Title: Safety Acceptance criteria in structural codes: a critical review
1Safety Acceptance criteria in structural codes a
critical review
D. Diamantidis, University
of Applied Sciences,
Regensburg, Germany
2OUTLINE
- I Introduction
- II General risk acceptance criteria
- III Developments in current standards
- IV Reflection of experience
- V Conclusions
3 The oldest rule Hammourabi code, Babylone,
1728-1686 BC
Rule 229 If a builder build a house for some
one, and does not construct it properly, and the
house which he built fall in and kill its owner,
then that builder shall be put to death.
4Failure Causes
Design
Execution
Use
Other
Origin
2
0
5
0
15
15
Errors due to human activity
Actions
Causes
80
20
5II General Risk Acceptance Criteria
- Human Safety (Societal Risk - ALARP)
- Calibration
- Optimization (including human life - LQI)
6ALARP Risk Acceptance Criteria(societal risk)
7Hazard probability levels
8Hazard severity levels
9Risk Acceptability Matrixfor risk
verificationAL Allowable NAL Not
AllowableALARP As Low As Reasonably Practicable
10Example tunnel structure
11II General Risk Acceptance Criteria
- Human Safety (Societal Risk - ALARP)
- Calibration
- Optimization (including human life - LQI)
12Domains of experienced fatalities
13Relation between Failure Probability pf and
Reliability Index ?
Calibration through computation of ? values for
various member types (piles, columns, beams etc.
inherent in the codes)
14Example dikes in Netherlands (Vrouwenvelder)
15II General Risk Acceptance Criteria
- Human Safety (Societal Risk - ALARP)
- Calibration
- Optimization (including human life - LQI)
16Cost evaluation including loss of human life
Life Quality Index (LQI)
- LQI gw e (1-w)
- g the gross domestic product per person per
year - e the life expectancy at birth
- w the proportion of life spent in economic
activity.
17ICAF Implied cost of averting a fatality
- Dgmax g/2 (1-w)/(w)
- g gross domestic product
- per year per person
- e life expectancy at birth
- w proportion of life spent in
- economic activity
- ICAF ge/4 (1-w)/(w)
- ICAF 2 5 Mio.
18Optimization criterion
- Costs
- Annualised investment costs
- Annual maintenance/operation costs
- Benefits
- Human risk reduction
- Direct/Indirect financial loss reduction
19III Developments in current Standards
- Limit State Design
- Partial safety factor format (Eurocodes)
- LRFD format (ACI)
- Checks at member level
- Performance Based Design
- FEMA, ASCE, ATC, NZBC
- Overall check of the structure under
- extreme loads (earthquake, blast, fire)
20Limit State Design
21Target Reliability (1 year ref. Period)new
structures, ULS, component level
Consequences
Cost of safety
Background Eurocodes, JCSS, 2001
22JCSS (2001) proposal for existing structures
ßE ßN ?ß ßE
target reliability index for an existing
structure ßN target reliability index for
a new structure ?ß reduction factor
23Performance Based Design PBD
- Loma Prieta earthquake,
- October 17, 1989
- Oakland, California
- Magnitude 6.9
-
24Performance objectives
25EQ Probability levels
26Performance Based Design
Hazard Levels
Performance
Levels
Commonly selected performance objectives
27PBD criteria
- pE . pNPE lt pT
- pE propability of event
- pNPEconditional probability of no
- performance given event
- pT acceptable probability
28PBD criteria (new structure)
- pE . pNPE lt pT
- pE 2 in 50 years
- pNPE 10
- pT 4x10-5 per year
29PBD criteria (old structure)
- pE . pNPE lt pT
- pE 4 in 50 years
- pNPE25
- pT 2x10-4 per year (5 times larger)
30IV Reflections (experience)
- Code committee work on safety targets (FIB, JCSS,
ISO) for normal structures - Safety acceptance criteria for special structures
(tunnels, offshore, etc.) - Safety acceptance criteria for various existing
structures (buildings, bridges, tunnels, offshore
structures)
31Sydney Cross City tunnel Resistance
considerations
- Fibers improve
- local resistance
- fire resistance
32Resistance safety factor ?R for fiber reinforced
shotcrete
?R
- Large consequences of failure(ß4,3 ) ?R 1,50
Moderate consequences of failure(ß3.8 ) ?R 1,35
ß
ß
ß
Minor consequences of failure(ß3.3 ) ?R 1,20
Vr
0,18
33Messina straits, submerged floating
tunnel(Preliminary design, 1987 1993)
Buoyant concrete structure 30m under water Cross
section alternative 42.5mx24m Anchorage system
four inclined steel anchors Progressive collapse
due to failure of tethers (similar to TLP
platforms) Acceptable system failure 10-6 per year
34Existing buidings in Germany
- Office building
- Concrete construction
- 70 years old
- Safety standards not satisfied
- Safety acceptance under reduced load
35V Conclusions
1) Failure records indicate in general
satisfactory safety level in standards 2) Risk
acceptance in codes are usually specified for
component failures (ULS) 3) Performance Based
Design can be used to investigate global failure
in case of extreme loads (earthquake, blast) 4)
Lower safety levels for existing structures are
acceptable compared to new ones 5) Need for a)
harmonization b) safety class
differentiation c) robustness
criteria gt Risk based rules