Title: Offender Management Network Information OMNI
1Offender Management Network Information (OMNI)
ISB Presentation January 12, 2006
2Agenda
- Introductions
- Plan for Moving Forward and Schedule
- Gated Approach Update
- Success Factor Update
- Schedule
- Current Status
- QA Initial Assessment
- Defect Resolution Plan and Schedule
- Specifications Staffing Plan and Schedule
- Allocation Request
- Questions
3Introductions
Harold Clarke Secretary, DOC Melanie
Roberts Deputy Secretary of Administrative
Services, DOC Nick Whitehead Project Director,
IBM Kent Keel Project Director, OMNI
4Plan for Moving Forward Gated Approach
5Success Factor Actions
6Success Factor Actions(continued)
7Success Factor Actions(continued)
8High-Level Schedule
November
December
January
February
March/April
Work with IBM team on defect evaluation (2
weeks)
Provide details on defect evaluation to ISB
Request funding to complete defect correction
work and begin project specification work
Correct defects
Finish agreed-upon defect corrections
Defects resolved prior to any Phase III coding
Complete project specifications
Upon approval begin Phase III (detailed
specification/design work)
Work on project specifications
Due to extended contract negotiations, these
activities moved to January. The project is
implementing contingency plans for keeping on
schedule.
9Current Status
- IBM contract signed and staff on site
- Defect resolution plan complete
- Defect resolution testing plan complete
- Testing contract process complete and staff
scheduled on site later this month - Specifications development plan complete
- QA contract signed and staff on site
- Initial project assessment complete
10QA Initial Assessment
- Key Findings
- Our initial assessment of OMNI Phase 3 is
positive in that it is clear that a dedicated
team is addressing the appropriate issues in the
early stages of the project. - Biggest risk concern Schedule
- Key Recommendations (1)
- OMNI project team should focus immediately on
development of a credible work plan to achieve
the March 31 end date. - DOC Response
- DOC and IBM have realigned resources to address
the delay in schedule.
11Defect Resolution Plan
- 4 developers assigned solely to defect resolution
- Fixes moved to a test region for OMNI DOC staff
to test and close - Additional developers will be assigned to address
schedule impact - Phase II code stable before approval for Phase
III detail design to begin
12Defect Fix Schedule
January
February
March
April
2
9
16
23
30
6
13
20
27
6
27
20
13
3
Chronos
Judge/Records/ Admin/Soundex
Work on defects may extend into April, if needed
Notifications
Offender
SSTA
13Specifications Staffing Plan
- Realigned resources
- Solution Architect now available full-time
- Data/Application Architect now available
full-time - Added Data Modeler
- Additional developers if necessary
- Available resource hours will be expended more
rapidly than planned
14Specifications Schedule
March
February
January
- Refine High- Level Design Specifications
- Continue UML
- Continue Architecture Design
- Complete Requirements Validation
- Initial High-Level Design Specifications
- Begin UML
- Begin Architecture Design
- Form Team
- Review Phase 3 Requirements
- Validate Requirements
- Review Current Architecture
- Begin Architecture Planning
15Allocation Request
16Questions?