Title: Energy Code Enforcement
1Energy Code Enforcement
Lessons from the field
Contact Mike Turns Ph 814-863-0623 E-Mail
mat289_at_psu.edu
2Presenters
- Bob Buddenbohn
- Instructor,
- PHRC
- Dave Buskirk
- Instructor,
- PHRC
- Mike Turns
- Housing Program Development Specialist,
- PHRC
3Pennsylvania Energy Code EnforcementEvaluation
Technical Assistance Program
4Program scope
- Limited to residential construction
- Detached one and two-family dwellings
- Townhouses
5PA Energy Code Evaluation
- Primary
- Technical assistance to municipalities 3rd
party agencies. - Secondary
- Determine how the energy code is being enforced
(common compliance problems and how to avoid
them). - Quantify actual home performance vs. code.
6PA Energy Code Evaluation
- Worked with code groups to market program.
- Pennsylvania Construction Code Academy
- Pennsylvania Association of Building Code
Officials - Pennsylvania Building Officials Conference
- Pennsylvania Association of Code Officials
- Lancaster Association of Code Officials
7PA Energy Code Evaluation
Small Municipality
COG
3rd Party Agency
City
H
8PA Energy Code Evaluation
- Provided the following
- Detailed Plan review
- Reviewed plan submittal forms and plan review
checklists - In-house meeting to discuss
- Overview of plan review and inspection process
- Experience and certifications of staff
- In-field rough framing inspection
- In-field insulation inspection (if they do one)
- Final Inspection
- Detailed performance review of house
- Blower door, duct blaster, IR scan, computer
simulation, etc. - Report to participants with recommendations
- Report to DOE Public
9Comparison of Performance vs. REScheck
10PHRC The Pennsylvania Housing Research Center
Energy Code Enforcement and Compliance in
Pennsylvania Lessons from the Field
219 Sackett Building University Park, PA 16802
Telephone (814) 865-2341 Facsimile (814)
863-7304 February 2008
11House Performance Findings
Typical Energy Program House
03 IECC Sim Performance Alt.
Depressing
OK
Impressive
H
Air Leakage
12House Performance Findings
H
Energy Star Limit
Depressing
OK
Impressive
Duct Tightness
13Big Issues
- Incomplete plan submittals
- Limited plan review
- Conditioned vs. unconditioned basement
- Slab insulation
- Thermal envelope sealing and continuity
- Ducts substantially airtight?
- Administrative issues
14Report recommendation 1
- Plan Submittal Requirement Checklist
- Code office administrators should create a plan
submittal requirement checklist containing
energy-related items (in addition to other
non-energy items) and enforce the submission of
these items. - See handout
15(No Transcript)
16Plan Review
17Consequences
- Incomplete plan submittals
- Repeated submittals
- Difficult, time-consuming, or incomplete plan
review - Lack of due diligence
- Conflicts in the field
18Report recommendation 3
- Identify the thermal envelope
- Plan reviewers should identify and mark the
building thermal envelope on the plans for each
area to be constructed ensuring that it is
continuous. - Also, check for continuity of insulation in
slabs, foundation walls, stairwells and other
architectural details where applicable.
19 H
20(No Transcript)
21Consequences
- Incomplete thermal envelope in constructed home
- Noncompliance
- Difficult, costly, or impossible remedy
22Conditioned vs. Unconditioned Basements
- Identify at plan review whether a basement is to
be conditioned or not - Unfinished ? Unconditioned
23(No Transcript)
24Slabs When is insulation required?
25Slabs Where is insulation required?
26(No Transcript)
27Report recommendations 5-7
- Review REScheck documentation
- Location, software version, code year
- All insulated building components present
- Component areas reasonable
28Consequences
- Noncompliance
- Higher than code-allowable energy use
29Inspections
- Floodplain
- Footing
- Foundation wall rebar inspection
(masonry/concrete) - Foundation Wall
- Rough Plumbing
- Rough Mechanical
- Rough Gas
- Rough Electrical
- Rough Framing
- Slab
- Insulation
- Wallboard
- Final Plumbing
- Final Mechanical
- Final Gas
- Final Electrical
- Other inspections
- Fire-Resistance
- Final
-
Inspections we will cover
30Slab Inspection
31Report recommendation 8
- Inspect for properly installed slab insulation.
Slab insulation should be required to extend
downward from the top of the slab.
32H
33Consequences
- Slab with no thermal break
- Cracking slab (if resting on footer)
- Energy loss
- Cold slab/comfort
- Moisture
34Rough Framing Inspection
35Report recommendation 10
Thermal envelope air sealing Inspectors should
check for the sealing of seams in sheathing, or
for house wrap installed to the manufacturers
instructions for installation as an air barrier.
36H
Seal seams
37Tyvek Homewrap
H
- To be considered an air barrier
- Bottom roll edge should extend over sill plate
interface at least 2? - Seal wrap at bottom of the wall (caulk, tape,
StraightFlash) - Use washer head fasteners or wide crown staples
(1? min.) - All vertical and horizontal seams taped
38Consequences
- Excessive infiltration
- Energy loss
- Moisture problems
- Comfort complaints
39Continuous air barrier
- New air sealing requirements Unclear in code
- Kneewalls
- Tubs showers (found on exterior walls)
40H
R-19 in a knee wall?
41H
Air barrier on the back side of a kneewall
H
42H
43H
44Consequences
- Air flow through porous insulation can
drastically reduce the R-value - Insulation in contact with sheathing on both
sides can improve R-value by 50. - Solution Completely encapsulate insulation
45Report recommendation 12
Fireblocking and air sealing shaft
walls Inspectors should check for blocking along
shaft walls in townhouses in every location where
these walls intersect with floors and ceilings.
46H
47Consequences
- Free air movement between wall and attic
- Fire spread
- R-value degradation
- Energy loss
- Moisture issues
48Mechanical Inspection
49Report recommendations 15-16
- Duct system properly sealed and connected
- During mechanical inspections inspectors should
make an attempt to follow duct runs from the
trunk or plenum to the register or grille to
ensure that all ducts are properly connected and
sealed. - Air handlers, filter boxes, building cavities
50H
51H
52H
53H
54Consequences
- Leaky distribution system
- Increased building infiltration
- Decreased equipment efficiency
- Decreased air quality
- Potential backdrafting of combustion appliances
- Moisture in building cavities
55Insulation Inspection
56Report recommendation 18
Continuous thermal envelope Inspectors should be
aware of the location of the thermal envelope as
specified by the approved plans and verify that
insulation is properly located and forms a
continuous boundary.
57 H
58Consequences
- Missing insulation
- Energy loss
- Discomfort
59Final Inspection
60Report recommendations 24-25
- Attic hatches
- Weatherstripping
- Permanently affixed insulation
61H
62H
63Consequences
- Thermal weakness and exfiltration
- Energy loss
- Moisture problems in attic
64General
65Report recommendation 27
Checklists Code offices should consider
developing and using plan review and inspection
checklists, or integrating energy items into
existing checklists to ensure consistency and
thoroughness.
66Consequences
- Inconsistency and/or incompleteness
- Builder confusion
- Home noncompliance
- Lack of quality assurance
67Summary
- Home performance
- Whole-house infiltration tighter than expected
- Duct tightness mixed bag
- Code enforcement opportunities for improvement
- More complete plan submittals
- Increased emphasis on plan review
68Summary
- Code enforcement opportunities for improvement
- Conditioned versus unconditioned basements
- Slab insulation
- Thermal envelope sealing and continuity
- Duct sealing and connections
- Quality assurance (checklists)