Title: GBAS PROJECT
1GBAS PROJECT
GBAS CAT-I Safety Assessment
- First Achievements and
- Next Steps
- SRC 14, 28-29 May 2002
2 OVERVIEW
- Initial Deliverables
- Current Activities
- Next Steps
- Way Forward for GBAS/SRC Interface
3SAFETY ASSESSMENT - Initial Deliverables
- GBAS Safety Policy
- Approach to facilitate the safety regulation
process - Safety regulatory position on acceptability of
changes - GBAS Safety Plan
- Route-map for the safety assessment of GBAS CAT-I
- Technical Operational issues in coherent
framework - Ground airborne systems in a harmonized manner
- Initiation of interface process with the SRC
- Endorsed on 22nd January 2002
4SAFETY ASSESSMENT - Application of the Safety Plan
- Provide support to States/ ATSPs through example
applications - Assess the practicability of the GBAS Safety Plan
to European airports - How well does it fit with their normal safety
assessment process and their GBAS implementation
plan? - Feedback States opinions/ experience to enhance
the Safety Plan - Application to Bremen, Malaga, and Zurich
- Final Plans by June 2002
5SAFETY ASSESSMENT - FHA The Phased Approach
- Pre-concept
- 1st hazard identification with aim to feed
forward into definition of concept of operations - Post-concept
- More in-depth analysis using concept of
operations and feeding forward into development
of phraseology, flight planning etc. - Detailed
- Detailed analysis of defined procedures, human
tasks
6SAFETY ASSESSMENT - Pre-Concept FHA
- First brainstorming session in Feb. 02 (6-8)
- Large participation AENA, British Airways, DFS,
DNV, GBAS Project, FDC, IATA, KLM, Skyguide,
STNA, Swissair and Thales ATM - Generic FHA for ATC Pilot Tasks
- Identification of failure modes subsequent
analysis - GBAS GS one-day session on 24th May at DFS
- Important input into GBAS CAT-I Concept of Ops
- Draft Report circulated - Final report by June 02
7SAFETY ASSESSMENT - Next Steps
- GBAS Post-Concept Safety Assessment
- Definition of the GBAS CAT-I Concept of Operation
- Interim FHA Detailed FHA
- PSSA
- To be Kicked-off early June 02
- TLS Safety Objectives
- Method to apportion ATM TLS derive Safety
Objectives - Application to GBAS
- Joint activity with SRC/SRU, SQS, SAF BA/EEC
- To be kicked-off early July 02 final
deliverables by Dec. 02 - Co-operation with JAA activated (JAA CNS/ATM SG
in September)
82001
2002
2003
2004
2005
SAFETY POLICY/PLAN
GBAS SAFETY POLICY PLAN Endorsement by SRC in
January 2002
GBAS IMPLEM.
SAFETY PLAN APPLICATIONS
APPLICATION TO AIRPORTS (05/2002)
GBAS OPERATION
CONCEPT OF OPS
PRE-CONCEPT FHA
GBAS Pre-Concept FHA (06/2002)
POST-C. FHA
GBAS Post-Concept FHA (10/2002)
DETAILED FHA
GBAS Detailed FHA (03/2003)
PSSA
GBAS PSSA (04/2003)
SSA
GBAS SSA (12/2004)
Outline of a GBAS Safety Case (12/2004)
9Way Forward for GBAS/SRC Interface
- Submission of the Detailed FHA Report (Q1 03)
- Need to develop RAD (Section specific to GBAS)
- Progressive FHA outcomes to feed forward into RAD
for GNSS - Need to reconvene SRC GNSS Group
10(No Transcript)
11SAFETY ASSESSMENT - Process
- GBAS Safety Policy
- GBAS Safety Plan
Pre-concept Hazard Identification Analysis
Post-concept Hazard ID Analysis
Detailed Hazard ID Analysis
PSSA SSA
Outline of a Safety Case
Detailed Definition of Ops Phraseology, Flight
Planning, Interfaces, etc.
Concept of Operations for GBAS CAT-I
GBAS Operational
GBAS Safety Process
GBAS Operational Validation