Title: D
1DØ RunIIb Trigger Upgrade
- Paul Padley
- for the DØ Trigger Upgrade Group
2This talk
- Will briefly review this (previously approved)
upgrade - Will give the current status of the major
components of this upgrade - Darien Wood will discuss future plans and cost to
completion.
3The Run IIa Trigger System
Detector
Level 1
Level 2
7 MHz
2.5 kHz
1 kHz
CAL
L1Cal
L2Cal
c/f PS
L1PS
L2PS
CFT
L1CTT
L2CTT
SMT
L2STT
L1Mu
MU-TRK
MU
L2Mu
FPD
L1FPD
Global L2
Lumi
Framework
L3/DAQ
100 Hz
Level 3
4The Run IIb Trigger System
Detector
Level 1
Level 2
7 MHz
2.5 kHz
1 kHz
CAL
L1Cal
L2Cal
Cal-TRK
c/f PS
L1PS
L2PS
CFT
L1CTT
L2CTT
SMT
L2STT
L1Mu
MU-TRK
MU
L2Mu
FPD
L1FPD
Global L2
Lumi
Framework
New (or replaced) System
L3/DAQ
100 Hz
Level 3
Enhanced System
5Ingredients of the Trigger Upgrade L1 Cal
- Calorimeter trigger upgrade
- sharpens turn-on trigger thresholds
- more topological cuts
- cf simulation talk
- Largest subproject in the trigger upgrade
- Will require removing the existing Cal trigger
6Ingredients of the Trigger Upgrade CalTrack
- Exploit new L1Cal trigger
- Improve Run IIa f matching granularity x8
- Needed in triggers for Higgs searches
- electrons in WH and H WW modes
- taus in H tt and H tn
- Fake EM rejection is improved by x2
- Fake t rejection is improved by x10
- Upgrade modeled on existing Mu-Track match system
- Very few changes with respect to Mu-Track
7Ingredients of the Trigger Upgrade L1CTT
- Level 1 Central Track Trigger (CTT) essential for
electrons, muons, taus (WH?l?jj) - Tracking trigger rates sensitive to occupancy
- Upgrade stategy
- Narrow tracker roads by using individual fiber
hits (singlets) rather than pairing adjacent
fibers (doublets) - Cal-track matching
8Ingredients of the Trigger Upgrade L1CTT
- Original idea was to simply replace FPGAs to
newer larger ones that allow more equations - Last year we upscoped the project to allow
enhanced monitoring and debugging capability - The project now involves replacing two crates of
electronics - All elements in this upgrade have been designed
to minimize commissioning time and simplify
debugging
9Ingredients of the Trigger Upgrade Level 2
- Level 2 STT expand system to allow for the new
channels - Level 2 Processors. Buy new faster processors to
allow more functionality at this trigger level
10Management structure
WBS 1.2 Trigger Upgrade P. Padley (Rice), D.
Wood (Northeastern)
WBS 1.2.1 Level 1 Calorimeter M.Abolins(MSU),
H.Evans(Columbia)
Project is largely university based
WBS 1.2.2 Level 1 Cal-track match K. Johns
(Arizona)
WBS 1.2.3 Level 1 Tracking M. Narain (Boston),
Don Lincoln (FNAL)
WBS 1.2.4 Level 2 Beta upgrade R. Hirosky
(Virginia)
WBS 1.2.5 Level 2 STT upgrade U. Heintz (Boston)
WBS 1.2.6 Trigger Simulation M. Hildreth (ND),
E. Barberis (NEU)
WBS 1.2.7 AFE upgrade (Pending) A. Bross (FNAL)
11WBS 1.2.1 L1Cal
Clustering
ADCdigital filtering
Global sums topological
12L1Cal Hardware VME/SCL
- VME/SCL (Distributes VME and SCL for the TAB and
GAB) - working reliably for over a year
- No changes have been required in the board
- SCLD (Distributes SCL for the ADF system)
- Has been used successfully in integration tests.
- Both boards are complete
VMC/SCL
SCLD
13ADF Prototype V1
ADF Prototype board Underwent integration tests
at Fermilab, Oct 03 Was successfully operated
with D0 timing signals Sent data to TAB using D0
timing signals
14ADF V2
- ADF V2 Prototypes are in hand and being bench
tested
15ADF V2
- 10 Cards received in January
- 4 cards fully stuffed and tested
- All 4 seem to work just fine
- VME connection . in good shape, doing everything
needed . - Analog ADC Section
- have been testing this heavily
- checking noise levels,
- cross talk,
- frequency response, etc.
- Output to TAB (Channel Link)
- SCL Connection
- All looks good. Production Readiness Review
scheduled for Feb 11
16TAB
- Fully tested including
- All algorithmic functionality
- All input output functionality
- Data from ADF
- Data to Cal-Track
- Data to L2/L3
- Production boards are in hand and bench testing
has finished
17GAB
- Production boards are in hand and bench testing
has finished - Both TAB and GAB are now undergoing long term and
system tests
18TAB GAB rack under test
19L1Cal Summary
- All boards are in good shape
- TAB/GAB production complete
- Bench testing has finished, system testing begun
- ADF preproduction boards are in hand and are
passing all tests. - Production review in one week.
20L1CalTrack Trigger Overview
21Hardware Status
- SLDBs (Serial Link Daughter Boards)
- Production complete
- Testing complete
- MTCM (Crate Mananger)
- Production complete
- Testing 50 complete
- MTCxx (Trigger Card)
- Production versions in hand and testing is
underway - UFB (Flavor Board)
- Production will be assembled by Feb 11
- Splitter Cards
- Will be made soon
22Preproduction MTCxx with Prototype MTFB
UFB
SLDBs
23UFB
Gbit/s XMIT
Gbit/s RECV
Stratix FPGA
24Infrastructure Status
- L1Caltrack trigger and readout crates
- Installed and populated (using spare L1MU cards)
- Rack infrastructure (power, water, )
- 98 Complete, small mod needed
- VME crate power supply
- In hand, waiting for delivery of custom power
leads - Currently using spare L1MU supply
- Cables
- Collision hall to MCH1 cables complete
- L1CTT will be made in spring
- MTCxx cable termination complete
25L1CalTrack Summary
- A lot of the hardware has been produced
- The rest is currently in production.
- Testing is ongoing
26L1 Central Track Trigger
- Digital Front End Axial (DFEA) daughter cards
redesigned with larger FPGAs (Xilinx Virtex-II
XC2V6000) - Allows more complicated equations for using
narrower roads - Implemented prototype firmware (Boston U)
- Includes equation files from all 4 momentum bins
- DFEA logic is implemented in two FPGAs
- Prototype board functionality tested
- Previously approved system design changes to make
the upgrade easier to commission were made
27DFEA Board
- Preproduction boards in hand
- Have been tested on the bench and in the
experiment - PRR was held in January
- Need a couple more quick tests
- About to release for production
28Controller, Backplane and Splitters
- All Done, tested
- New backplane
- Controller
- LVDS Splitters Bare PC boards are now in hand
29CTT summary
- Things are progressing well
- About to go into full production of final boards
30Run 2B hardware summary
Run 2A Run 2A Run 2B I Run 2B I Run 2B II Run 2B II upgrade
system have system need system need baseline
FRC 6 7(10) 6 0 6 0 0
STC 54 64(80) 60 0 60 0 7
TFC 12 17 12 0 24 10 8
MB 72 100 78 0 90 10 20
BC 72 75(87) 78 30 90 30 20
LTB 78 134 84 0 114 20 52
LRB 90 144 96 0 132 20 46
hotlink 12 16 12 0 24 15 15
need to check how many work need to check how many work need to check how many work requires new hotlink merge card requires new hotlink merge card requires new hotlink merge card requires new hotlink merge card
Two different 2B scenarios compared to 2A and
baseline. 2B-I scenario chosen due to its
simplicity
31STT upgrade
- This upgrade is simply making more of the boards
that are currently used to allow for the
inclusion of layer 0 - Parts in danger of obsolescence have been
procured - Gaining experience from Run IIa
- PRR was held and production has begun
- Now only building Buffer Controllers
32L2 Beta Upgrade
- This is a simple replacement of CPUs in the L2
system - One candidate board (Concurrent Technology P220)
was tested and rejected - Adlink SBC tested and met requirement
- Board is compatible with future faster Intel
processors
33Directors Review - Trigger
- Recommendations
- Secure the manpower for all installation needed
in the 2004 shutdown to allow testing during the
data taking of FY05. - CF Simulation and SCIPC talks. Those are the
areas where help was needed and much progress has
been made - Establish a forum (presumably through the
Director for Research) for ongoing dialog with
CDF and the Accelerator Division on the timing of
the FY05 shutdown (maybe this exists already). - Agreed. The director is aware of this.
- It would be helpful to have a presentation on the
trigger simulation and validation efforts some
time in early 2005. - CF. simulation talk
- It would be useful to have a presentation of the
SC-IPC task list around the same time. - Cf. SCIPC talk
34Conclusions
- Outstanding progress has been made on all fronts.
- Lots of stuff is being built now and the rest is
about to go into production - It is an exciting time for the project as it
starts to come together.