Title: London CPE


1
LCE Energy Project Action Plan Workshop Monday
28th April 08
2
LCE Energy Project
  • Welcome and introduction
  • Michael Wood
  • Programme Director

3
Purpose of the Workshop
  • To find out about the Local Government Energy
    Procurement Action Plan and how it can help your
    authority
  • To find about undertaking the Action Plan Self
    Assessment
  • To find out about the current status of the
    project and the wider public agenda

4
Purpose of the Workshop (cont)
  • To share your views on what you would like the
    project to do over the next year
  • To learn about a new savings toolkit that will
    help authorities to track their procurement
    performance

5
Agenda
  • 1000 Welcome
  • 1025 Background to the Action Plan
  • 1045 Undertaking the Self Assessment
  • 1140 Discussion Future Support
  • 1220 Networking Lunch
  • 1320 Update on National Landscape and Savings
    Toolkit
  • 1350 Update on Procurement Evaluations
  • 1410 Discussion Future Support (cont)
  • 1500 Round up and close

6
Intended outcomes
  • Greater understanding about undertaking the Self
    Assessment and how it can help your authority
  • Shared experience and best practice to facilitate
    problem solving
  • Issues for further consideration identified

7
LCE Energy Project
Background to the Action Plan Jo
Chambers Programme Manager
8
Local Government Energy Procurement Action Plan
  • Published in April 2007 in response to the LCE
    Energy Review Report
  • Aims to help authorities identify and manage the
    key areas that enable effective and efficient
    energy procurement

9
Local Government Energy Procurement Action Plan
  • Section A contract information
  • To provide a picture
  • of the contract
  • landscape across London

10
Local Government Energy Procurement Action Plan
  • Section B Actions and self assessment
  • Data Quality
  • Procurement
  • Financial Management
  • Monitoring Targeting
  • Performance Indicators

11
Local Government Energy Procurement Action Plan
  • Section C Questions for authorities
  • To help the project team
  • target resource effectively
  • To identify opportunities for peer support
    across London

12
Self Assessment
  • To help the project team identify areas of
    support, we asked authorities to score themselves
    against the Action Plan
  • This also helps authorities know which areas to
    target in their own authority

13
Self Assessment - Results
  • 33 authorities returned self assessments for 2007
  • The results of the self assessments identified
    Automated Meter Reading and Financial Management
    as areas for improvement

14
LCE Action Plan Self Assessment
  • The average scores for March 2007 for each
    section are shown below

Scale 0 Not yet considered or decided against
implementation 4 At least 95 implemented
15
LCE Action Plan Self Assessment cont.
16
LCE Action Plan Self Assessment cont.
17
LCE Action Plan Self Assessment cont.
18
LCE Energy Project
Undertaking the Self Assessment
19
Self Assessment Process
  • Identify key players in your authority, including
    energy, procurement and finance
  • Review last years Self Assessment
  • Undertake the Self Assessment
  • Completed self assessments should be returned by
    May 9th to lce.energy_at_haringey.gov.uk

20
Self Assessment Process
  • The results will be used to identify progress and
    where support might be needed in future
  • Results expected in mid-June
  • We recommend that authorities hold a planning
    meeting e.g. with the DoF and energy and
    procurement teams

21
Undertaking the Self Assessment
  • Go through each action, step by step
  • Ask any questions and clarifications
  • Share examples of best practice and learning
    experiences

22
LCE Energy Project
  • Discussion around
  • Future Work

23
Discussion around future work
  • The project has been working to support
    improvements for local authorities
  • e.g. Best Practice Procurement Model
  • e.g. Specification of Requirements
  • e.g. Action Plan for improvements
  • e.g. Workshops to target support

24
Discussion around future work
  • We would like to share ideas on
  • What has the project helped with?
  • What support do you expect to need over the next
    year?
  • How would you like this support to be delivered?
  • Anything else?

25
LCE Energy Project
  • Lunch

26
LCE Energy Project
Update on National Landscape and Savings
Toolkit Susie Owen Office of Government
Commerce
27
LCE Energy Project
Update on Procurement Evaluations Michael
Wood Programme Director
28
Procurement evaluations
  • July 2007 - Feasibility Study recommended
    aggregation of energy requirements and adopting
    flexible wholesale procurement
  • September 2007 Preferred Procurement Model
    signed off
  • November 2007 Customer driven Specification of
    Requirements approved

29
Procurement evaluations
  • We have been working with central purchasing
    bodies (CPBs) to help drive market development,
    in that the best practice developed through the
    project can be met
  • We are now evaluating CPBs against the SoR in
    order to assess current capability and capacity,
    and what future improvements are planned

30
Procurement evaluations
  • This requires a purchasing body to
  • undertake a self assessment against the LCE
    Statement of Requirements
  • evidence their self assessment in the LCE
    evaluation process
  • jointly agree an improvement plan milestones
    against the gap analysis
  • work closely with the LCE to deliver the
    improvement plan

31
Procurement evaluations
  • Organisations involved include
  • TEC evaluation near complete, improvement plan
    in development
  • OGCbuying.solutions evaluation in progress,
    improvement plan to be developed
  • KCC Laser meeting established, hope for future
    collaboration

32
Procurement evaluations
  • The Project Board will issue to authorities the
    results of the evaluations and improvements plans
  • Authorities will then have the information to
    make decisions

33
Procurement evaluations
  • Current advice to LAs
  • Market development is occurring but has been
    slower than expected
  • Roll forward and keep options forward where
    possible
  • There will potentially be a new provider in the
    market TEC - in time for Oct 2008

34
LCE Energy Project
  • Discussion around
  • Future Work (cont)

35
Discussion around future work (cont)
  • What has the project helped with?
  • What support do you expect to need over the next
    year?
  • How would you like this support to be delivered?
  • Anything else?

36
LCE Energy Project
  • Wrap up and close

37
Self Assessment Process
  • Identify key players in your authority, including
    energy, procurement and finance
  • Review last years Self Assessment
  • Undertake the Self Assessment
  • Completed self assessments should be returned by
    May 9th to lce.energy_at_haringey.gov.uk