1VCCS SIS V8 Upgrade ProjectDecember 2004
Update
2VCCS SIS V8 Upgrade Project - Working with
PeopleSoft
- PeopleSoft eBusiness Architecture Assessment
- On-site review and assessment completed August 16
26 for Version 7.6 and Version 8 - Recommendations incorporated into Technology
Architecture plan - PeopleSoft Upgrade Lab assessment and upgrade
preparation - Completed August 23 September 24
- Reports and analysis reviewed and completed by
ITS staff - PeopleSoft Project planning and Independent
Validation and Verification - Completed September 20 24
- Upgrade project plan and project charter based on
PeopleSoft COMPASS methodology published - Completed initial IVV review of planning and
project charter, fit/gap functional requirements
and specifications, and Design - PeopleSoft certified Version 8 Demo install
- Completed September 27 - 30
- Hands-on training and knowledge transfer to ITS
staff - PeopleSoft Upgrade Lab on-site install
- Completed October 12 through November 5th
3PeopleSoft Upgrade Lab review of VCCS 7.6
Production Database August / September 2004
4PeopleSoft Upgrade Lab review of VCCS 7.6
Production DatabaseAugust / September 2004
5PeopleSoft Upgrade Lab review of VCCS 7.6
Production DatabaseAugust / September 2004
- Almost all modifications to objects are well
documented. Most are minor in nature. Also good
naming conventions were used for custom added
objects. - The changes to records and record fields are
minor in nature. These modifications can be
carried forward. - Most of the modifications are well commented. A
few undocumented changes could be the result of
applying fixes. Reapplying customizations will be
the most challenging part of the upgrade . . .
.. - Most of the modifications are documented and
consist mostly of additional fields. Three
modified panels are not documented. - Minor modifications were made to the PeopleSoft
panel groups and all but two are documented. All
of these modifications can be carried forward
where possible. - Very minor field changes were made and are
documented. Most of the modifications consisted
of changes in description changes for translate
modifications. All field changes can be carried
forward. - Most of the changes to the PeopleSoft delivered
translate values exist because of inactive
setting changes. These changes will be carried
forward. - No indexes were modified.
-
6VCCS SIS V8 Upgrade Project PeopleSoft Compass
Methodology
- Phases Strategy, Planning, Structure,
Construct, Transition, - Deploy
- Activities major sections of a Phase,
consisting of Steps that - conclude in a project
deliverable or milestone - Steps similar tasks that are part of
an Activity - Application specific information includes table
setup sequences, - application features,
integration detail, and - application-specific
tasks
Scalable
7VCCS SIS V8 Upgrade Project PeopleSoft Compass
Methodology
- Strategy Phase
- Usually pre-sales
- Planning Phase
- Includes the Upgrade Planning Technology
Assessment Packaged Services - Structure Phase
- Includes detailed implementation planning,
specifically defining requirements and developing
a project charter, fit/gap analysis, and
functional specs
- Construct Phase
- Includes designing, building, and initial testing
of the PeopleSoft system - Transition Phase
- Includes System Test, other testing activities,
and getting ready for Production (Production
Readiness) - Deploy Phase
- Includes go-live and production support
8VCCS SIS V8 Upgrade Project Plan Summary as of
November 22, 2004
- VCCS SIS Version 8 Upgrade Project (Compass
Methodology) Sun 8/15/04 Fri 6/10/05 57 - Structure Phase Sun 8/15/04 Mon 4/11/05 99
- Planning and Project Charter Sun 8/15/04 Sat
11/20/04 99 - Delta Fit/Gap Functional Requirements and
Specifications Sun 8/15/04 Mon 4/11/05 98 - Close Structure Phase Thu 10/21/04 Thu
10/21/04 0 - Construct Phase Sun 8/15/04 Tue 1/11/05 44
- Design Sun 8/15/04 Thu 11/18/04 91
- Build and Test Sun 8/15/04 Tue 1/11/05 24
- Close Construct Phase Tue 1/11/05 Tue
1/11/05 0 - Transition Phase Sun 8/15/04 Fri 2/25/05 5
- Build Comprehensive Technical Architecture for
Production Mon 12/6/04 Mon 1/10/05 0 - Perform Test Move to Production 2 Fri
12/10/04 Fri 1/14/05 0 - System Test Sun 8/15/04 Fri 2/4/05 3
- Perform Test Move to Production 3 Fri
1/14/05 Fri 1/28/05 0 - Production Readiness Sun 8/15/04 Fri
2/25/05 7 - Close Transition Phase Fri 2/25/05 Fri
2/25/05 0
9VCCS SIS V8 Upgrade Project Plan Moves to
Production
- First Test Move to Production
- October 6th through November 5th
- 23 days 8 hours 184 hours
- Go-Live / Move to Production
- March 1st _at_ 600pm through March 7th _at_ 600am
- 5.5 days 24 hours 132 hours
- 1st Test Move to Production created from October
5th Production backup - 2nd Test Move to Production created from
November 10th Production backup - Time savings already realized through hardware,
database and script changes - 1st Test Move to Production data conversion steps
took 33.7 processing hours - 2nd Test Move to Production data conversion steps
took 13.9 processing hours
10VCCS SIS V8 Upgrade Project Test Plans
- Rik Gillette - Test Coordinator
- Validation testing
- completed the week of November 8th
- involving 18 representatives from 12 colleges
- Functional testing
- Completed November 15th through December 3rd
- Involving 53 representatives from 19 colleges
- College User Testing
- Scheduled for mid-December through mid-February
- College designated testing teams and scenarios
- Performance / Stress Testing
- Scheduled for January 2005
- Using automated testing tools and ITS / College
developed scripts
11VCCS SIS V8 Upgrade Project Training Plans
- Jeff Mitchell named as Training Coordinator
- Training focus
- Delta Training - PeopleSoft instruction on
changes in the Version 8 SA products - Workshops - Demonstrations and instruction on the
new VCCS SIS - User Productivity Kit - End-user documentation
and automated training materials development - Additional Training - Alternative training
options to meet specific college needs - Regional Core Module Workshops
- December 6th, Paul D. Camp Community College
- December 14th, Greenfield Education and Training
Center - Break out sessions on the following topics
- Version 8 Admissions/Academic Advising/Student
Records - Sue Cooley (LFCC), Cathy Barker
(BRCC), Kathy Harcum (VCCS) - Version 8 Student Financials - Myra Maiorana
(TCC), John Thornburg (TCC), Linda Silver (VCCS),
Rik Gillette (VCCS) - Version 8 Financial Aid - Cathy Swain (VWCC),
Janet Rathbun (VWCC), Kathy Camper (VCCS) - Version 8 Query/Reports - Misty Coles (VCCS)
- Version 8 SIS Support - Imad Abi-Falah (VCCS),
Annette Sherrill (VCCS), Jeff Mitchell (VCCS) - User Productivity Kit
12VCCS SIS V8 Upgrade Project Security Update
- All existing security related data (logon ids,
passwords, security classes, and the model
operator identifiers) will be automatically
recreated under PeopleTools V8. - College Roles and Responsibilities during
Migration - Review the security classes and model operator
ids. - Request deletion of model operator ids not
currently active or assigned to an active user. - Request deletion of all unnecessary security
classes. - VCCS Information Security Officer
- Create all roles used.
- Distribute a list of roles and permission lists
assigned to each role. - Make the necessary changes to security classes
and model operator ids in PS 7.6 - College Information Security Officer or person(s)
fulfilling that role - Review the roles to make sure they are the
equivalent of the existing model operator ids. - Submit any changes to permission list or model
operator ids - Test every model operator id
- Other Version 8 Tasks
- Completed an audio conference in late October to
review the security plan and migration strategy.
13VCCS SIS V8 Upgrade Project Query / Reports /
Mass Change Update
- Misty Coles is coordinating the Query / Reports /
Mass Change review projects. - Over 4,000 college queries currently exist.
- Many are no longer used or are duplicates of
other queries. - Use different strategies and table sources to
report data - inconsistent results - Opportunity to convert existing queries into
Version 8 is consistent with PeopleSoft best
practices - Develop a pool of common queries and reports for
use in PeopleSoft Version 8 - Create and maintain a searchable query catalog so
users may easily locate a query to meet their
needs. - Cataloging existing reports and mass changes
being used by colleges - Reports submitted by BRCC, CVCC, GCC, JSRCC,
JTCC, MECC, NVCC, PDCCC, RCC, SVCC, TCC, VWCC - Mass Changes submitted by JTCC, MECC, PDCCC,
SWCC, TCC, VWCC - Project websites developed and released through
VCCS Discuss - track the project progress,
- see the outcome of the review for each query
described, - See the selection of a model query as a guide
for development in version 8,
14VCCS SIS V8 Upgrade Project More Information
Outages - Hours - Privacy Use - Search - Site
MapPeopleSoft 8 - Performance - System Office -
VCCS Colleges - Webmaster
- Version 8 Upgrade Project Website -
http//helpnet.utility.vccs.edu/ASC/Psoft/PSoft8/
Psoft8menu.htm - The VCCS initial version will be SAS V8 SP1 and
PeopleTools 8.20.13. All released updates and
fixes for SP1 will be applied. - Client Services Version 8 Communications
- SIS V8 Updates from the Vice Chancellor
- SIS V8 Training Center
- Security Presentation Differences in PS 7.6
and PS 8 Security" - V8 Upgrade Training Strategy
- Technology Council Powerpoint Presentation
10-7-04 - http//peoplesoft8vanilla.vccs.edu
- PeopleSoft SIS Version8 Demonstration Database
- Version 8 Student Administration Upgrade Project
Plan Task List - Task Excel version MS Project version
- High Level Testing Scenarios for PeopleSoft 8
- Version 8 Student Administration Upgrade Project
High Level Task List - Version 8 Student Administration Upgrade Project
Plan - College Specific Tasks List - Version 8 Student Administration Upgrade Project
Charter - Query Migration Site