Title: Flood Risk Management
1Flood Risk Management
- Plan Formulation, Project Development,
Stakeholder Issues
2Flood Risk Management Measures
- Structural measures
- Modify flood behavior
- Dams and reservoirs, levees, walls, diversion
channels, bridge modifications, channel
alterations, pumping, and land treatment - Nonstructural measures
- Modify damage susceptibility
- Flood warning and preparedness Evacuation and
relocation National Flood Insurance Program
(NFIP) Flood proofing
3Structural FRM Measures
- Dams
- Reservoirs
- Floodwalls
- Levees
- Channels
- Straightening
- Clearing and snagging
- Closure structures
- Bridge modifications
- Conveyance modifications
- Pumping
- Channel diversions
- Beach Nourishment
4Structural - Reservoirs
Mt. Morris Dam
McCook, Ill.
Yatesville Lake, Ky.
Center Hill Lake, Tenn.
5Structural - Walls Levees
Lock Haven, PA
Frankfort, KY
Frankfort, KY
West Columbus
6Channel Modification Projects
Minnesota River, MN, diversion
Martins Fork, KY, diversion
Harlan, KY, tunnels
River Rouge, MI, channelization
7Beach Nourishment, (Before) Miami/Dade County, FL
Beach Nourishment, (After) Miami/Dade County, FL
8National Nonstructural/ Flood Proofing Committee
http//www.usace.army.mil/inet/functions/cw/cecwp/
NFPC/nfpc.htm
9Nonstructural FRM Measures
- Elevation
- Relocation
- Floodwalls, Levees and Berms
- Buyout/Acquisition
- Dry Flood Proofing
- Wet Flood Proofing
- Flooding Warning/Preparedness
10Elevating on Extended Foundation Walls
11Elevating on Fill
12Elevation on Piers, Posts, Piles, or Columns
Piers
Posts
Columns
Piles
13Relocation Process
- Evacuate temporary roadway
- Attach structure to trailer
- Transport structure to new site
14Relocation Process Restoration of Old Site
- Plan must include a new use for the evacuated
floodplain - Demolish and remove foundation and pavement
- Disconnect and remove all utilities
- Grading and site stabilization
15Evacuated floodplain area
16Ring wall/levee
17Ring wall/levee - closure
18Ring wall/levee
19Dry Flood Proofing Methods
Waterproof Sealant
20Dry Flood Proofing Method Waterproof Sealant
21Wet Flood Proofing
Elevate Utilities
22Wet Flood Proofing
Let Water In
Louvre
23Flood Warning/Preparedness Components
- Flood Threat Recognition System
- Warning Dissemination
- Emergency Response
- Post-Flood Recovery
- Continued Plan Management
24Nonstructural FDR Solutions
Flood Warning Emergency Evacuation Plans (FWEEP)
- Detailed evacuation plans and inundation
mapping - Stream gages with/without remote
sensing - Rain gages with remote sensing
FWEEPs are almost always cost effective and
relatively inexpensive
25National Flood Insurance Program 44CFR 59-78
- Flood Plain Regulation (FDR)
- Flood Insurance (Risk Sharing)
- Flood Mitigation (FDR)
26FEMA Definition 100 Year Floodplain
______________________________?100 year flood
_____
Base Flood?
STREAM CHANNEL
27Structural and Nonstructural Measures
- Structural measures keep the floods away from
resources in the floodplain
- Nonstructural measures keep the resources away
from floods in the floodplain
28Basic Formulation Strategy
- The basic formulation strategy is to formulate to
meet each of your planning objectives without
violating any constraints. - Every iteration of the formulation step must
employ this basic strategy.
29How - Formulation Strategies
- All possible combinations
- Measures strategy
- Convergent thinking
- Divergent thinking
30Formulation Strategies
- Nonstructural (statutory requirement)
- Change timing
- Flood
- Resources
- Change magnitude
- Flood
- Resources
- Outputs
- Maximum damage reduction
- Life cycle costs
- Sponsor financial capability
- Locally Preferred (LPP)
- Change location
- Flood
- Resources
31Nonstructural Opportunities
- New Uses of the Evacuated Flood Plain
- Ecosystem Restoration
- Recreation
- Spillover Benefits
- Water Quality Improvement
- E.O. 11988
- NFIP Regulations
- Mitigation of Adverse Effects of Structural
Projects
32How do we help this situation?
High ground behind red line
Town limits
33What measures would help?
Detention pond?
Channel Modification?
Non-Structural Measures?
High ground behind red line
Town limits
Levee/Wall?
34Evaluation of Existing
35Future Without Conditions
36Channel Modification
37Reservoir / Detention Storage
38Non-Structural Measures
39Levee
40FDA Model Evaluates Measures
- Mathematical models are used to evaluate the
impacts of alternatives for flood damage
reduction - The Corps Flood Damage Assessment (FDA) model of
expected annual damage estimation is the
preferred method of modeling the effects of
formulated plans - Developed and Maintained at HEC Specific
training is available on the FDA model
41Formulation With FDA Model
Walls, levees Floodproofing
Channels Clearing snagging
Dams Detention reservoirs
42EAD Calculation for with project condition
43Where do we begin in formulation?
Detention pond?
Channel Modification?
Non-Structural Measures?
High ground behind red line
Town limits
Levee/Wall?
44First or Last?
Detention pond
High ground behind red line
Levee
45Dependencies
- Flood damage reduction plans often comprise
several measures - Some measures may require implementation of other
measures in order to function properly - Interior drainage measures (pump stations and/or
ponding areas) with levees/floodwalls - Warning system, operations manual, or FWEEP when
plans have closure structures requiring human
intervention (put the sand bag in the slot, flip
the switch on the gate motor power control, etc.)
46Combinability
- Flood damage reduction plans often comprise
several increments - More often flood damage reduction plans have
measures that can be combined in many ways,
shapes, and sizes to achieve NED
47Initial Formulation (we have only just begun)
Measure NED Cost NED Benefit
Net NED Benefit
48And we look at it all again - Reformulation
- First or last positioning of measures
- Dependencies
- Combinability
- Incremental Analysis
49Increment Defined
- An increment is any part of a plan that can be
eliminated without jeopardizing the proper
function of the remaining parts of the plan. - Thus, different levels of project performance are
not increments. - WRDA 1986 Definition of Separable Element.
For purposes of this Act, the term
"separable element" means a portion of a
project-- (1) which is physically separable from
other portions of the project and (2) which--
(A) achieves hydrologic effects, or (B) produces
physical or economic benefits, which are
separately identifiable from those produced by
other portions of the project.
50Another Example - Whats An Increment?
Levee alignment
Reach 1
Levee tie-back options
Reach 2
High ground behind red line
Town limits
Reach 3
51Separable Increments of a Flood Damage Reduction
Plan
Plan Increment NED Costs NED Benefits Net NED Benefits
Levee A (1) 21M 20M -1M
Levee B (12) 40M 70M 30M
Levee C (1,2 3) 60M 80M 20M
52Separable Increments Did we miss an opportunity
the first time?
Plan Increment NED Costs NED Benefits Net NED Benefits
Levee D (2) 21M 50M 29M
Levee E (3) 20M 10M -10M
Levee F (2 3) 39M 60M 21M
53Identifying the NED Plan
- Without-project damages
- With project damages
- Benefits are damages reduced
- Net benefits are benefits less project costs
(total life cycle costs, including environmental
mitigation) - Compare across project scales and between
alternatives to determine plan that yields
greatest NED benefits - Decision-makers always have the final say
54Environmental Consequences
- Flooding is natural flood damage reduction is
not - Flood damage reduction measures can have
environmental consequences - Some are intended, some are not
- Some are anticipated, some are not
- Some are beneficial, some are adverse
- Unanticipated, unintended consequences may be the
worst type
55Flood Plain Management Issues
- Induced flooding is not the NED issue
- Induced damages are the issue
- Avoiding or mitigating for induced damages are
part of project costs and must be considered in
plan formulation - Induced flooding is an NFIP/EO 11988 issue that
must be disclosed in the documentation
Where does the water go?
56Flood Protection Levee Lock Haven, PA
Do you think this property could be affected?
57FEMA and NED Formulation Issues
- National Flood Insurance Program participation
assumed - FEMA coordination essential and a matter of
policy - FEMA buyout land restrictions on Corps measures
- Locally desired protection (especially 100-year)
58Sponsors Old Role
- Prior to 1986
- Not as politically active
- Uninvolved in project development
- No cost sharing other than LERRDs
59Sponsors Changing Roles
- Todays Sponsors are
- Very politically active
- In many cases technically capable of
accomplishing work without COE support - Actively involved in project development
- Demanding faster, better, cheaper
- Want special application of policies for their
projects.
60Sponsors Political Activities
- Actively building state and local coalitions
- Campaigning for tight state revenues
- Working closely with Congressional Delegations
- Actively participating in national associations
- Engaging ASA(CW)
61Greater Involvement in Project Development
- - Integral member of study team
- - Performing more in-kind services
- - Meeting often with Corps team
- - In on major study changes
- - Will call and visit HQ quickly
62Greater Involvement in Project Development
- Congress provided sponsors authorities to conduct
planning, design and construction of project. - Section 203 WRDA 86 - study deep draft navigation
- Section 204 WRDA 86 - design and construct deep
draft navigation - Section 303 WRDA 90 - construct small navigation
- projects
- Section 206 WRDA 92 - construct shoreline
protection projects - Section 211 WRDA 96 - construct flood control
project - Section 2003 WRDA 07 credits for materials and
services provided for design and/or construction
63Demanding Faster, Better, Cheaper
- Section 203 WRDA 96
- If feasibility study cost increases greatly after
the FCSA has been signed, the sponsors
incremental share can be delayed until after
project construction or 5 years after the Chief
of Engineers report is issued. - Reconnaissance Studies
64Equal Treatment
- - Regional consistent analysis
- - Equal application of policies
- - In-kind credit
- Crediting for construction related activities now
allowed under Section 2003 of WRDA 2007!!
65Take Away Points
- Plan formulation is the art of creating plans to
address the objectives and constraints related to
flood damage reduction problems and opportunities - In developing plan formulation strategies, you
need to understand the basic policies affecting
plans for flood damage reduction improvements. - Breakpoints in costs are especially important to
formulation and associated costs need to be
included in the analysis - While a study may recommend a locally preferred
plan, the NED Plan establishes the limit on the
Federal investment.