Further Steps Along the Road Steps 15,16,17 - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Further Steps Along the Road Steps 15,16,17

Description:

Lighting system replacements. Steam Trap Replacements. Process Equipment Replacements ... info_at_secondsighttechnical.com. Tel: 087 2542969. Take Action ! www.sei. ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 29
Provided by: AlR9
Category:

less

Transcript and Presenter's Notes

Title: Further Steps Along the Road Steps 15,16,17


1
Further Steps Along the Road Steps 15,16,17
  • Liam Tolton
  • Second Sight Technical

2
Topics
  • Show me the Money
  • Revision of the Register of Opportunities
  • The Savings Register
  • Where Does all the Energy Go ?
  • The Significant Energy Users
  • Keeping your Eye on the Ball
  • An introduction to Monitoring
  • Workshop
  • What is your Site EPI ?
  • Write Your Elevator Speech

3
Show me the Money STEP 15 Revision of Register
of Opportunities from Step 9
  • Information for the Savings Register comes from
    the Register of opportunities
  • Information Common to all Projects
  • Revision Number / Date
  • Assumptions e.g. Energy Costs / CO2 Emissions
  • Project Specific Information
  • EVERY project idea / energy saving opportunity
    should be on the savings register
  • Project Categories
  • Housekeeping Actions (little or no capital)
  • Investment Projects
  • Small to Medium Investment
  • Large Investment Items

4
Data and Assumptions
  • Document Control
  • Revision Date
  • Person responsible for the update
  • Energy Cost Data
  • Electricity Price
  • Gas/Oil Price
  • Volatile Pricing
  • Suggest you agree a Standard Price for Budgeting
    Purposes
  • Consult with Company Accountant

5
Register of OpportunitiesStep 9Template
available on Website
6
Project Specific Information
  • Project Title
  • Person Responsible
  • Latest Estimate of Savings
  • kWhrs
  • M3 of Gas
  • Tonnes of Oil
  • EUROS based on Standard Costs
  • Quantify other financial benefits
  • e.g Reduced Maintenance
  • Latest Project Cost Estimate
  • Estimate of Simple Payback Period
  • Project Cost / Annual Savings

7
Project Cost Estimate
  • Make the Project Cost as INCLUSIVE as possible
  • Design Costs
  • Capital Equipment Cost
  • Installation Cost
  • Removal of Redundant Equipment
  • Impact of Residual Book Value (Negative Impact)
  • Allowance for Salvage value (Positive Impact)

8
Schedule Information
  • Include a REALISTIC Start Date
  • Pre Approval Evaluation Period
  • Approval Date Milestone
  • Specify a REALISTIC Project Completion Date
  • Keep a separate Schedule for Each Project with
    Milestone Dates
  • Design Completion
  • Procurement Completion
  • Equipment Delivery
  • Installation Completion
  • Commissioning Completion
  • Start Up

9
The Savings RegisterTake Action Step 15
  • Monthly Estimate of Planned Savings for each
    initiative /project
  • Updated Regularly
  • Information Comes from Monitoring Programme
  • Energy Bills
  • Meter Readings
  • Savings Estimates
  • For the savings register use ACTUAL costs
  • Include a Cumulative Column

10
(No Transcript)
11
Graphical Portrayal
  • Advantages
  • Clear Representation of Progress
  • Trends can be seen immediately
  • Corrective Action can be taken immediately
  • Effects of Corrective Action should be clear
  • May be posted on notice boards

12
Graphical Savings Register
13
Key Attributes of a Good Savings Register
  • Complete ALL projects included
  • Up to Date Regularly Revised
  • Accurate Based on Good Input Data
  • USED TO STIMULATE ACTION
  • Corrective Action
  • Assign a Person Responsible for Corrective Action
  • Investigate Deviations Promptly
  • Report Back Quickly
  • Monitor Success of the Corrective Action

14
Challenges
  • Changing Times
  • Energy Price Volatility
  • Use LATEST Prices
  • Data Accuracy
  • The Greatest Challenge
  • No Easy Answer
  • MEASURE as much as possible
  • Justification for M T Project
  • Base ESTIMATES on Measurement / Good Science
  • Corrective Action Follow up
  • Assign a person to follow up deviations from the
    norm
  • Monitor the Success of Corrective Actions
  • WALK the plant !!

15
Where does all the Energy Go ?Step 16
Significant Energy Users
  • By now everyone will KNOW their Significant
    Energy Users
  • But.
  • HOW WELL do you know yours ?
  • Is it like a Nodding Acquaintance?
  • Do you only know how much energy they use ?
  • Is it like a Close Friend ?
  • Do you know how much it REALLY costs to own the
    item ?

16
The LIFE Cycle Approach
  • Each Energy User has a Life Cycle
  • Cradle to Grave .
  • Even before the Cradle comes
  • Conceptual Design
  • Detailed Design
  • Procurement
  • Installation
  • Operation
  • Maintenance
  • Retirement
  • At ALL stages there are potential pitfalls and
    opportunities

17
The Life Cycle Approach
  • Conceptual Design
  • The most fundamental choices
  • Often rushed
  • Rarely does Energy Play a part in this decision
  • Lobby to get Energy Considered by asking about
  • Choice of Technology
  • Choice of Energy Source
  • Establish Life Cycle Costs early in the process

18
Detailed Design Procurement
  • Major Equipment usually selected NOW
  • Assess Design Options for Energy Impact
  • Is there a Green Purchasing Procedure in place ?
  • Will energy use be evaluated as part of
    Competitive Tendering Process.
  • Does the detailed specification include an Energy
    Performance Specification ?
  • Are buildings included in the Energy Performance
    Specification?

19
Installation
  • Is Energy management considered in the
    Installation Phase ?
  • Full Thermal Insulation installed before start
    up?
  • Easy Access to equipment energy monitoring ?
  • Critical Data readily available on BMS system?
  • Budget for Energy Consumption during
    Commissioning?

20
Equipment Operation
  • Operate equipment at Optimum Performance
  • Are operators trained to know what optimum
    performance is ?
  • Is there potential for variability among
    operators?
  • Is there an Standard Operating Procedure?
  • Ensures consistency between operators
  • Maintains Optimum Performance.

21
Equipment Maintenance
  • Regular equipment inspection
  • By operators
  • By Trained Maintenance Personnel
  • Regular Preventive Maintenance Regime
  • Are Energy Consumption Checks built into PMs?
  • Examples include
  • Motor Efficiency Checks
  • Thermal Efficiency Checks
  • Steam Trap Testing
  • Compressed Air /Steam Leak Detect Repair
  • (Monitored / corrected at Shift Supervisor/Shift
    Technician Level)

22
Equipment Retirement
  • Dont be Afraid to retire early .
  • NO Not YOU, the equipment .
  • Technological Progress may make Early Retirement
    Attractive
  • Lighting system replacements
  • Steam Trap Replacements
  • Process Equipment Replacements
  • VSD improvements
  • Consider the higher cost of maintaining older
    equipment

23
Introduction to Energy Performance Indicators
(EPIs)Step 17 Monitor
  • What is an EPI ?
  • A means of Comparison of Performance versus a
    standard
  • Internal EPI
  • e.g. compare one machine or line against another
  • External EPI
  • Compare two sites against each other
  • Compare sites against a Best Practice Site
  • Compare sites against a selection of similar
    sites.

24
Two Approaches
  • Best Practice
  • Usually an External Comparator
  • Relies on independent accurate assessment of best
    practice sites
  • Past Performance
  • Usually an Internal Comparator
  • Relies on gathering good measurement data for
    comparison

25
Overall Site EPI
  • An overall site EPI is very useful
  • Keep it Simple
  • Ensure it is easily measured
  • Communicate it to everyone on site
  • The Simplest EPIs are
  • Units of Energy per unit of Output
  • Cost of Energy per unit of Output
  • Can be used in your ELEVATOR SPEECH

26
Workshop
  • 1. Does your site have an EPI?
  • If so
  • What is it ?
  • How do you measure it?
  • How often is it measured?
  • How do you communicate it?
  • 2. Write your Elevator Speech for the Energy
    Team.
  • You have 30 seconds to tell the CEO about your
    EM programme.
  • What are the main points you need to convey?
  • What is he/she interested in hearing?
  • Ensure it answers these four questions
  • What is the EM programme about?
  • Why is it important?
  • What will success look like?
  • What do we need from you?

27
Summary
  • We revised the Register of Opportunities
  • We reviewed the Savings Register
  • We examined the Life Cycle for Significant Users
  • We briefly introduced the Concept of Energy
    Performance Indicators
  • We drew up simple EPis
  • We wrote an Elevator Speech for our EM programme

28
Take Action !
  • Liam Tolton
  • info_at_secondsighttechnical.com
  • Tel 087 2542969

Technical
www.sei.ie/energymap
Write a Comment
User Comments (0)
About PowerShow.com