Title: High Lake Project Hydrology
1High Lake ProjectHydrology Surface Water
Quality
- Eugene Yaremko,nhc
- Leslie Gomm, GLL
2HydrologyImpact Assessment
- Has followed an Issues-based approach where
mining activities would have an impact on - Â Surface Water Quantity
- Distribution of Water
3HydrologyImpact Assessment
- Local study area vs. environmental impacts
- It has been assumed that impacts related to
mining activities and surface water will not
extend beyond the LSA
4HydrologyBaseline Data
- Streamflow 14 hydrometric stations
- 10 of these associated with Kennarctic River Flow
- 2 stream crossings along all-season road
- Periods of record available range from on to
three years, beginning in 2004 - Climate station near south end of High Lake
installed in 2004 - Temperature, rainfall, relative humidity, wind
speed and direction
5HydrologyBaseline Data
- Snow course measurements immediately prior to
spring freshet (2004 and 2005) - Bathymetric surveys of primary lakes within LSA
6HydrologyRegional Assessment
- The short streamflow and climate record available
within the LSA make it necessary to utilize
regional information principally - Six water survey of Canada stations
- Climate records for Lupin/Contwoyto Lake
Kugluktuk/Copper River and Cambridge Bay.Â
7HydrologyWater Balance Assessments LSA
- Three primary components in the process
- Annual precipitation
- Annual evaporation
- Coefficient of runoff
8HydrologyAnnual Precipitation
- Estimate of annual precipitation at mine site has
to be regional information - Three long-term climate stations were utilized
- Lupin/ Contwoyto Lake (combined) centered 250
km south of High Lake - Kugluktuk/Coppermine (combined) centred 170 km
south and 50 km north of High Lake - Cambridge Bay centred 240 km East and 175 km
north of High Lake
9HydrologyAnnual Evaporation
- Mean Annual Evaporation for Project 240 mm
- Estimate of mean annual evaporation based on
regional information principally - Lupin 275 mm
- Doris North Project 220 mm
- Salmita (Reid) 286 mm
- Hydrological Atlas of Canada MAE contours
10HydrologyRunoff Coefficient
- Adopted value of 0.60
- Based on local and regional information
11Surface Water Quality
- Site Water Management - Overview
- Predicted Impacts
- 4 pathways
- Key Issues
- Assessment Approach For Kennarctic River
- Summary of Baseline
- Total vs. Dissolved Metals and TSS
- Water Quality Model
- Water Management Plan
12Site Water Management
- The following principles were used in the design
of water-related aspects of the Project - Minimizing the number of drainage areas
(sub-catchments) affected by the Project by
limiting most of the development to within the
High Lake drainage area - Minimizing the disturbance footprint outside of
the High Lake drainage area - Implementation of BMPs for the collection,
treatment and handling of all site runoff
13Site Water Management
- Filling pits with tailings
- Routing of mill tailings, mine water, pre-treated
deep groundwater, treated sewage, and runoff from
the waste rock piles, mill area and buildings to
the High Lake Tailings Impoundment - Treatment at or near source
- Maximizing underground mine backfilling of PAG
material - Seasonal discharge to Kennarctic River (June
October) with treatment if required
14Retention Time 2 to 3 Years
Ore StockPile
15(No Transcript)
16Predicting Site Water Quality
- High Lake Water Quality Model
- Predict the water quality, water volumes and
elevations in High Lake, AB Pit and D Pit - Source loading terms for mine rock and pit walls
based on kinetic tests - Incorporates inputs due to explosives residues
from mine rock and pits - Predict water quality any discharges to receiving
environment including the Kennarctic River, L15,
and L4 during mine operations, closure and
post-closure (to Year 150) - Based on a MAP of 280 mm and MAE of 240 mm and
run using different hydrological scenarios
modeled including a 3 yr drought and 2 year wet
period
17Predicting Site Water Quality
- High Lake Water Quality Model - Results
- All predicted concentrations of regulated
parameters below MMER except zinc for first 1.5
years - Chloride, nitrite, aluminum, antimony, arsenic,
cadmium, chromium, copper, lead, manganese,
nickel, selenium, silver and zinc above
threshold levels - Copper, zinc and cadmium - existing lake
conditions - decrease over time from the
naturally high levels - Chloride, chromium and cadmium estimated
pre-treated inflows from underground mine - Ammonia, nitrate and nitrite nitrogen
explosives residues and sewage (minor) - Selenium and other parameters primarily mill
effluent and secondarily mine rock
18Predicting Site Water Quality
- High Lake Water Quality Model - Results
- Discharge to Kennarctic River will not occur
until 3rd year of operations - Treatment of discharge through polishing pond
will be carried out to reduce metal levels in
discharge copper, cadmium, chromium and zinc -
where required - Long term water cover
- High Lake - 5 m
- D-Pit - gt 10 m
19Surface Water Quality Predicted Impacts
- Surface water quality impacts were assessed using
the following thresholds - CCME Guidelines for the Protection of Aquatic
Life - Cadmium U.S. EPA Criterion Continuous
Concentration (CC) - Chloride U.S. EPA CCC
- Manganese - Canadian Drinking Water Guidelines
aesthetic objective
20Surface Water Quality Predicted Impacts
- SWQ1 Project activities, including roads,
outside immediate High Lake catchment - Based on annual load model predicted
concentrations above existing baseline
concentrations but below threshold values for
protection of aquatic life except for - Copper in L15 within range of baseline
concentrations
21Surface Water Quality Predicted Impacts
- SWQ2 Diversion of streams L18 to Kennarctic
River and L15 to L4 - Permanent diversion of these streams will not
result in any appreciable changes in water quality
22Surface Water Quality Predicted Impacts
- SWQ3 Construction of High Lake Tailings
Facility - Discharge of treated High Lake water during dam
construction will not result in any changes in
the water quality in the Kennarctic River except
for cadmium - Predicted cadmium concentrations are above
background levels but below the threshold for
protection of aquatic life
23Surface Water Quality Predicted Impacts
- SWQ4 Discharge of water from the High Lake
Tailings Facility to the Kennarctic River - Predicted open water season concentrations in the
Kennarctic River immediately downstream of
discharge are predicted to be above existing
baseline concentrations but below threshold
values except for copper and selenium - Predicted under-ice concentrations (from deep
groundwater inflows after Year 34) of selenium
and chromium are above threshold values
24Surface Water Quality Predicted Impacts
Selenium - Other jurisdictions acknowledge
unpredictable effects with wide range of
guidelines. Body burden in fish more useful than
water concentration. Will monitor body burdens in
fish.
25Surface Water Quality Issues
- Kennarctic River
- Concerns have been raised regarding the approach
taken for assessment of water quality impacts in
the Kennarctic River - The following outlines the approach taken in the
assessment including significance determination
26Surface Water Quality Issues
- Kennarctic River Open Water Season
- Fully mixed concentrations in the Kennarctic
River downstream of discharge are predicted to be
above existing baseline concentrations for a
number of COCs but below threshold values for all
except for copper and selenium
27Surface Water Quality Issues
- Kennarctic River-Open Water
- Copper
- Max. concentration 0.0034 mg/l (LSA)
- Above CCME threshold (0.002 mg/L) for 5 years
during operations in both LSA and RSA - Selenium
- Max. concentration 0.002 mg/L (LSA)
- Above CCME threshold (0.001 mg/L) for 3 years
during operations in both LSA and RSA
28Surface Water Quality Issues
- Kennarctic River-Under Ice
- Predicted under-ice concentrations (from deep
groundwater inflows after Year 34) of selenium
and chromium are above threshold values - Selenium Max. concentration 0.0012 mg/l
- Above threshold (0.001 mg/L) for 6 years (May
only) in LSA - Chromium Max. Concentration 0.0011 mg/l
- Above threshold (0.001 mg/L) for 10 years (May
only) in LSA
29Surface Water Quality Issues
- Kennarctic River
- Magnitude of impacts were assessed using
following criteria
30Surface Water Quality Issues
- Kennarctic River
- Summary of Significance Rating Criteria
31Surface Water Quality Issues
Assessment of significance would not change by
making LSA smaller and having RSA start farther
upstream same magnitude (moderate) in both LSA
and RSA.
32Surface Water Quality Issues
- Plume Delineation
- Downstream distance for complete mixing of the
High Lake discharge 230 m - Based on a single point channel side discharge
configuration with instantaneous vertical mixing - Estimated that at 50 m downstream 90 diluted
- A plume delineation study will be carried out
- Modelling of High Lake discharge
- Field monitoring to calibrate and validate model
results - Based on plume delineation study results,
appropriate mitigation may be implemented to
minimize mixing zone
33Surface Water QualityIssues
- Summary of Baseline Data
- Concern that baseline data not presented
adequately to characterize natural variability - Zinifex will provide an updated summary and
evaluation of the baseline water quality data set
including - Evaluation of temporal and spatial variability
- Additional data collected in 2006 and 2007
- Discussion of linkages to the future site AEMP
34Surface Water Quality Issues
- Total vs. Dissolved Metals and TSS
- Concerns raised of the use of dissolved metals
for mine rock source terms under-estimates metal
concentrations - High Lake model
- Pits and waste rock dissolved metals
- Tailings supernatant, residual drainage, ore
stock pile total metals - Road model
- Road construction material - dissolved metals
- Natural drainage total metals
35Surface Water Quality Issues
- Total vs. Dissolved Metals and TSS
- This approach to modelling was adopted given
- In general, in aquatic toxicology, it is the
dissolved metal fraction is considered to be the
metal fraction that is bio-available and elicits
most of any toxic effect. - BMPs will be used on-site to minimize TSS
loadings to the receiving environment - Also note - that fractions estimated as
dissolved report to tailings area but
discharge to environment was estimated as total
metals
36Surface Water Quality Issues
- Total vs. Dissolved Metals and TSS
- Concerns raised with modelling of road runoff
- No particulate fraction
- Assumed 15 mg/L only in first year
- Concerns also raised about use of annual load
model
37Surface Water Quality Issues
- Total vs. Dissolved Metals and TSS
- Zinifex is committed to re-evaluating the impacts
of metals associated with particulate matter
including - Assessment of the contribution of particulate
fraction to overall loading and associated
impacts in both models - Sensitivity analysis of TSS loading in the road
runoff model - Monthly model has subsequently been developed for
road runoff
38Surface Water QualityIssues
- WQ Model
- Predict the water quality, water volumes and
elevations in High Lake, AB Pit and D Pit - Predict water quality any discharges to receiving
environment including the Kennarctic River, L15,
and L4 during mine operations, closure and
post-closure (to Year 150) - Different hydrological scenarios modeled
including a 3 yr drought and 2 year wet period - Model originally in Stella recently transferred
to Goldsim
39Surface Water QualityIssues
- WQ Model
- Several concerns have been raised during review
of DEIS regarding the High Lake water quality
model including - Lack of rationale for selection of runoff
coefficients - Selection of drought/wet scenarios
- Use of average flow conditions
40Surface Water QualityIssues
- WQ Model
- Model has been update for ease of running
scenarios to adequately characterize the system
and run scenarios - Highlights of Goldsim Model
- Water treatment at source (AB Pit, D Pit and ore
stockpile) - Desalination of deep groundwater
- Updated source loading terms from mine rock
41Surface Water QualityIssues
- WQ Model
- Highlights of Goldsim Model
- Increased AB Pit Cap and AB NAG cover from 5 m to
10 m - Use of thermo-siphons
- Updated estimates of deep and shallow groundwater
seepage - Incorporates receiving environment modelling
including L4, L15 and the Kennarctic River - Climate change scenario
42Surface Water QualityIssues
- Updated Model Results
- Predicted open water concentrations similar to
previous results with same duration and extent - 0.0032 mg/L Copper and 0.002 mg/L Selenium
- Predicted under-ice concentrations no longer
any parameters above thresholds - 0.0005 mg/L Chromium and 0.0009 Selenium
- Reduced impact (under ice) but no change in
overall determination of significance - Impacts will be further evaluated in an Aquatic
Risk Assessment
43Surface Water QualityIssues
44Surface Water QualityIssues
45Surface Water QualityIssues
46Surface Water QualityIssues
47Surface Water QualityIssues
- Additional 100-year extreme drought scenario -
test ability to maintain water cover - Year 20
- 1100 return event 164 mm
- Evaporation 292 mm
- Year 21
- 150 return event 180
- Evaporation 265 mm
- Year 22
- 110 return event 216
- Evaporation 240 mm
48Surface Water QualityIssues
49Surface Water QualityIssues
- Water Management Plan
- Preliminary Water Management Plan (WMP) was
provided as part of the DEIS which included a
summary of - Site water management facilities including
treatment - Mine rock storage plan
- Tailings management
- Predicted performance of water management systems
(water quality and flows) - High Lake Water Quality Model
- Monitoring
50Surface Water Quality Issues
- Water Management Plan
- Several concerns have been raised during review
of DEIS including lack of detail on - Rationale for assumptions
- Schematics of water management systems
- Drainage management systems including sediment
and erosion control - Proposed treatment systems
- Monitoring to support adaptive management and
system performance monitoring - Site water modelling and associated results
51Surface Water Quality Issues
- Water Management Plan
- Zinifex is committed to providing an updated
comprehensive water management plan with
supporting detailed model documentation to
address these concerns
52Surface Water QualityIssues
- Additional 100-year extreme drought scenario -
test ability to maintain water cover - Year 20
- 1100 return event 164 mm
- Evaporation 292 mm
- Year 21
- 150 return event 180
- Evaporation 265 mm
- Year 22
- 110 return event 216
- Evaporation 240 mm
53Hydrology and Surface Water Quality