D - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

D

Description:

P. Padley (Rice), D. Wood (Northeastern) WBS 1.2.1: Level 1 Calorimeter ... Project is largely university based. Director's Review, Feb 05. 11. WBS 1.2.1: L1Cal ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 35
Provided by: darienwood
Category:

less

Transcript and Presenter's Notes

Title: D


1
DØ RunIIb Trigger Upgrade
  • Paul Padley
  • for the DØ Trigger Upgrade Group

2
This talk
  • Will briefly review this (previously approved)
    upgrade
  • Will give the current status of the major
    components of this upgrade
  • Darien Wood will discuss future plans and cost to
    completion.

3
The Run IIa Trigger System
Detector
Level 1
Level 2
7 MHz
2.5 kHz
1 kHz
CAL
L1Cal
L2Cal
c/f PS
L1PS
L2PS
CFT
L1CTT
L2CTT
SMT
L2STT
L1Mu
MU-TRK
MU
L2Mu
FPD
L1FPD
Global L2
Lumi
Framework
L3/DAQ
100 Hz
Level 3
4
The Run IIb Trigger System
Detector
Level 1
Level 2
7 MHz
2.5 kHz
1 kHz
CAL
L1Cal
L2Cal
Cal-TRK
c/f PS
L1PS
L2PS
CFT
L1CTT
L2CTT
SMT
L2STT
L1Mu
MU-TRK
MU
L2Mu
FPD
L1FPD
Global L2
Lumi
Framework
New (or replaced) System
L3/DAQ
100 Hz
Level 3
Enhanced System
5
Ingredients of the Trigger Upgrade L1 Cal
  • Calorimeter trigger upgrade
  • sharpens turn-on trigger thresholds
  • more topological cuts
  • cf simulation talk
  • Largest subproject in the trigger upgrade
  • Will require removing the existing Cal trigger

6
Ingredients of the Trigger Upgrade CalTrack
  • Exploit new L1Cal trigger
  • Improve Run IIa f matching granularity x8
  • Needed in triggers for Higgs searches
  • electrons in WH and H WW modes
  • taus in H tt and H tn
  • Fake EM rejection is improved by x2
  • Fake t rejection is improved by x10
  • Upgrade modeled on existing Mu-Track match system
  • Very few changes with respect to Mu-Track

7
Ingredients of the Trigger Upgrade L1CTT
  • Level 1 Central Track Trigger (CTT) essential for
    electrons, muons, taus (WH?l?jj)
  • Tracking trigger rates sensitive to occupancy
  • Upgrade stategy
  • Narrow tracker roads by using individual fiber
    hits (singlets) rather than pairing adjacent
    fibers (doublets)
  • Cal-track matching

8
Ingredients of the Trigger Upgrade L1CTT
  • Original idea was to simply replace FPGAs to
    newer larger ones that allow more equations
  • Last year we upscoped the project to allow
    enhanced monitoring and debugging capability
  • The project now involves replacing two crates of
    electronics
  • All elements in this upgrade have been designed
    to minimize commissioning time and simplify
    debugging

9
Ingredients of the Trigger Upgrade Level 2
  • Level 2 STT expand system to allow for the new
    channels
  • Level 2 Processors. Buy new faster processors to
    allow more functionality at this trigger level

10
Management structure
WBS 1.2 Trigger Upgrade P. Padley (Rice), D.
Wood (Northeastern)
WBS 1.2.1 Level 1 Calorimeter M.Abolins(MSU),
H.Evans(Columbia)
Project is largely university based
WBS 1.2.2 Level 1 Cal-track match K. Johns
(Arizona)
WBS 1.2.3 Level 1 Tracking M. Narain (Boston),
Don Lincoln (FNAL)
WBS 1.2.4 Level 2 Beta upgrade R. Hirosky
(Virginia)
WBS 1.2.5 Level 2 STT upgrade U. Heintz (Boston)
WBS 1.2.6 Trigger Simulation M. Hildreth (ND),
E. Barberis (NEU)
WBS 1.2.7 AFE upgrade (Pending) A. Bross (FNAL)
11
WBS 1.2.1 L1Cal
Clustering
ADCdigital filtering
Global sums topological
12
L1Cal Hardware VME/SCL
  • VME/SCL (Distributes VME and SCL for the TAB and
    GAB)
  • working reliably for over a year
  • No changes have been required in the board
  • SCLD (Distributes SCL for the ADF system)
  • Has been used successfully in integration tests.
  • Both boards are complete

VMC/SCL
SCLD
13
ADF Prototype V1
ADF Prototype board Underwent integration tests
at Fermilab, Oct 03 Was successfully operated
with D0 timing signals Sent data to TAB using D0
timing signals
14
ADF V2
  • ADF V2 Prototypes are in hand and being bench
    tested

15
ADF V2
  • 10 Cards received in January
  • 4 cards fully stuffed and tested
  • All 4 seem to work just fine
  • VME connection . in good shape, doing everything
    needed .
  • Analog ADC Section
  • have been testing this heavily
  • checking noise levels,
  • cross talk,
  • frequency response, etc.
  • Output to TAB (Channel Link)
  • SCL Connection
  • All looks good. Production Readiness Review
    scheduled for Feb 11

16
TAB
  • Fully tested including
  • All algorithmic functionality
  • All input output functionality
  • Data from ADF
  • Data to Cal-Track
  • Data to L2/L3
  • Production boards are in hand and bench testing
    has finished

17
GAB
  • Production boards are in hand and bench testing
    has finished
  • Both TAB and GAB are now undergoing long term and
    system tests

18
TAB GAB rack under test
19
L1Cal Summary
  • All boards are in good shape
  • TAB/GAB production complete
  • Bench testing has finished, system testing begun
  • ADF preproduction boards are in hand and are
    passing all tests.
  • Production review in one week.

20
L1CalTrack Trigger Overview
21
Hardware Status
  • SLDBs (Serial Link Daughter Boards)
  • Production complete
  • Testing complete
  • MTCM (Crate Mananger)
  • Production complete
  • Testing 50 complete
  • MTCxx (Trigger Card)
  • Production versions in hand and testing is
    underway
  • UFB (Flavor Board)
  • Production will be assembled by Feb 11
  • Splitter Cards
  • Will be made soon

22
Preproduction MTCxx with Prototype MTFB
UFB
SLDBs
23
UFB
Gbit/s XMIT
Gbit/s RECV
Stratix FPGA
24
Infrastructure Status
  • L1Caltrack trigger and readout crates
  • Installed and populated (using spare L1MU cards)
  • Rack infrastructure (power, water, )
  • 98 Complete, small mod needed
  • VME crate power supply
  • In hand, waiting for delivery of custom power
    leads
  • Currently using spare L1MU supply
  • Cables
  • Collision hall to MCH1 cables complete
  • L1CTT will be made in spring
  • MTCxx cable termination complete

25
L1CalTrack Summary
  • A lot of the hardware has been produced
  • The rest is currently in production.
  • Testing is ongoing

26
L1 Central Track Trigger
  • Digital Front End Axial (DFEA) daughter cards
    redesigned with larger FPGAs (Xilinx Virtex-II
    XC2V6000)
  • Allows more complicated equations for using
    narrower roads
  • Implemented prototype firmware (Boston U)
  • Includes equation files from all 4 momentum bins
  • DFEA logic is implemented in two FPGAs
  • Prototype board functionality tested
  • Previously approved system design changes to make
    the upgrade easier to commission were made

27
DFEA Board
  • Preproduction boards in hand
  • Have been tested on the bench and in the
    experiment
  • PRR was held in January
  • Need a couple more quick tests
  • About to release for production

28
Controller, Backplane and Splitters
  • All Done, tested
  • New backplane
  • Controller
  • LVDS Splitters Bare PC boards are now in hand

29
CTT summary
  • Things are progressing well
  • About to go into full production of final boards

30
Run 2B hardware summary
Run 2A Run 2A Run 2B I Run 2B I Run 2B II Run 2B II upgrade
system have system need system need baseline
FRC 6 7(10) 6 0 6 0 0
STC 54 64(80) 60 0 60 0 7
TFC 12 17 12 0 24 10 8
MB 72 100 78 0 90 10 20
BC 72 75(87) 78 30 90 30 20
LTB 78 134 84 0 114 20 52
LRB 90 144 96 0 132 20 46
hotlink 12 16 12 0 24 15 15
need to check how many work need to check how many work need to check how many work requires new hotlink merge card requires new hotlink merge card requires new hotlink merge card requires new hotlink merge card
Two different 2B scenarios compared to 2A and
baseline. 2B-I scenario chosen due to its
simplicity
31
STT upgrade
  • This upgrade is simply making more of the boards
    that are currently used to allow for the
    inclusion of layer 0
  • Parts in danger of obsolescence have been
    procured
  • Gaining experience from Run IIa
  • PRR was held and production has begun
  • Now only building Buffer Controllers

32
L2 Beta Upgrade
  • This is a simple replacement of CPUs in the L2
    system
  • One candidate board (Concurrent Technology P220)
    was tested and rejected
  • Adlink SBC tested and met requirement
  • Board is compatible with future faster Intel
    processors

33
Directors Review - Trigger
  • Recommendations
  • Secure the manpower for all installation needed
    in the 2004 shutdown to allow testing during the
    data taking of FY05.
  • CF Simulation and SCIPC talks. Those are the
    areas where help was needed and much progress has
    been made
  • Establish a forum (presumably through the
    Director for Research) for ongoing dialog with
    CDF and the Accelerator Division on the timing of
    the FY05 shutdown (maybe this exists already).
  • Agreed. The director is aware of this.
  • It would be helpful to have a presentation on the
    trigger simulation and validation efforts some
    time in early 2005.
  • CF. simulation talk
  • It would be useful to have a presentation of the
    SC-IPC task list around the same time.
  • Cf. SCIPC talk

34
Conclusions
  • Outstanding progress has been made on all fronts.
  • Lots of stuff is being built now and the rest is
    about to go into production
  • It is an exciting time for the project as it
    starts to come together.
Write a Comment
User Comments (0)
About PowerShow.com