprates and IC
- Necessary modifications in the instrumentation
and control systems in relation to power
upratings are usually not very substantial. The
following preconditions must be fulfilled in the
frame of IC - sufficient measurement ranges
- sufficient accuracy of process parameter
measurements - sufficient calculation algorithms to indicate
credible reactor thermal power - sufficient possibilities for the adaptation of
new limit values in the Reactor Protection
System, limitation systems and control systems
12Typical examples of IC changes
- Modification of specific control systems to
enable operation under different conditions. - Inclusion of additional process sensors
- Replacement of sensors by ones with improved
accuracy - Optimised calculation of the measurement
uncertainties permitting a reduction in the
margin applied to the measurement of reactor
thermal power. - Modification of the reactor protection system
setpoints - Changes in the appropriate HSIs to accurately
assess the current state of the plant - Changes in alarm setpoints
- Changes in the instrument calibration procedures
- Adjustment of the plant computer and safety
parameter display system - Development of additional instrument validation
processes
13Power Uprating inthe Paks NPP
14Early activities (uprate from 440 to 465 MW)
- High Pressure Turbine
- Blades of all stages of the High Pressure Rotor
the 1st stage excepted were exchanged. - From the diaphragms in the HP housing, stages No.
5 and 6 were exchanged. As for the diaphragms of
stages No. 2, 3 and 4, only the projections above
the bandage were replaced. - Final (end) - and diaphragm sealing were
exchanged from flat springs to spiral ones. - Low Pressure Turbine
- Blades of rotor stages No. 1, 2, 3 and 4 were
exchanged. - From diaphragms of LP housing, those of stages
No. 1, 2, 3 and 4 were exchanged. - Having the steam separator exchanged, steam
intake of the LP housing was modernized. - Final (end) - and diaphragm sealing were
exchanged from flat springs to spiral ones. - Took place from 1997 to 2001
15The replacement of the turbine rotor
16Modifications for the new, 8 power uprating
- New fuel
- Primary circuit
- Core monitoring (VERONA)
- Secondary circuit
- Electrical systems
- IC systems
- No feedwater flow measurement problems
17The specific modifications
18The specific modifications (contd)
19The new encased bus bar for Units 1 and 2
20The new encased bus bar for Units 1 and 2
21Implementation of power uprating in Paks
- The first modified fuel was loaded in 2005 in
Unit 4 (one third of the core). In 2006, when the
Unit 4 reactor contained two loads of the
modified fuel, the 108 power could be attained. - The stepwise increase of power, however, required
a test run at about 104 for several months
thus, the further increase up to 108 took about
four months from the unit restart, and was
reached on 28 September, 2006. - As for Units 1-3, operation of the fuel
assemblies that are suspected to contain deposits
will be terminated probably in 2006 in Unit 1,
and in 2008 in Unit 2. Power uprating in a core
loaded with fuel assemblies with deposits is not
considered.
22Main parameter changes after power uprating
23Primary circuit pressure control improvement
24Physical parameters limiting thermal power
- Maximum allowable temperature at the core
sub-channel outlets 325 oC - Corresponding primary circuit pressure 120,57
bar
25The saturation temperature and pressure
bar
0C
26The saturation temperature and pressure
bar
Real operating temperature
0C
27Characteristic of the old pressure controller
28Primary circuit pressure at a regular weekend
29Physical parameters limiting thermal power
- As a result of power increase, the core outlet
temperature increases, nearly proportionally with
the power increase, thus it gets nearer to the
saturation temperature. - The primary circuit pressure control system must
ensure a finer maintenance of the primary circuit
pressure, the margin of saturation shall be kept
at the required level. - The operating pressure must be maintained at a
stable 123.0 bar with an accuracy of /- 0.25 bar.
30The saturation temperature and pressure
bar
Real operating temperature
0C
31The saturation temperature and pressure
bar
Real operating temperature
0C
32Static characteristic of the new controller
33The structure of the new system
Pressurizer vessel
FieldPLC-1 (WAGO 750)
Injection valves-1
Pressure transmitter (Rosemount 3051)
FieldPLC-2 (WAGO 750)
Injection valves-2
FieldPLC-3 (WAGO 750)
Solid state switch
Electricalheaters
Network switch (Hirschman)
Process computer-1
Process computer-2
Supervisor Notebook
34The main controller
35Electrical heater solid state controller
36The injection valve controller
37IAEA TECDOC onThe Role of IC Systemsin Power
Uprating Projectsin NPPs
38IAEA TECDOC
39TECDOC contents
- Introduction to power uprating
- Limits, margins and their relevance to IC
- Calculation of thermal power
- Impact of power uprating on plant IC
- Human and training aspects
- Regulatory aspects
- IC implementation guidelines for power uprating
- IC benefits and lessons learned from power
uprating - Key recommendations
- References
- Glossary
- Country reports
40Key recommendations
- It is important to fully understand the safety
and technical bases for the claimed margins and
limits. - It is important to fully evaluate the areas of
potential measurement uncertainty. - Power uprates could potentially lead to various
unwanted effects. It may be necessary to add new
instrumentation to ensure that the operating
conditions at the higher power level are
adequately monitored and controlled. - A power uprating could provide the opportunity
for a wider modernisation of the plant IC
systems. - A comprehensive analysis should be undertaken
covering all aspects of plant behaviour in all
operational modes to provide input for the
modified IC design. - It is important to consider the changed (possibly
more severe) operating conditions for IC
equipment, qualification, etc.
41Key recommendations (contd)
- Particular attention should be paid to the design
of the HSI modifications (if any), and of
integration of this with the existing HSI, to
ensure that operating staff performance is
enhanced rather than degraded. - In terms of the licensing application for a power
uprate project, it should be noted that the
Regulatory Authority will require the licensing
submission to positively demonstrate that the
existing safety level has been maintained or
preferably increased, including all the IC
aspects and consequences of it. - Experience feedback from past power uprate
projects has shown that some plants have incurred
serious problems with their implementation (e.g.
inadvertent violation of licensed power limits),
due to instrumentation issues. Lessons learned
from other PU projects should be considered.
42Thank you for your attention!
43(No Transcript)