2LTU Computing Resources
People Dick Greenwood Institutional Rep. Joe
Steele Researched/researching LHC Grid analysis
tools (ADA, ARDA, etc.), D0SAR representative in
data reprocessing group, Certifying data file
merging for all of D0's remote reprocessing
farms,Updating SamGrid documentation. Kshitij
Limaye High Availability Computing research
(with Box) system manager. Sunitha Polam CS
Grad. Student gt graduated Michael Bryant former
system manager gt will help run farm
3Personnel Using LaTech IAC (CAPS) Linux
Cluster
- At present
- D0 Group
- Lee Sawyer, Dick Greenwood (IAC Rep.), Joe
Steele, - Julie Torborg
- Jefferson Lab Group (G0, Qweak Experiments)
- Kathleen Johnston, Neven Simicevic, Steve Wells,
Tony Forest - Other users
- Box Leansuksan, LaTech CS
4CAPS CLUSTER
5D0SAR MC Delivery Stat. (as of 3/28)
Presently running a 200,000 event request.
Still changing to SamGrid/Runjob
6LTU Plans
- Small site should continue taking MC production
requests - Participate in the development of the Louisiana
Optical Network Initiative (LONI) with its
10GB/sec connectivity to the National Lambda
Rail. - The NLR POP in Baton Rouge has not been affected
(the route runs from Baton Rouge to Houston). - The core routers will be delivered to each
campus as soon as they are ready. - The awarding of the local loops seems to be the
bottleneck with all of the purchasing/bid
requirements. - HSC-NO data center is located at the Public
Safety office (BR?) - Tulane data center is located in Houston.
- UNO data center is at LSU.
7Status of CAPS Site
- Caps Mostly recovered from (premature)
installation sam v6 products. Had to retailor - all samgrid products. Had issue (again) with
disks declared as INACTIVE. - Problem had to do with mixed case nature of
domain name(Latech.edu vice latech.edu) - Found workaround to this problem by digging into
the Samshifter FAQ's. - At present I am about finished getting an upgrade
to condor installed on all machines (windys
still not done). - Also recovering from loss of an /apps/ disk
8Status of SuperMike Site
- LTU (at supermike). Will use on machine with sam
station and gatekeeper combined. - Installed an additional 200 G on this machine